Bolsover District Council
Executive, Monday 31 July 2023 at 10.00am

Woburn Close Cluster, Prestart costs

Approved Executive 1 paper

Executive approved this item on Monday 31 July 2023. Below is the council's own wording, with the papers it was decided on.

ItemEX21-23/24

Resolved

RESOLVED that £86,736.24 is approved for the demolition of the bungalows at Woburn Close, Blackwell to start immediately, using the HRA budget for New Scheme Evaluations (H019). Reasons for Recommendation This expenditure had been endorsed by Dragonfly Development Ltd. · To avoid delay relating to demolition ecology issues in starting on site. · To save council tax on empty properties. · To prevent anti-social behaviour. · To replenish the BDC housing stock as soon as possible. Alternative Options and Reasons for Rejection Executive could choose not to support the request for funds, but this could delay the start on site, increase antisocial behaviour, which could have associated reputational and financial costs, increase empty property council tax liability, and could increase total costs if prices in the construction market increase over the time delay period.
Word for word from the decision Bolsover published for this meeting. Source: committees.bolsover.gov.uk

Follow this further

Built from Bolsover's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Woburn Close Cluster, Prestart costsReport 207 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bolsover

Search all
  1. Woburn Close Cluster, Prestart costsThis decision
  2. Application no. 24/00355/VAR - Variation of condition 2 (revised plans) - Woburn Close, BlackwellApproved
  3. Bolsover Homes Scheme - Woburn Close Cluster, BlackwellDecided
  4. 22/00380/FUL - Demolition of existing bungalows and assisted living building. Replacement with 23no. new dwellings (comprising 8no. houses and 15no. bungalows), and a 20no. flat independent living building - Development Site at Woburn Close, BlackwellApproved
  5. 22/00380/FUL - Demolition of existing bungalows, assisted living building and community centre; and replacement with 22 no. new dwellings, comprising 4 no. houses and 18 no. bungalows, a 20 no. flat independent living building and a new community centre - Development Site at Woburn Close, BlackwellDeferred

More from Bolsover Executive

All decisions
MeetingDecisionOutcome
27 Jul 2026 Compliments, Comments and Complaints (CCC) Policy Housing Ombudsman ReviewRESOLVED that the CCC Policy changes following recommendations by the Housing Ombudsman, and the Customer Services Sc... Approved Open
27 Jul 2026 Anti-Fraud, Bribery, and Corruption PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Anti-Money Laundering PolicyRESOLVED that the be approved. Approved Open
27 Jul 2026 Biodiversity Net Gain Receptor Site ProjectRESOLVED that the option of entering the BNG receptor site market using the limited land currently allocated for envi... Decided Open
27 Jul 2026 Review of the Creation of Climate Resilience Plan and ConsultationRESOLVED that 1) the work undertaken by the Climate Resilience Group to date, to develop the DRAFT Climate Resilience... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies