Resolved
RESOLVED that the report be accepted. (Option 1)
Cabinet decided this item on Wednesday 10 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be accepted. (Option 1)
Cabinet and Council only Date signed off by the Monitoring Officer: 14.12.23 Date signed off by the Section 151 Officer: 14.12.23
Committee: Cabinet Date of meeting: 10th January 2024 Report Subject: Disabled Facilities Adaptations (DFG’s) – Quarter 2 – Budget and Performance Monitoring Report Portfolio Holder: Cllr Helen Cunningham, Deputy Leader / Cabinet Member Place and Environment Report Submitted by: Mark Congreve, Team Manager – Housing Solutions
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Scrutiny Cabinet Council Other Management Leadership Holder / & Audit Services Committee (please Team Team Chair Committee Committee state) 07.11.23 09.11.23 06.12.23 05.12.23 10.01.24
1. Purpose of the Report 1.1 The purpose of this report is to provide a brief update on progress and current spend against the DFG Capital Budget and Enable funding at the end of Quarter 2 - 2023-24. The report also updates on other relevant matters – staffing pressures and the statutory performance indicator relating to disabled facilities grants (DFG) delivery times.
2. Scope and Background 2.1 On the 16th March 2022 a decision was made by the Executive Committee to remove the means test (Appendix 4) for disabled facilitates adaptions grants (Visit here for full report – item 7). This decision was based on the understanding that this would improve access to adaptations for people who need them, reduce grant delivery times, improve health outcomes, and save money in health and social care. However, recognising that the impact of this policy change would need to be closely ‘monitored’ to assess the potential consequences this could have on service delivery and capital costs, as this could drive up demand, and result in an increase in applications from people who would not previously have applied or been eligible for an adaptations grant or those people who cancelled their applications due to needing to provide a contribution to the cost of the adaptation works.
2.2Therefore, in line with the monitoring arrangements, the position as of the 30th September 2023 (end Q2) is as follows: 2.2.1 Capital Budget 23/24
Medium/Large adaptations £ £ DFG Capital Programme & ENABLE Grant 446,386 Uplift Carry Forward from 2022/23 262,756 ENABLE Grant (via Care & Repair) 92,800 Housing Care Fund (grants over 36k) 96,260 Housing Care Fund (top up funding) 112,000 Total 1,010,202
Expenditure 23/24 Q2 £ Q4 end £ forecast £ Capital Budget 385,684 815,661 ENABLE Grant (via Care & 59,022 92,800 Repair) Total 444,706 908,461 Carry forward to 24/25 101,741
Forecast Budget 24/25
Medium/Large adaptations £ £ Forecast Carry Forward from 23/24 101,741 DFG Capital Programme 24/25 (& Enable 446,386 Uplift ENABLE Grant (via Care & Repair) 92,800 Housing Care Fund (top up funding) 112,000 Total 752,927
Estimated Expenditure 24/25 £ £ DFG & Enable Grant Uplift (excludes HCF - 812,201 grants over 36k) ENABLE Grant 92,800 Total 905,001
Key Points:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 93 KB | Download |
PDF |
Appendix 2Appendix 2 | 56 KB | Download |
PDF |
Appendix 3Appendix 3 | 62 KB | Download |
PDF |
Appendix 4Appendix 4 | 69 KB | Download |
PDF |
Disabled Facilities Adaptations (DFG’s): Quarter 2: Budget and Performance Monitoring ReportReport | 181 KB | DownloadRead as text |
Follow Cabinet at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | CabinetRESOLVED that the decisions be accepted as a true record of proceedings. | Decided | Open |
| 7 Sep 2026 | Conferences, Courses and InvitationsRESOLVED that approval be granted for 1 Member to attend each Conference. | Approved | Open |
| 7 Sep 2026 | Cabinet Forward Work Programme -19th October 2026RESOLVED that the report be accepted and the Forward Work Programme for the October Cabinet meeting be agreed. | Agreed | Open |
| 7 Sep 2026 | Annual Corporate Safeguarding Report 2025/26RESOLVED that the Annual Corporate Safeguarding Report 2025/26 be accepted as presented. | Decided | Open |
| 7 Sep 2026 | Establishment of a Gwent-Wide Social Care Workforce Development ServiceRESOLVED that the report be accepted and Cabinet approves Blaenau Gwent County Borough Council’s participation in the... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.