AI summaryBolsover District Council approved a temporary 99.9MWac energy storage system at Hurst Farm, subject to conditions. Development must begin within seven years of permission; the temporary period is 40 years from first use, with the substation remaining permanently.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTemporary permission for a 99.9MWac energy storage system.
MoneyNot stated
What happens nextMeet the permission conditionsStart before seven years expire and follow approved documents.
Who it affectsGrid, countryside, heritage and residentsTemporary storage, permanent substation, roads and footpaths.
What was decided
Bolsover District Council's Planning Committee approved application no. 25/00302/FUL for an Energy Storage System at Hurst Farm, Tibshelf, subject to conditions. The permission covers a 40 year temporary period from first use, after which the storage development will be removed and the land restored. The substation and associated infrastructure will remain permanently for adoption by the Distribution Network Operator. Report P2, P14, P145
Development must be begun before the expiration of seven years from the date of the permission.
The development must be carried out in accordance with the approved drawings and documents listed in the decision, unless a specific condition states otherwise.
Why
The scheme supports energy security and renewable generation, with economic and environmental benefits. It is consistent with national policy and the transition to net zero. Report P3, P5, P6, P29, P130
The officer judged those benefits outweighed the conflict with countryside policies and the visual and heritage harm, taking account of national policy, guidance and related appeal decisions. Report P5, P6
The location, topography, design and planting limit visual effect to a few points around Hardwick Hall. Heritage harm was assessed at the low end of less than significant, although some visual industrialisation would remain. Report P6, P35
What happens next
Begin development before the expiration of seven years from the date of the permission.
Carry out the development in accordance with the approved drawings and documents, subject to any specific conditions in the decision.
The officer report identifies condition requirements for design and colour, lighting, noise, contamination and coal mining risks, archaeology, access and road visibility, construction management, drainage, fire safety, biodiversity and restoration. Final colour, landscape and restoration details may be submitted to the Council for approval. Report P37, P38, P39, P41, P42, P47, P48, P51, P52, P63, P74, P80, P83, P100, P141, P142, P143, P145
The money
£40 billion Estimated average annual clean energy investment under the Clean Power 2030 Action Plan between 2025-2030 Report P113
Options considered
Chosen: Grant temporary permission for the Energy Storage System. The officer judged the economic and environmental benefits outweighed the countryside policy conflict and visual and heritage harm. Report P5, P6
Chosen: Retain the three southern BESS clusters. The higher storage capacity was considered more beneficial, subject to controls on equipment colour and fencing. Report P144
Rejected: Omit the three southern BESS clusters. Removal would significantly reduce storage capacity, require renegotiation with the Distribution Network Operator and could jeopardise feasibility, for a limited reduction in visual impact. Report P144
Rejected: Grass the spaces between BESS units. Fire guidance says vegetation within 10 metres should be kept clear because it could increase fire spread between units. Report P142
Chosen: Use suitably coloured permeable gravel between units. It would reduce the appearance of built form in distant views while avoiding combustible vegetation close to the units. Report P142
Chosen: Add more mature tree planting. The revised landscape proposals use more mature trees for screening, although effective screening would take time. Report P143
Implications
Climate: Storing and releasing electricity would balance supply and demand and support renewable energy generation. The proposal would also support energy security. Report P3, P6, P130
Financial: The landowner said the development would provide an additional income stream, support farm diversification and help the farm become more resilient to volatile energy prices and future market conditions. Report P87
Legal: The permission is temporary for 40 years from first use. All above ground elements except the substation and associated infrastructure will then be removed and the land restored, while the permanent infrastructure will be adopted by the Distribution Network Operator. Report P2, P14, P145
Legal: The proposal does not meet any countryside policy SS9 category, but renewable energy policy SC6 applies because the assessed effects did not meet the significant harm thresholds. It will nevertheless harm the setting of the Hardwick heritage assets, with less than substantial harm at the lower end of the scale. Report P35, P36, P125, P130, P136, P147, P148
Risk: Potential site contamination and coal mining legacy require investigation and possible remedial work. The Coal Authority supports the proposal only subject to conditions. Report P48, P73, P74
Risk: Archaeological features may be of regional importance. Approval should require excavation and recording, preservation by design, or both, within the development footprint. Report P50, P51
Risk: BESS sites fall outside Building Regulations. Once occupied, the responsible person must maintain and regularly review a fire safety management plan and fire risk assessment. Report P79, P80
Risk: Tree planting along the access could create predator perches and reduce the suitability of offsite fields for breeding skylark. Derbyshire Wildlife Trust sought confirmation that the planting was necessary or could be reduced. Report P76, P77
Who and where
Electricity network and the Distribution Network Operator Report P2, P3, P14
Farm operator at Hurst Farm Report P87
Residents at Hurst Farm and nearby properties Report P46, P86, P87
Operators of offsite fields west of the access track Report P76, P77
Derbyshire Fire and Rescue Service Report P78, P79, P80, P81, P82
Road users during construction and abnormal load movements Report P53, P58, P59, P72
Timeline
9th January 2025: The Local Planning Authority concluded that an Environmental Impact Assessment was not required. Report P21
September 2025: An updated ecological assessment with final breeding bird and bat survey results was submitted. Report P75
10 October 2025: Revised drawings and supporting documents were received. Report P16
2025-12-10: The Planning Committee approved application no. 25/00302/FUL.
Before the expiration of seven years from the date of this permission: Development must have begun.
40 years from the date it is first brought into use: The temporary operating period begins. Report P14
At the end of the 40 year period: The storage development will be removed, the land restored and the permanent substation infrastructure retained. Report P14, P145
Plain English for the jargon
99.9MWac: The proposed storage capacity, projected in the application.
ESS and BESS: Energy Storage System and Battery Energy Storage System, storing electricity in batteries.
DNO: The Distribution Network Operator, which adopts the permanent substation and associated infrastructure.
EIA: An environmental assessment screened for. The Council concluded it was not required.
PRoW: A public footpath route through or next to the site.
Policy SC6: The Local Plan policy for renewable and low carbon energy development.
Policy SS9: The Local Plan policy for development in the countryside.
Biodiversity net gain: The required 10% gain, delivered through habitat creation and improvement.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPL54-25/26
Resolved
RESOLVED that application no. 25/00302/FUL be APPROVED subject to the following conditions: The development must be begun before the expiration of seven years from the date of this permission. The development hereby permitted shall be carried out in accordance with the following approved drawings and documents unless specifically stated otherwise in the conditions below: · Location Plan GBR_Hurst Farm_AD - SLP_07 – Drawing no. AD-SLP, received 23 rd July 2025; · Preliminary Design Layout GBR_Hurst_LP2-PDL-BESS_05 – Drawing no. LP2-PDL, received 10 th October 2025; · General Arrangement of Site Access - Drawing no. HFD-BWB-GEN-XX-DR-TR-101 S2 Rev. P7, received 10 th October 2025; · General Arrangement of Access from Site to Road – Overview – Drawing no. HFD-BWB-HML-00-DR-TR-100 S2 Rev. P8, received 10 th October 2025; · Landscape Strategy Plan – Drawing no. NT16771-020 Rev. P07, received 10 th October 2015; · Ecological Impact Assessment Tree Retention and Removal Plan – Drawing no. 16625-P05d, received 11 th July 2025; · Ecological Impact Assessment Bat Static Location Plan – Drawing ... view the full minutes text for item PL54-25/26
Word for word from the decision Bolsover published for this meeting.Source: committees.bolsover.gov.uk
The application requires planning committee consideration in accordance with the officer scheme of delegation, as it is recommended for approval but is contrary to countryside policies in the Council’s Local Plan.
This planning application seeks temporary planning permission for an Energy Storage System (ESS) at land at Hurst Farm, Tibshelf. The ESS will operate for a period of forty years before the development is decommissioned and the land returned to its former state, except for the substation and associated infrastructure that will remain a permanent feature to be adopted by the Distribution Network Operator (DNO).
The ESS stores electricity in batteries and releases it into the network when needed, helping balance supply and demand and supporting the growth of renewable energy generation by increasing the capacity that is available to store energy that is generated. The proposed development is projected to have a storage capacity of 99.9MWac.
The applicant provides that the location of the proposed development is the result of extensive engagement with National Grid Electricity Distribution (NGED) to ensure that the proposal can be delivered, in addition to policy and other feasibility considerations through a robust site selection process.
The key consideration is whether the weight that should be afforded to the economic and environmental benefits of the proposed development outweighs the visual and heritage impacts; countryside location and setting of Hardwick Hall.
On balance, the location of the site, topography of the land and proposed design and planting limits the visual impact to few points around Hardwick Hall. The impact on heritage assets is therefore considered on the low end of ‘less than significant’. While detached from the farm complex and resulting in a degree of visual industrialisation of the countryside location, it is read to some extent in the context of the existing pylons and power lines, and the M1 motorway which is adjacent. The conflict with countryside policies of the Local Plan and harm identified is considered to be outweighed by benefits of the development, having regard to the importance of energy security, the importance of supporting the provision and use of renewable energy, national policy and guidance and related appeal decisions. Site Location Plan
OFFICER REPORT ON APPLICATION NO. 25/00302/FUL
SITE & SURROUNDINGS
The site comprises approximately 7.9 hectares of agricultural land at Hurst Farm, Tibshelf. The farm building complex sits at the end of a long access road off Mansfield Road, to the east of the M1 motorway. The main part of the application site comprises a detached and distinct agricultural field to the north of the farm complex, with topography that drops from west to east. The remainder of the site comprises sections of agricultural fields linking back to Mansfield Road from which the primary access will be carved. The existing farm access is included within the site as a secondary / emergency access. Public rights of way run through and adjacent to the site (Footpaths 35 and 36). Agricultural fields generally surround the site, with areas of scrub, the M1 motorway to the west and Sawpit Lane Industrial Estate beyond Mansfield Road to the south.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.