Resolved
RESOLVED that the update be noted.
Planning Committee noted this item on Wednesday 4 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the update be noted.
1.1Section 106 agreements are legal agreements between the Council and landowners/developers that are often completed alongside applications for planning permission for major developments. They are needed to deal with the additional pressures on infrastructure that result from the new development. They are only required where the effects of the development would otherwise be unacceptable in planning terms and where they cannot be dealt with by conditions of the planning permission.
1.2As can be observed, implementation of these Section 106 Agreements in a timely manner alongside the build-out of the approved developments is important as failure to achieve this will mean important infrastructure improvements lag behind the impact of the development.
1.3Furthermore, if the Council fails to spend monies provided through the Section 106 Agreement within a set period, often within 5-years of entering into the agreement, there is a risk to the Council that the developer would be entitled to request the money back. This risk is thankfully relatively low but it is one that the Council must take seriously due to both the negative impact on the affected local community and the consequential reputational impact on the Council.
1.4To manage and mitigate this serious risk the Council has approved a procedure for recording and monitoring Section 106 Agreements. The most recent version of this was approved by Planning Committee in September 2022 and it governs the work of the Council’s cross-departmental Section 106 Monitoring Group.
1.5Following the quarterly Section 106 Monitoring Group meeting, officers provide a progress report to the Planning Committee in respect of the monitoring of Section 106 Agreements. In line with the approved Procedure this progress report is required to highlight any sums at risk of clawback that need spending within 24 months, as well as a summary of the sums being held by infrastructure type that are in years three, four and five.
1.6Accordingly, this report is the quarterly progress report following the meeting of the Section 106 Monitoring Group held on 18th July 2024.
2. Details of Proposal or Information
2.1The Council’s Section 106 Agreement Monitoring Procedure requires sums within 24 months of their deadline to be highlighted for Member’s attention.
2.2Members will recall that in the report provided on 19th June, eight sums were identified as being within their 24-month deadline as of 18th April 2024.
2.3As of the Monitoring Group meeting on 18th July 2024 there are nine sums within their 24-month deadlines (details below).
Spend Date within 12 months (by 18th July 2025)
Action Finance Site Infrastructure Amount Date Plan Spreadsheet and amount remaining
Item 17 Line 83 Mansfield Outdoor Sport £162,915 20.12.24 Road, (£164,153) Reduced Tibshelf by £88
Item 19 Line 89 Oxcroft Outdoor Sport £123,469.8 10.3.25 Lane, (£125,336.69) 4 Bolsover Reduced by £144.35
Now spent
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarterly Update on Section 106 Agreement MonitoringReport | 11 pages | DownloadRead as text |
Follow Planning Committee at Bolsover and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Feb 2026 | Application no. 25/00509/FUL - Station Yard, Chesterfield Road, PleasleyRESOLVED that application no. 25/00509/FUL be APPROVED subject to the following planning conditions: 1. The developme... | Approved | Open |
| 18 Feb 2026 | Application no. 25/00491/VAR - Willow Tree Family Farm, Langwith Road, ShirebrookRESOLVED that application no. 2 5/00491/VAR be referred to the Secretary of State via the National Planning Casework ... | Approved | Open |
| 18 Feb 2026 | Application no. 22/00478/FUL - Land Between St. Lawrence Avenue and Rotherham Road, North Of Langwith Road, BolsoverRESOLVED that Planning Committee Members noted the typographical error in the Consultation section of the previous Co... | Noted | Open |
| 18 Feb 2026 | Historic Environment Supplementary Planning Document - Consultation DraftRESOLVED that Planning Committee: 1) approve the contents of the proposed consultation draft Historic Environment Sup... | Approved | Open |
| 18 Feb 2026 | Quarterly Update on Section 106 Agreement MonitoringRESOLVED that Planning Committee note the contents of the report and highlight any concerns about the implementation ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.