ItemPL19-20/21
Resolved
RESOLVED that the Application be REFUSED Reason for Refusal 1. Part Q.2 (1) of Class Q, Part 3, Schedule 2 of the Town and Country Planning General Permitted Development Order 2015 as amended, requires that where the development proposed is development under Class Q(a) together with development under Class Q(b), development is permitted subject to the condition that before beginning the development, the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to 'flood risks on the site' (sub section d). The building proposed for conversion, along with the site access and part of the driveway is sited within Flood Zones 2 and 3. The submitted Flood Risk Assessment which is deemed to be inadequate by the Environment Agency, does not comply with the requirements for site-specific flood risk assessments, as set out in paragraphs 30 to 32 of the Flood Risk and Coastal Change section of the planning practice guidance, and therefore fails to adequately assess the flood risks posed by the development. Without the submission of necessary information by the applicant, the proposal is considered to be contrary to the provision of Class Q as potential flood depths are at this ... view the full minutes text for item PL19-20/21
Word for word from the decision Bolsover published for this meeting.
Source: committees.bolsover.gov.uk