Blaenau Gwent County Borough Council and Group – Audit Plan 2025

Noted Finance 1 paper

AI summaryBlaenau Gwent's Governance and Audit Committee noted the Audit Wales Audit Plan 2025, setting out financial and performance audit work for 2024-25 with an estimated total fee of £459,032.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee accepted the report and noted its contents
Money£459,032 estimated total audit feeFor 2024-25 accounts, up from £451,359 actual for 2023-24
What happens nextDraft accounts now expected in 2026Repeated delays have pushed submission of 2024-25 financial statements to 2026
Who it affectsNot stated

What was decided

The committee accepted the Audit Wales Audit Plan 2025 and noted the information it contained.

The plan sets out the audit of the Council's and Group's financial statements for 2024-25, including an opinion on truth and fairness. Report P29, P34

A new auditing standard on the audit of groups will be implemented this year, with a more risk-based approach. Report P15

Why

Audit Wales is required to plan and report on the Council's financial statements and to assess proper arrangements for economy, efficiency and effectiveness. Report P29, P108

Historic problems with the timeliness and quality of the financial statements have increased the risk of material misstatement, requiring extra audit focus. Report P55, P62

Materiality levels are set at £3.166m (planning), £2.374m (performance) and £0.158m (reporting threshold), based on 2023-24 audited figures. Report P44, P46, P48

What happens next

Audit Wales will work with officers to agree a revised realistic timetable for the 2024-25 accounts and audit, which has already been delayed twice. Report P58, P65

Performance audit work is aimed to be substantially completed by the end of June 2026, with focus on workforce pressures, a follow-up of the Planning Service audit, and a possible review of housing adaptations in South East Wales. Report P120, P122, P124

The audit team will keep the Council updated through quarterly liaison meetings as fieldwork progresses between November 2025 and January 2026. Report P104, P124

The money

  • £459,032 Estimated total audit fee for 2024-25 Report P131, P139
  • £284,284 Estimated financial statements audit fee for 2025 Report P138
  • £122,875 Estimated performance audit work fee for 2025 Report P138
  • £51,873 Estimated grant certification work fee for 2025 Report P138
  • £451,359 Total actual fee for 2023-24 Report P143
  • £279,532 Actual financial statements audit fee for 2023-24 Report P142
  • £120,821 Actual performance audit fee for 2023-24 Report P142
  • £51,006 Actual grant certification fee for 2023-24 Report P142
  • £295,155 Original estimated financial audit fee for 2023-24 Report P132
  • 1.7% Average increase to Audit Wales fee rates in 2025-26 Fee Scheme Report P129

Options considered

  • Chosen: Accept and note the Audit Plan 2025

Implications

  • Financial: Higher-than-typical audit fee reflects historic challenges and current delays, with further fee changes possible if elector questions or objections are received. Report P128, P133
  • Risk: Repeated slippage of the draft accounts deadline is described as disappointing, with audit resource shifted twice and a revised timetable still to be agreed. Report P58, P61
  • Legal: Several legal cases could materially affect the valuation of the Local Government Pension Scheme net liability or surplus. Report P74, P77
  • Other: The plan will focus extra attention on the treatment of the Lime Avenue agreement following past issues with the project. Report P91, P92, P94
  • Other: IFRS 16 Leases takes effect from 1 April 2024, changing how most leases are recognised on the balance sheet. Report P95

Who and where

  • Blaenau Gwent County Borough Council as single entity Report P34
  • Bedwellty House and Park Charitable Trust as a group component Report P34
  • Council taxpayers and residents of Blaenau Gwent Report P29, P108

Timeline

  • October to November 2025: Planning stage of financial statements audit, including risk and fraud assessments Report P103
  • November 2025 to October 2026: Period when financial statements audit fee is payable Report P144
  • December 2025: Audit Plan 2025 issued by Audit Wales Report P2
  • November to December 2025: Fieldwork stage of financial statements audit Report P104
  • December 2025 / January 2026: Reporting stage, presentation of findings to those charged with governance Report P105
  • New year (2026): Draft 2024-25 financial statements now expected to be submitted to auditors Report P58
  • By end of June 2026: Performance audit work aimed to be substantially completed Report P124

Plain English for the jargon

  • Materiality: The level of misstatement that could mislead a user of the accounts, used to scope the audit and set sample sizes.
  • ISAs: International Standards on Auditing, the framework setting audit requirements, including ISA 240 on the risk of management override of controls.
  • ISSAI 3000: International Standard for Supreme Audit Institutions performance audit, used by Audit Wales for value-for-money work.
  • IFRS 16 Leases: Accounting standard requiring most leased assets and liabilities to be recognised on the balance sheet, adopted by local government from 1 April 2024.
  • Section 151 Officer: The local authority officer with statutory responsibility for financial administration, who the auditors liaise with on accounts production.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED that the report be accepted and the information contained therein be noted.
Word for word from the decision Blaenau Gwent published for this meeting. Source: democracy.blaenau-gwent.gov.uk

Follow this further

Built from Blaenau Gwent's papers

What the report saysPro

Report to Governance & Audit Committee

Blaenau Gwent County Borough Council and Group – Audit Plan 2025 Audit year: 2024-25

Date issued: December 2025

Document reference: 5164A2025 Blaenau Gwent County Borough Council and Group – Audit Plan 2025

Contents Contents 2 Introduction 4 Our aims and ambitions 5 Financial audit work 6 Performance audit work 15 Other statutory audit functions 18 Audit fee 18 Audit team 20 Audit quality 21 Supporting you 22

2 Blaenau Gwent County Borough Council and Group – Audit Plan 2025

This document has been prepared as part of work performed in accordance with statutory functions.

The Auditor General, Wales Audit Office and staff of the Wales Audit Office accept no liability in respect of any reliance or other use of this document by any member, director, officer or other employee in their individual capacity, or any use by any third party.

For further information, or if you require any of our publications in an alternative format and/or language, please contact us by telephone on 029 2032 0500, or email [email removed].

We welcome correspondence and telephone calls in Welsh and English. Corresponding in Welsh will not lead to delay. Rydym yn croesawu gohebiaeth a galwadau ffôn yn Gymraeg a Saesneg. Ni fydd gohebu yn Gymraeg yn arwain at oedi.

3 Blaenau Gwent County Borough Council and Group – Audit Plan 2025

Introduction

I am pleased to share my 2025 Audit Plan. The Plan sets out how I will undertake your audit.

My audit team has developed the Plan following a structured and risk-based planning process, which will remain ongoing throughout the audit. My Code of Audit Practice provides further detail on how my audit and certain other functions are to be carried out by my auditors. Adrian Crompton At the core of all our work is our commitment to Auditor General maintaining the highest standards of professional for Wales integrity, objectivity, independence and audit quality. Our three lines of assurance model (page 24) sets out how we will ensure those standards of quality are met. Our latest annual quality report, Audit Quality Report 2024, provides more information about our audit quality arrangements.

My audit team will work constructively with your staff to understand the issues you are facing, ensure the audit process operates as smoothly as possible, and provide valuable insights about any areas for improvement.

For this year of audit we are required to implement a new auditing standard on the audit of groups which will see us adopting a more risk- based approach to that work.

My local performance audit work programme, as outlined in this Plan, sits alongside other national audit work that may include coverage of your organisation. Local performance audit work may also inform wider national reporting.

Should you have any questions about your audit my audit team will be happy to discuss them with you. They will also keep you regularly updated as work progresses.

4 Blaenau Gwent County Borough Council and Group – Audit Plan 2025

Our aims and ambitions

Our purpose

Assure people Explain how that that public Inspire the public money is being money is being sector to improve spent managed well

Our vision

Fully exploiting Strengthening our Increasing our Being a model our unique position as an visibility, organisation for perspective, authoritative, influence, and the public sector expertise and trusted and relevance in Wales and depth of insight independent beyond voice

Our areas of focus

A strategic, A targeted and A culture and dynamic, and impactful operating model high-quality audit approach to that enables us to programme communications thrive and influencing

You can find out more about Audit Wales in our Annual Plan 2024-25 and Our Strategy 2022-27.

5 Blaenau Gwent County Borough Council and Group – Audit Plan 2025

Financial audit work

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blaenau Gwent County Borough Council and Group: Audit Plan 2025Report 874 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 19 attended
CH
Cheryl HuckerChair, present
JM
Councillor Jen Morgan, J.P.Vice-Chair, present
JP
Councillor John P. MorganCommittee Member, present
HT
Councillor Haydn TrollopeCommittee Member, apologies
JW
Councillor Joanna WilkinsCommittee Member, apologies
LW
Councillor Lisa WinnettCommittee Member, absent
DW
Councillor Dean WoodsCommittee Member, present
MV
Martin VealeCommittee Member, apologies
DA
Debbie AustinCommittee Member, apologies
RH
Rhian HaydenOfficer, present
LM
Luisa Munro-MorrisOfficer, apologies
LR
Louise RosserOfficer, present

All 19 on the meeting page

On this subject at Blaenau Gwent

Search all
  1. Blaenau Gwent County Borough Council and Group – Audit Plan 2025This decision
  2. Blaenau Gwent Council Corporate Plan Annual Performance Report 2025/2026Noted
  3. Blaenau Gwent CBC Corporate Risk Register - Quarter 4 UpdateNoted
  4. Joint Blaenau Gwent and Torfaen Joint Local Development Plan: Collaboration AgreementAgreed
  5. Blaenau Gwent Resource and Waste Strategy 2026-2031Approved
  6. Blaenau Gwent Council Corporate Plan Annual Performance Report 2025/26Agreed

More from Blaenau Gwent Governance & Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. Decided Open
20 Jul 2026 Action SheetRESOLVED that the Action sheet be noted. Noted Open
20 Jul 2026 Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. Decided Open
20 Jul 2026 Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... Decided Open
20 Jul 2026 Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies