Statement of Accounts Recovery Plan 2025/2026 & 2026/2027

Noted Finance 3 papers

AI summaryGovernance & Audit Committee accepted the Statement of Accounts Recovery Plan 2025/2026, noting an Audit Wales letter flagging late accounts. Revised targets push draft 2025/26 accounts to 31 August 2026, with weekly monitoring and exception updates.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOption 1 accepted: letter noted, plan approved, monitoring endorsed
Money£317,878Actual 2022/23 audit cost, up from £227,878 estimate
What happens nextException reportingWeekly monitoring by Head of Financial Services
Who it affectsCouncil accounts processStatutory accounts production and audit completion

What was decided

The Committee accepted the report and approved the Statement of Accounts Recovery Plan 2025/2026 as the preferred option. Report P14

Members noted the 9 March 2026 letter from Audit Wales on declining timeliness and quality of statutory accounts across Welsh local government. Report P2, 2.1

The Committee endorsed strengthened governance and monitoring arrangements, with further progress updates on an exception basis. Report P14

Why

Audit Wales wrote to all Chief Executives about sector-wide concerns, noting that only 18 of 32 local government bodies (56%) met the 30 June 2025 deadline for 2024-25 accounts. Report 2.1, P5

Blaenau Gwent has a persistent pattern of delays: 2023/24 accounts were certified on 31 July 2025, eight months after the sector deadline, and 2024/25 draft accounts were submitted on 8 February 2026 instead of by 30 September 2025. Report P7

Late and low-quality accounts have driven up audit fees, with the 2022/23 audit costing £317,878 against an estimate of £227,878. Report 2.4, P9, 5.1, P20

What happens next

The Council will work to revised targets: draft 2025/26 accounts by 31 August 2026, with audit completion dates to be agreed with Audit Wales, and a return to the 30 June 2027 statutory deadline for 2026/27 draft accounts. Report P36, P37, P38

The Head of Financial Services will monitor progress weekly, escalating to the GRIPP meeting and the Governance & Audit Committee by exception. Report 7.1, P54

The Recovery Plan sets out eight workstreams covering training, supervision, audit queries, and ongoing engagement with Audit Wales and the Chief Accountants Group. Report P36, P44, P24

The money

  • £227,878 Estimated audit fee for 2022/23 Report 2.4, P9
  • £317,878 Actual 2022/23 audit cost Report 2.4, P9
  • £279,441 Actual audit fee for 2023/24 Report 2.4, P9
  • £284,284 Standard audit fee for the 2024-2025 accounts Report 5.1, P20

Options considered

  • Chosen: Option 1 (Preferred): note the Audit Wales letter, approve the Recovery Plan 2025/2026, endorse strengthened governance and monitoring, and receive further progress updates on an exception basis. Responds to Audit Wales concerns and addresses persistent delays in statutory accounts Report 3.1, P13, P14
  • Rejected: Option 2: do not agree the recommendations in Option 1 Report 3.2, P16

Implications

  • Financial: Late and low-quality accounts and working papers lead to longer audits and higher audit fees compared with the standard fee. Report 5.1, P20
  • Legal: Account preparation, inspection, audit, approval and publication requirements are set by the Public Audit (Wales) Act 2004 and the Accounts and Audit (Wales) Regulations 2014 as amended in 2018. Report 5.3, P26
  • Risk: Key risks include capacity constraints in the Accountancy Team, delays in external information such as valuations and actuarial data, outstanding 2024/25 audit work, and system issues affecting ledger closure. Report 5.2, P22
  • Risk: Mitigations include enhanced training and supervision, regular timetable monitoring with escalation, and ongoing collaboration with Audit Wales. Report 5.2, P23, P24
  • Other: The Council will not meet the June or September 2026 deadlines for 2025/26 accounts, and has set a revised draft accounts target of 31 August 2026. Report P36, P37
  • Equalities: EqIA screening not applicable. Report 6.8, P51
  • Staffing: Human resources implications marked as N/A. Report 5.4, P28

Who and where

  • Blaenau Gwent residents and council taxpayers Report 6.2, P41
  • The Council's Accountancy Team Report 5.2, P22
  • Audit Wales Report 2.5, P11
  • Officers across the Council supporting Statement of Accounts preparation Report P48

Timeline

  • 30 June 2025: Welsh Government statutory deadline for 2024-25 accounts (only 56% of bodies met it) Report 2.1, P5
  • 31 July 2025: 2023/24 accounts certified, eight months after the sector deadline Report P7
  • 30 September 2025: Agreed deadline for 2024/25 draft accounts, missed Report P7
  • 8 February 2026: 2024/25 draft accounts submitted Report P7
  • 9 March 2026: Audit Wales letter received flagging timeliness and quality concerns Report P2
  • 31 August 2026: Revised target for completion of 2025/26 draft accounts Report P37
  • 30 June 2027: Statutory deadline target for 2026/27 draft accounts Report P38
  • 30 September 2027: Target for 2026/27 final accounts, subject to audit Report P38

Plain English for the jargon

  • Statement of Accounts: The Council's annual statutory accounts setting out its financial position, required under the Public Audit (Wales) Act 2004.
  • Audit Wales: The body responsible for auditing Welsh public sector organisations, including local authorities.
  • GRIPP: Governance, Risk, Integrity, Performance and Partnership meeting, an internal council oversight group.
  • Workstreams: The eight structured areas of work set out in the Recovery Plan to deliver the Statement of Accounts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

RESOLVED, subject to the foregoing, that the report be accepted and the following points be noted (Option 1):- • The letter received from Audit Wales and issues raised • Approve the Recovery Plan 2025/2026 • Endorse the strengthened governance and monitoring arrangements
Word for word from the decision Blaenau Gwent published for this meeting. Source: democracy.blaenau-gwent.gov.uk

Follow this further

Built from Blaenau Gwent's papers

What the report saysPro

Report to Governance & Audit Committee

Purpose of the report

1.1The purpose of this report is to:

• Inform the Governance & Audit Committee of the letter received from Audit Wales dated 9 March 2026, relating to the timeliness and quality of the Council’s statutory accounts • Present the Council’s Statement of Accounts Recovery Plan 2025–2026, which has been developed to address the issues raised and to support improvement for the 2025/26 and 2026/2027 financial years • Provide assurance regarding the actions underway to ensure compliance with sector deadlines and expectations for financial governance.

2. Scope and Background

2.1Audit Wales has written to all Chief Executives highlighting sector‑wide concerns about declining timeliness and quality in the production of statutory accounts across Welsh Local Government. The letter, attached at Appendix 1 highlights that:

• Only 18 local government bodies (56%) met the Welsh Government deadline of 30 June 2025 for the 2024-2025 accounts (down from 21 bodies (66%) in 2023-2024 and 22 bodies (68%) in 2022-2023. • By October 2025, only 9 of 22 unitary authorities, 3 of 4 police authorities and 3 of 3 fire authorities were certified on time. No national park authorities were certified by the deadline.

2.2The letter emphasises that high‑quality, timely accounts remain critical to public confidence, governance, and financial sustainability. 2.3 The Committee will be aware of the delays experienced by Blaenau Gwent in recent years, Audit Wales note a persistent pattern of delayed draft accounts and extended audit durations, including:

• 2023/24 accounts certified on 31 July 2025, eight months after the sector deadline; draft accounts were submitted on 8 April 2025. • 2024/25 draft accounts not delivered by the agreed deadline of 30 September 2025; instead submitted on 8 February 2026

2.4These delays have resulted in significant additional audit costs:

• Estimated audit fee 2022/23: £227,878 • Actual 2022/23 audit cost: £317,878 • Actual audit fee 2023/24: £279,441

2.5Audit Wales has therefore asked the Council to implement a realistic, robust and detailed recovery plan for the audit of the 2024/25 accounts and the completion of the 2025/26 accounts and demonstrate how future accounts will meet the sector deadlines.

3. Options for Recommendation

3.1Option 1 (Preferred Option)

3.1.1 The Governance and Audit Committee consider the report and:

• Note the letter received from Audit Wales and issues raised • Approve the Recovery Plan 2025/2026 • Endorse the strengthen governance and monitoring arrangements • Receive further progress updates on an exception basis

3.2Option 2

3.2.1 The Governance and Audit Committee consider the report and do not agree the recommendations detailed in Option 1.

4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan

4.1Timely, high-quality accounts support strong governance, financial resilience, and responsible stewardship of resources, aligning with the Council’s Corporate Plan. . 5. Implications Against Each Option

5.1Impact on Budget (short and long term impact)

5.1.1 Non timey, low quality accounts and working papers can result in the audit of the accounts taking longer to conclude resulting in higher audit fees (see paragraph 2.3) in comparison to the cost of a standard audit. The standard audit fee for the 2024-2025 Accounts is £284,284.

5.2Risk including Mitigating Actions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 144 KB Download
PDF
Appendix 2Appendix 2 78 KB Download
PDF
Statement of Accounts Recovery Plan 2025/2026 & 2026/2027Report 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 19 attended
CH
Cheryl HuckerChair, present
JM
Councillor Jen Morgan, J.P.Vice-Chair, absent
JP
Councillor John P. MorganCommittee Member, absent
HT
Councillor Haydn TrollopeCommittee Member, present
JW
Councillor Joanna WilkinsCommittee Member, present
LW
Councillor Lisa WinnettCommittee Member, present
DW
Councillor Dean WoodsCommittee Member, present
MV
Martin VealeCommittee Member, present
DA
Debbie AustinCommittee Member, present
RH
Rhian HaydenOfficer, present
LM
Luisa Munro-MorrisOfficer, present
LR
Louise RosserOfficer, present

All 19 on the meeting page

On this subject at Blaenau Gwent

Search all
  1. Statement of Accounts Recovery Plan 2025/2026 & 2026/2027This decision
  2. Statement of Accounts 2025/2026 UpdateDecided
  3. Statement of Accounts 2024/2025Agreed
  4. Draft Statement of Accounts 2024/2025Approved
  5. Verbal Update - Draft Statement of Accounts 2024/25Decided
  6. Progress on Statement of Accounts 2024/2025Noted

More from Blaenau Gwent Governance & Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. Decided Open
20 Jul 2026 Action SheetRESOLVED that the Action sheet be noted. Noted Open
20 Jul 2026 Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. Decided Open
20 Jul 2026 Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... Decided Open
20 Jul 2026 Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) Approved Open