Draft Annual Governance Statement 2024/25

Decided Finance 2 papers

AI summaryBlaenau Gwent Governance and Audit Committee asks for changes to the draft Annual Governance Statement 2024/25 before final approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee to propose amendments to draft AGS
MoneyNoneNo direct financial implications from producing the AGS
What happens nextAmendments to draft AGSFuture AGS will report on progress
Who it affectsCouncil governance frameworkAssessment covers April 2024 to October 2025

What was decided

The committee accepted the report and endorsed Option 2, so proposed amendments and alterations will be made to the draft Annual Governance Statement 2024/25. Report P11

Why

The AGS is a statutory requirement under the Accounts and Audit Regulations (Wales) 2014 and must accompany the Statement of Accounts. Report 4.2, 2.3

It is built on CIPFA and Solace's Delivering Good Governance in Local Government Framework (2016) and drawn from internal and external regulatory reports, performance data and Senior Manager Assurance Statements. Report 2.2, 2.5

The committee acts as those charged with governance, so it needs to be sure the statement matches its understanding of the wider issues affecting the council. Report 2.4, P11

What happens next

Officers will make the committee's proposed amendments and alterations to the draft AGS 2024/25. Report P11

Recommendations for development set out in the AGS will be carried forward and progress reported through future years' statements. Report 6.4, P27

Options considered

  • Rejected: Option 1: Approve the draft AGS 2024/25 as presented, after considering and challenging the content.. The committee instead chose to propose changes to ensure consistency with its understanding. Report P10, P11
  • Chosen: Option 2: Propose amendments or alterations to the draft AGS 2024/25. Report P11

Implications

  • Legal: Both options comply with the Accounts and Audit Regulations (Wales) 2014; no direct legal implications arise from producing the AGS. Report 5.2, 5.3, 4.2
  • Financial: No direct financial implications arise from producing the AGS.
  • Staffing: Senior Management time is invested from across the authority, met from within existing resources. Report 5.4, 6.7
  • Risk: The two options are presented as compliant with regulatory requirements, with mitigating actions covered by the governance framework. Report 5.2, 6.5
  • Other: No Integrated Impact Assessment is required, and there is no direct impact on decarbonisation or carbon emissions. Report 6.8, 6.9

Who and where

  • Members of the Governance and Audit Committee, as those charged with governance Report 2.4
  • Senior managers across all council directorates who contribute to the AGS Report 5.4, 6.3, 6.7
  • Residents and partners, including the Blaenau Gwent Public Service Board Report 6.2, 6.6

Timeline

  • April 2024 to October 2025: Period covered by the draft AGS, because of the timing of previous presentation alongside the Statement of Accounts. Report 1.2
  • 17th November 2025: Date of the Governance and Audit Committee meeting that considered the draft AGS. Report P2, P3

Plain English for the jargon

  • AGS: Annual Governance Statement, the council's yearly assessment of its governance arrangements.
  • CIPFA / Solace Framework (2016): Delivering Good Governance in Local Government: Framework, the standard used to build the AGS.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED, subject to the foregoing, that the report be accepted and Option 2 be endorsed, namely that the Governance & Audit Committee proposed amendments / alterations be made to the draft AGS 2024/25.
Word for word from the decision Blaenau Gwent published for this meeting. Source: democracy.blaenau-gwent.gov.uk

Follow this further

Built from Blaenau Gwent's papers

What the report saysPro

Report to Governance & Audit Committee

Cabinet and Council only Date signed off by the Monitoring Officer: Date signed off by the Section 151 Officer:

Committee: Governance and Audit Committee Date of meeting: 17th November 2025 Report Subject: Draft Annual Governance Statement 2024/25 Portfolio Holder: Leader / Cabinet Member Corporate Resources Report Submitted by: Service Manager Performance and Democratic

Reporting Pathway Joint Leadership Portfolio Governance Democratic Scrutiny Cabinet Council Other Executive Team Holder / and Audit Services Committee (please Team Chair Committee Committee state) 17/11/2025

1. Purpose of the Report 1.1 To present the Governance and Audit Committee with the Draft Annual Governance Statement (AGS) for 2024/25 (attached at Appendix 1).

1.2Owing to the timing of previously presenting the AGS alongside the Statement of Accounts, the information contained within the Statement includes information between April 2024 up to October 2025. 2. Scope and Background 2.1 The report provides the AGS covering the period 2024/25 (including the note at 1.2), providing a retrospective assessment of the effectiveness of the Authority’s governance arrangements.

2.2The AGS is developed using CIPFA/Solace’s Delivering Good Governance in Local Government: Framework (2016). Welsh Government anticipates that relevant bodies will prepare an annual governance statement on internal control using the CIPFA/Solace Framework to best represent proper practices in relation to the statement on internal control which requires an annual governance statement to be produced.

2.3As best practice CIPFA recommends that: • a full version of the AGS should accompany the statement of accounts; and • the AGS should be approved by members meeting as a whole committee at the same time as the statement of accounts is approved under Regulation 10(2) in Wales.

2.4Responsibility for reviewing the AGS has been delegated to the Governance and Audit Committee as ‘those charged with Governance’.

2.5The statement is collated following evidence gathering exercise which calls upon a number of sources including: • Internal and external regulatory reports; • Annual Report of the Audit and Risk Manager; • Various performance monitoring reporting and information; and • Senior Manager Assurance Statements. Changes made to the 2024/25 report include: • A diagram to show the Core Principles of Good Governance; • An additional section on Independent Assurance; • A list of key resources to provide additional evidence to the information provided against each Core Principle; and • An additional appendix within the report, appendix c, to include the Actions identified from the 2024/25 Annual Governance Statement.

3. Options for Recommendation 3.1 Option 1 For the Governance and Audit Committee to approve the draft AGS 2024/25 having considered and challenged the content, ensuring it is consistent with their knowledge and understanding of the wider issues affecting the Council.

Option 2 For the Governance and Audit Committee to propose amendments / alterations to the draft AGS 2024/25 should it not be consistent with their knowledge and understanding of the wider issues affecting the Council.

4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan

4.1Production of an AGS assists the Authority in achieving its Corporate Plan Priority, ‘An ambitious and innovative council delivering quality services at the right time and in the right place’, by providing an assessment of the governance arrangements in place for Blaenau Gwent CBC.

4.2Production of the AGS is a statutory requirement under the Accounts and Audit Regulations (Wales) 2014 to accompany the Statement of Accounts.

5. Implications Against Each Option 5.1 Impact on Budget (short and long term impact) There are no direct financial implications arising from the production of the AGS.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Annual Governance Statement 2024/25Report 142 KB DownloadRead as text
PDF
Final AGS 24-25 DRAFTReport 1.1 MB Download

At this meeting

Whole meeting

Who was there

15 of 21 attended
CH
Cheryl HuckerChair, apologies
SB
Councillor Sonia BehrVice-Chair, present
JG
Councillor Jules GardnerCommittee Member, absent
JP
Councillor John P. MorganCommittee Member, present
HT
Councillor Haydn TrollopeCommittee Member, present
JW
Councillor Joanna WilkinsCommittee Member, apologies
LW
Councillor Lisa WinnettCommittee Member, present
MV
Martin VealeCommittee Member, present
DA
Debbie AustinCommittee Member, present
RH
Rhian HaydenOfficer, present
LM
Luisa Munro-MorrisOfficer, present
LR
Louise RosserOfficer, present

All 21 on the meeting page

On this subject at Blaenau Gwent

Search all
  1. Draft Annual Governance Statement 2024/25This decision
  2. Final Annual Governance Statement 2024/25Approved
  3. Annual Governance Statement 2023/24Approved
  4. Draft Annual Governance Statement 2023/24Decided
  5. Final Annual Governance Statement 2022/23Approved
  6. Annual Governance StatementDecided

More from Blaenau Gwent Governance & Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. Decided Open
20 Jul 2026 Action SheetRESOLVED that the Action sheet be noted. Noted Open
20 Jul 2026 Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. Decided Open
20 Jul 2026 Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... Decided Open
20 Jul 2026 Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies