Objection Report on the Proposal to Decrease the Capacity at Abertillery Learning Community Primary Phase
DecidedCommittee5 papers
AI summaryBlaenau Gwent Council approves closure of Abertillery Learning Community's Roseheyworth Road Campus from September 2027, cutting primary places from 980 to 710 to save around £2.2 million over five years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedClose Roseheyworth Road Campus by September 2027
Money£2.2 million five-year savingPlus £670,000 annual cost reduction, £100,000 capital works
What happens nextImplementation from September 2027Transition planning to support learners, staff, community
Who it affectsAbertillery Learning Community pupils, staff, parents389 valid objections received during statutory period
What was decided
Council accepted the Objections Report and approved the proposal to reduce primary phase capacity from 980 to 770 places by closing the Roseheyworth Road Campus, with pupils transferring to Six Bells and Tillery Street campuses by September 2027. Report P12, P58
Members acknowledged the strength of opposition but concluded no viable alternative had been identified to address declining pupil numbers, surplus capacity and financial pressures. Report P3, P53
Why
Pupil numbers across the county borough have declined, creating significant surplus capacity and ongoing financial sustainability challenges at the four-campus school. Report 2.2, P8, P9
At the end of 2025/26 the Learning Community had an outturn deficit of £558,000, projected to rise to £1.3m by March 2027 and approximately £3.4m by 2029/30 if no action is taken. Report P33
Professional advice from Estyn and the School Improvement Service indicated the proposal would at least maintain educational standards and support long-term sustainability. Report P10, P54
What happens next
Education will lead implementation through a comprehensive transition plan, with monitoring of attendance, attainment, wellbeing and operational delivery against key performance indicators. Report P50, P51
Minor works costing approximately £100,000 will be carried out across the remaining two campuses, funded from existing maintenance budgets. Report P35
Human Resources, school leadership and Trade Unions will manage staffing changes, prioritising redeployment and natural turnover to minimise compulsory redundancies. Report P43
The money
£2.44 million Council-approved increase to Individual Schools Budget for 2025/26 and 2026/27 Report 4.2
approximately £3 million Cumulative outturn deficit across Blaenau Gwent schools at end of 2025/26 Report P30
£11.1million Total funding for Abertillery Learning Community at end of 2025/26 Report P33
£558,000 Abertillery Learning Community outturn deficit position at end of 2025/26 Report P33
£1.3m Projected Learning Community deficit by 31st March 2027 if no action taken Report P33
approximately £3.4m Projected Learning Community deficit by 2029/30 if no action taken Report P33
approximately £670,000 Estimated annual cost reductions from the proposal Report P34
around £2.2 million Estimated total savings over five years from the proposal Report P34
approximately £100,000 Estimated cost of minor works at remaining campuses Report P35
£30,000 Estimated additional annual home-to-school transport cost Report P36
Options considered
Chosen: Option 1: Accept the Objections Report and implement the proposal to close Roseheyworth Road Campus by September 2027. Considered the most appropriate, proportionate and sustainable response to surplus capacity and financial risks, supported by Estyn and School Improvement Service advice. Report P58, P3, P54
Rejected: Option 2: Do not proceed to implementation and identify alternative options to address the financial deficit. No viable alternative identified; doing nothing would allow the deficit to grow to approximately £3.4m by 2029/30. Report P59, P33
Rejected: Alternative Option 1: Move half of Tillery Street Campus learners to Roseheyworth Campus. Does not resolve declining numbers, surplus capacity or financial sustainability. Report P22, P23
Rejected: Alternative Option 2: Use Roseheyworth Campus for additional training capacity. Primary focus must be statutory education; does not address surplus capacity or financial sustainability. Report P25, P26
Implications
Financial: Annual cost reductions of approximately £670,000 and five-year savings of around £2.2 million, moving the school closer to an in-year balanced budget. Report P34
Financial: Capital works of approximately £100,000 to be funded from existing maintenance budgets; additional transport cost of £30,000 per year. Report P35, P36
Equalities: Risks around Additional Learning Needs provision, vulnerable learners and wellbeing identified, with mitigation including additional pastoral support and retention of friendship groups where possible. Report P19, P45
Legal: Process followed the Welsh Government School Organisation Code (2018) statutory consultation and objection requirements. Report P7, P27, P49
Staffing: Risk of staffing reductions and potential redundancies; mitigation through natural turnover, redeployment and cross-matching, working with HR and Trade Unions. Report P42, P43
Risk: Risks around transport, traffic congestion, pedestrian safety and future capacity pressures identified, with mitigation through transport assessments and contingency planning. Report P39, P40, P46
Other: Community impact and cohesion concerns raised in objections, alongside concerns about consultation process and trust; Council's Integrated Impact Assessment and Community Impact Assessment included as appendices. Report P19, P53, P63, P65
Who and where
Learners at Abertillery Learning Community, particularly those at Roseheyworth Road Campus Report P12, P45
Staff at Abertillery Learning Community, including potential redundancy risk Report P42, P43
Parents, carers and families of pupils Report P49, P50
Wider Abertillery community, including residents raising objections on community cohesion grounds Report P19, P49
Governors, elected members, trade unions and school leadership Report P43, P49
Timeline
March and April 2026: Formal statutory consultation undertaken by Education in accordance with the Welsh Government School Organisation Code Report P7
30th April 2026: Consultation outturn report presented to Cabinet, which agreed to publish the statutory notice Report P11
5 May 2026: Statutory notice published, commencing 28-day objection period Report P13
3 June 2026: Statutory objection period concluded Report P13
07.07.2026: Report signed off by the Monitoring Officer Report P1
08.07.2026: Report signed off by the Section 151 Officer Report P1
15th July 2026: Council meeting considered and approved the Objections Report and proposal Report P2
September 2027: Planned full implementation, with learners transferred to Six Bells and Tillery Street campuses Report P12, P58
Plain English for the jargon
Statutory notice: Formal published notice under the Welsh Government School Organisation Code (2018) triggering a 28-day objection period on a school reorganisation proposal.
Campus: A physical site of a school; Abertillery Learning Community has four campuses, three primary and one secondary.
ALN: Additional Learning Needs, provision for learners with identified needs requiring additional support.
Outturn: The actual financial position at the end of a financial year, as opposed to budgeted figures.
Individual Schools Budget: Funding allocated directly to schools by the local authority, separate from central education services.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
RESOLVED, subject to the foregoing, that the report be accepted and Option 1 be endorsed, namely that the Objections Report, associated documents and course of action, to implement the proposal for September 2027 be accepted. The meeting was paused for a two-minute recess at this juncture in the proceedings.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: Date signed off by the Section 151 Officer:
Committee: Cabinet Date of meeting: 30th April 2026 Report Subject: Outturn Report on the Proposal to Decrease the Capacity at Abertillery Learning Community Primary Phase Portfolio Holder: Cabinet Member Children, Young People & Families Report Submitted by: Head of Resources & Planning, Education
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Scrutiny Cabinet Council Other Management Leadership Holder / Audit Services Committee (please Team Team Chair Committee Committee state) Y 30.04.26
1. Purpose of the Report 1.1 The purpose of this report is to provide a detailed overview of the responses received from the statutory consultation undertaken by Education for the proposal to reduce the capacity of Abertillery Learning Community – Primary Phase, by closing the Roseheyworth Road Campus. The report provides an overview of the consultation:
• Methodology, process; and, • outcome responses including key themes emerging from the responses received
A determination is sought from Cabinet in line with the proposal to proceed to Statutory Notice.
2. Scope and Background 2.1 Consultation Process and Methodology The Welsh Government School Organisation Code – second edition (2018), dictates that proposals must be published for the following elements of school reorganisation:
1. the opening of a maintained school (including a special school). 2. the closing of a maintained school (including a special school). 3. to make a regulated alteration to a maintained school; and, 4. to change the category of a maintained school.
2.2Therefore, the proposal to reduce the capacity at Abertillery Learning Community – Primary Phase must be subject to a formal consultation as the Council is proposing to close Roseheyworth Road Campus reducing Primary Places from its capacity of 980 to 770 pupils from September 2027.
2.3The consultation was initiated and conducted via a formal consultation document and accompanying online survey (Appendix 1) which is compliant with the statutory requirements set out within the aforementioned Code. The purpose of the consultation was to establish the views and opinions of consultees in relation to the proposal.
2.4In accordance with the Welsh Government School Organisation Code, the Authority is required to publish a consultation report (at least 2 weeks prior to the publication of statutory notice) which:
• summarises the issues raised by consultees. • responds to these by means of clarification, amendment to the proposal or rejection of the concerns, with supporting reasons. • sets out Estyn’s response to the consultation in full; and, • responds to Estyn’s response by means of clarification, amendment to the proposal or rejection of the concerns, with supporting reasons.
2.5Formal consultation commenced on Monday 2nd March 2026. The process concluded on Tuesday 14th April 2026. Consultees were asked to provide their views, opinions and feedback via one or more of the following methods:
• attending a pre-arranged virtual or face to face session, to answer any questions and to be signposted to the below, • completion of an on-line survey; and/or, • in writing via the 21st Century Schools email address. 2.6 The Council targeted consultees, as directed by the Welsh Government School Organisation Code, (Appendix 2 for list of consultees). Electronic letters and copies of the document were distributed to:
• Abertillery Learning Community Staff • All parents of Abertillery Learning Community pupils • Abertillery Learning Community Governing Body via the Chair of Governors • All other Headteachers of schools within Blaenau Gwent • Other consultees as detailed within Appendix 2
2.7Information regarding the consultation was shared with:
• Teaching & Non-Teaching Staff of Abertillery Learning Community • Parents/Carers of pupils at Abertillery Learning Community • Wider community groups
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Scrutiny Report 2025-2026RESOLVED that the report be accepted and - the ‘scrutiny activity’ that had been undertaken by each Scrutiny Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.