External Quality Assessment Action Plan

Noted Finance 2 papers

Governance & Audit Committee noted this item on Wednesday 17 January 2024. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that the report be accepted and the Governance & Audit Committee considered the action plan developed in response to the findings from the EQA, attached at Appendix A & B, and noted the progress made.
Word for word from the decision Blaenau Gwent published for this meeting. Source: democracy.blaenau-gwent.gov.uk

Follow this further

Built from Blaenau Gwent's papers

What the report saysPro

Report to Governance & Audit Committee

Purpose of the report

The purpose of this report is to present to the Governance & Audit Committee the progress made against the action plan from the External Quality Assessment (EQA) of the Internal Audit Service.

2. Scope and Background

2.1The Internal Audit Service work in accordance with the Public Sector Internal Audit Standards (PSIAS). The standards ensure an internal audit service that is effective, meets the needs of an organisation, adds value and assists the organisation in meeting its objectives.

2.2As part of the standards, there is a requirement for the service to undergo an external assessment at least once every five years. The assessment is to be conducted by a suitably qualified, independent assessor from outside of the organisation.

2.3The last EQA was conducted in 2022 with the final report and action plan being presented to this committee in January 2023. The action plan has been updated to show the current status of each of the actions identified.

Recommendation

3.1The Governance & Audit Committee consider the action plan developed in response to the findings from the EQA, attached at Appendix A & B, and note the progress made. 4. Evidence of how this topic support the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan

4.1In line with the Corporate Plan Priority of an ambitious and innovative council delivering quality services at the right time and in the right place, presentation of progress made against the Internal Audit EQA action plan demonstrates the professionalism and competency of the service. In doing this it also supports the Chief Officer – Resources in satisfying her statutory duties under Section 151 of the Local Government Act (1972) in providing an effective Internal Audit Service.

4.2The Governance & Audit Committee, in their role as those responsible for governance, and in compliance with the PSIAS, have a responsibility to oversee the performance of the Internal Audit function. The EQA provides an external independent view of the performance of the service, and progress made against the action plan shows the service’s commitment to ongoing improvement.

5. Implications Against Each Option

5.1Impact on Budget (short- and long-term impact) Completion of the EQA action plan does not have any financial implications other than officer time.

5.2Risk including Mitigating Actions Failure to address any non-compliance issues identified in the action plan is a missed opportunity to improve the service.

5.3Legal Provision of an adequate internal audit service, demonstrated in part through an External Quality Assessment, contributes to the Section 151 officer being able to fulfil her statutory duties under the Local Government Act (1972).

5.4Human Resources The EQA involves the investment of officer time. The commitment is met from existing resources.

6. Supporting Evidence

6.1Performance Information and Data From the 304 best practice requirements within the PSIAS, it was found that Blaenau Gwent conformed to 267 of them, a further 30 were considered not applicable, 6 had partial conformance and 1 was a non-conformance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 88 KB Download
PDF
External Quality Assessment Action PlanReport 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 19 attended
JA
Joanne AbsalomChair, present
SB
Councillor Sonia BehrVice-Chair, present
DB
Councillor Derrick BevanCommittee Member, apologies
KC
Councillor Keith ChaplinCommittee Member, apologies
WH
Councillor Wayne HodginsCommittee Member, apologies
CS
Councillor Chris SmithCommittee Member, present
JW
Councillor Joanna WilkinsCommittee Member, present
MV
Martin VealeCommittee Member, present
CH
Cheryl HuckerCommittee Member, present
RH
Rhian HaydenOfficer, present
LR
Louise RosserOfficer, present
BE
Bernadette EliasOfficer, present

All 19 on the meeting page

On this subject at Blaenau Gwent

Search all
  1. External Quality Assessment Action PlanThis decision
  2. External Quality Assessment Action PlanNoted
  3. External Quality Assessment of Blaenau Gwent Internal Audit ServicesAgreed

More from Blaenau Gwent Governance & Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. Decided Open
20 Jul 2026 Action SheetRESOLVED that the Action sheet be noted. Noted Open
20 Jul 2026 Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. Decided Open
20 Jul 2026 Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... Decided Open
20 Jul 2026 Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies