BLAENAU GWENT COUNTY BOROUGH COUNCIL
Report to: Planning, Regulatory & General Licensing Committee
Report Subject: Potential DNS Schemes for Wind Farms
Report Author: Team Manager Development Management
Directorate: Regeneration and Community Services
Date of meeting: 12th October 2021
1.0Purpose of Report 1.1 Members may be aware of that The Council has recently been consulted by Welsh Government (via The Planning Inspectorate) in respect of four Scoping Directions which have been submitted to them in relation to wind farms at: - Mynydd Carn-y-Cefn (DNS/3272424) - Mynydd Llanhilleth (DNS/3273368) - Maenmoel (DNS/3239181); and - Abertillery (DNS/3278009).
1.2Details of the Scoping Request can be found at https://dns.planninginspectorate.gov.uk/projects/. A request for a Scoping Direction is not a planning application, it is a process whereby it is formally agreed what information will be included in an Environmental Impact Assessment which will accompany any future planning applications submitted to the Welsh Government.
1.3The Council is not the developer nor is it the landowner. We have no part in the development of any of these projects nor are we a partner. Report author: Steve Smith Date: October 2021
1.4It is important to note that not all planning applications are submitted to the Council. Any scheme for renewable energy that generates above 10 Megawatts is called a 'Development of National Significance (DNS)'. These schemes are submitted to Welsh Government to be decided by an independent Planning Inspector. All of these schemes as currently presented to Welsh Government will be DNS so the deciding body will not be Blaenau Gwent. However the Council will be formally consulted on any subsequent planning applications.
1.5This report is to make Members aware of the locations and scale of each project that the Council may be formally consulted on in the near future. It will also enable Members to answer any queries form constituents as these schemes are public.
2.0Background & Context 2.1 Below is a map which identifies the location of each site, a brief description of each site and what the proposal may include.
2.2
Manmoel Wind Farm 2.3 The site is situated mostly within the Blaenau Gwent County Borough Council (BGCBC) area, although its south-western corner lies within the Caerphilly County Borough Council (CCBC) Report author: Steve Smith Date: October 2021
local authority boundary. The southern half of the site is in one of the Future Wales - Pre-assessed Areas (FWPAA). The site lies within registered Commons Land.
The draft proposal includes: • up to 5 turbines of up to 180m maximum tip height and associated crane hardstandings; • transformers housed adjacent to or in turbines; • onsite access tracks plus underground cable runs alongside; • an onsite sub-station building; • construction compound(s); borrow pits; and • access into the site boundary.
Mynydd Carn y Cefn 2.4 The site lies within the Blaenau Gwent County Borough Council administrative area and its boundary is located approximately 500m from the western edge of Abertillery. The eastern section of the site is separated from the town’s western boundary by a 200- 300m buffer of mature trees. The Site is accessed from a forestry haul road which is taken off the A4046 Aberbeeg Road.
The proposed development site compromises a mix of semi- improved and unimproved grassland which forms the southern end of a forked upland ridge between the Ebbw Fawr valley and the Ebbw Fach valley. The site is split by a forestry haul road, woodland and an operational solar farm.
The draft proposal includes: • up to eight wind turbines with heights to blade tip in a range of between 170-180m and a combined maximum rated output of up to 48MW of electrical power; • substation and transformer housing; • temporary construction compound; • temporary site offices; • crane pads and cabling; and • access track construction.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Potential DNS Schemes for Wind FarmsReport | 292 KB | DownloadRead as text |
Follow Planning, Regulatory & General Licensing Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2022 | Planning Applications ReportRESOLVED that planning permission be REFUSED. Application No. C/2022/0047 7 Beaufort Terrace, Beaufort, Ebbw Vale, NP... | Refused | Open |
| 16 Jun 2022 | Appeals, Consultation and DNS Update - June 2022RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
| 16 Jun 2022 | List of Applications decided Under Delegated Powers Between 17th February, 2022 and 30th May, 2022RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
| 3 Mar 2022 | Planning Applications ReportRESOLVED that planning permission be APPROVED. The Chair did not take part in the vote. C/2021/0386 Land to Southern ... | Approved | Open |
| 3 Mar 2022 | Application: C/2021/0253 Premier Club, William Street, Cwm, Ebbw ValeRESOLVED that the report be accepted and the inclusion of the following conditions on the planning permission to be i... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.