RESOLVED that: 1. The Risk Management Framework be recommended to Cabinet for approval with the Committee’s comments; 2. The quarter 4 risk information to the end of March 2015 be noted. SR
Audit & Governance Committee approved this item on Monday 22 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: 1. The Risk Management Framework be recommended to Cabinet for approval with the Committee’s comments; 2. The quarter 4 risk information to the end of March 2015 be noted. SR
Reviewed and updated Risk Management Framework Headline strategic risks Quarter 4 2014/15
1. That Committee comment on the reviewed and updated Risk Management Framework at Appendix 1 for referral to Cabinet for approval 2. That Committee comment on the Q4 risk information to the end of March 2015
The Audit & Governance Committee is responsible for monitoring the effective development and operation of risk management in the Council according to its terms of reference.
ALTERNATIVES CONSIDERED
Alternative reporting arrangements REPORT
1. Introduction 1.1 The Corporate Plan sets the strategic objectives for the Council. In 2014/15 the four corporate objectives were: 1) Revitalizing and promoting our town and rural borough 2) Safe, secure homes and neighbourhoods 3) Promoting greener and healthier communities 4) Deliver better council services with less money
1.2Each quarter we monitor our strategic risks – those risks which could impact most on the achievement of our corporate priorities. We also exception report lower-level risks at the discretion of Heads of Service.
2. Risk Management Framework – Appendix 1 2.1 The Risk Management Framework is attached at Appendix 1 and sets out the Council’s approach to risk management. This is reviewed annually. It has been reviewed and updated based on good practice and lessons learned over the year. It has been signed off by CMT and Heads of Service Team (HoST) and comes to Committee for comment and recommendation to Cabinet for approval.
3. Summary risk management process 3.1 Strategic, operational, project and partnership risks are identified and/or reviewed at the beginning of each financial year.
3.2Strategic risks are identified by looking at the potential risks (both negative and opportunity risks) which may impact on how the Council delivers its priorities in the year ahead. These strategic risks are set out below by priority.
3.3Operational risks are those which may impact on individual service areas. Project risks are those which may impact on a project successfully achieving its objectives. Partnership risks are those which may impact on a partnership successfully achieving its objectives.
Likelihood is measured from 1 to 4 – hardly ever, possible, probably or almost certain. Impact is measures from 1 to 4 – negligible, minor, major, critical
3.4The Council’s risk appetite is reviewed annually and is reflected in the risk tolerance lines in the diagram below, marked green, amber and red. We give priority to addressing the high red risks first wherever possible.
3.5A lead officer is identified for each risk. They are responsible for monitoring the risk, controls and recommended actions. Strategic, operational, project and partnership risks are reported quarterly to Scrutiny, Cabinet and Audit & Governance Committee. 4. Headline strategic risks 2014/15:
Key CP1: Revitalising and promoting our town and rural borough CP2: Safe, secure homes and neighbourhoods CP3: Promoting greener and healthier communities CP4: Delivering better council services with less money Overall risk to the Council
5. Detailed risk information 2014/15 – Appendix 2 5.1 Detailed risk information is set out in Appendix 2.
5.2For each of the corporate priorities, the following elements are laid out:
List of possible risks Risk scores Lead officer Risk descriptions Possible negative risks Possible opportunity risks Controls already in place Actions completed in 2014/15
6. Exception reporting 6.1 No new high risks have been identified in Q4.
6.2No risks without suitable mitigation in place have been identified in Q4.
CONCLUSION Strategic and operational risks continue to be managed in accordance with the Risk Management Framework. FINANCIAL IMPLICATIONS
There are no financial implications specific to this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Framework 2015-16Appendix 1 | 10 pages | Download |
PDF |
Risk detail quarter 4Appendix 2 | 5 pages | Download |
PDF |
QUARTER 4 RISK REPORTReport | 4 pages | DownloadRead as text |
Follow Audit & Governance Committee at Boston and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Apr 2026 | Internal Audit Progress Report - April 2026It was agreed that this matter required further consideration to ensure future meetings were adequately supported. Th... | Agreed | Open |
| 21 Apr 2026 | External Audit plan and strategy for the year ending 31 March 2026That the External Audit Plan and Strategy for the year ending 31 March 2026 be noted. | Noted | Open |
| 21 Apr 2026 | Accounting Polices 2025/26That the Accounting Policies for 2025/26 ... view the full minutes text for item 61. | Decided | Open |
| 21 Apr 2026 | Regulation of Investigatory Powers Act (RIPA) 2000 - Annual UpdateThat the Regulation of Investigatory Powers Act 2000 – Annual Update be noted. | Noted | Open |
| 21 Apr 2026 | Work ProgrammeThat the Work Programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.