Pleasley Vale Regeneration Project - Update

Approved Committee 3 papers

Council approved this item on Wednesday 4 December 2024. Below is the council's own wording, with the papers it was decided on.

ItemCL59-24/25

Resolved

RESOLVED that (1) the continued investment in Pleasley Vale Business Park and Conservation Area aligned to the Corporate ‘Economy’ priority be endorsed; (2) approval be given for the use of reserves to fund the works to the value of £428,537 as presented in the table at 3.19 in the report; (3) approval be given for the Section 151 Officer to trawl the already approved reserve funded schemes to identify if any were no longer required and could be used to fund the shortfall of £342,462 or failing that to approve the additional borrowing necessary to fund the gap for the additional capital works and surveys as identified in the report, subject to further reports being presented to the Executive following appropriate procurement exercises; and (4) delegated authority be given to the Chief Executive Officer to establish the post and budget of a Building Surveyor / Contracts Administrator into the Property Services Team of DMBL, to manage and oversee the building works and repairs at Pleasley Vale Business Park.
Word for word from the decision Bolsover published for this meeting. Source: committees.bolsover.gov.uk

Follow this further

Built from Bolsover's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Pleasley Vale Regeneration Project: UpdateReport 381 KB Copy on its way
PDF
item 9, Appendix 1: Scope of Works: Copy -24/25Appendix 19 MB Copy on its way
PDF
item 9, appendix 2 -24/25Appendix 626 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bolsover

Search all
  1. Pleasley Vale Regeneration Project - UpdateThis decision
  2. Contract Award for the delivery of an Options Appraisal for Pleasley Vale Business ParkNoted
  3. Approval of appointment for works at Pleasley ValeApproved
  4. Pleasley Vale Business Park Flood Mitigation WorksApproved
  5. Pleasley Vale Regeneration Programme - Monitoring UpdateNoted
  6. Pleasley Vale Regeneration Programme - Monitoring UpdateNoted

More from Bolsover Council

All decisions
MeetingDecisionOutcome
4 Mar 2026 Change to the Council's Constitution - Definition of Working DayRESOLVED that approval be given to amend the Constitution to include a definition of the term “working day” to mean M... Approved Open
4 Mar 2026 Domestic Abuse PolicyRESOLVED that (1) the at Appendix 1 to the report be approved; and (2) that the HR Team take steps to raise awareness... Approved Open
4 Mar 2026 Future delivery of the Council's Housing Stock Condition SurveyRESOLVED that (1) approval be given for the creation of a new full-time permanent Contract Administrator/Building Sur... Approved Open
4 Mar 2026 Fire Door Safety InspectionsRESOLVED that (1) approval be given to the budget of £48,391 for establishing fire door inspections; (2) approves the... Approved Open
4 Mar 2026 Whistleblowing Update Report 2025RESOLVED that the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies