DECISION That the revised contribution of £344,310 to the BroadbandUK (BDUK) project, to be met from the existing £300,000 Capital Programme allocation, plus parts of the 2014/15 Capital Budget underspend, be approved. Portfolio Holder and Officer Cllr Spencer RB
Word for word from the decision Boston published for this meeting.Source: democracy.boston.gov.uk
The BroadbandUK (BDUK) project to deliver SuperFast broadband across Lincolnshire has now provided over 80,000 homes with access to broadband speeds that would not otherwise have been financially viable.
Based on an agreement made by the Chief Executives of the Lincolnshire Districts to collectively contribute £4m of the total £14m public sector contribution towards the Lincolnshire BDUK programme, Boston Borough Council agreed to contribute an 8.6% share of the £4m required. This would have meant a maximum contribution from Boston of £344,310. It was originally hoped that additional European Regional Development Fund (ERDF) funding would reduce the Borough’s contribution, and so an allocation of £300,000 was made in the Council’s Capital Programme.
Unfortunately, ERDF funding has not been forthcoming for this project, and this report seeks approval for an additional sum of £44,310 to be allocated to support the project, funded from capital resources.
Scheme estimates anticipate that up to 1,800 jobs will be created as a result of the project, equating to approximately 150 in the Boston area if shared equally within the county.
Recommendations
Members are asked to approve the revised contribution of £344,310, which will be met from the existing £300,000 Capital Programme allocation, plus parts of the 2014/15 Capital Budget underspend. REASONS FOR RECOMMENDATIONS
The BroadbandUK project has countywide support, and has already delivered improved broadband access speeds to significant parts of the Borough, with completion via the BDUK project set for 2016.
Original predictions stated that Lincolnshire as a whole would experience a gross value added (GVA) uplift of around £47m to £66m per year over the next 5 – 7 years through the introduction of SuperFast Broadband. This equates to between 1,300 and 1,800 new jobs across the County.
Using the 8.6% Boston contribution this equates to GVA uplift in Boston Borough of around £4m to £5.7m per year, and between 111 and 154 new jobs .
ALTERNATIVES CONSIDERED
Not to support the initiative, and the revised contribution.
1.0CURRENT POSITION
1.1The Broadband UK (BDUK) project to deliver SuperFast broadband across Lincolnshire has provided over 80,000 homes with access to broadband speeds that would not otherwise have been financially viable.
1.2The original project aimed to reach 90% of households in the county, but advances in technology during the project means that 95% of households are now anticipated to be included by the end of the project.
1.3Across the Borough of Boston, this has resulted in over 6,000 properties having access to broadband speeds in excess of 24mbps which would not otherwise have been provided access to SuperFast speeds.
1.3The BDUK project has 8 stages, and is currently nearing the end of Stage 5. As most borough locations were included in Phases 3 and 4 of the programme, this means the rollout in the borough is almost complete.
1.4There is some further work to be completed in the borough, with approximately 4,600 properties scheduled for upgrades by the end of Stage 6, which ends in September 2015.
1.5Not all properties in the Borough are eligible for the BDUK access to SuperFast speeds, however, as some areas were already included in BT’s own commercial rollout plan. It is anticipated that this commercial rollout will be completed by 2017. 1.6 Customer take-up of the new high speed services varies enormously across the Borough, and depends on many factors, with some of the early elements now approaching 20% take-up. It is expected that numbers will increase significantly in the coming years as customers begin to adopt increasingly popular online video and television services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Strategy / Policy Review and DevelopmentThat the policies and strategies listed in Appendix A be extended to 31 March 2028 where their current expiry date is...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.