Boston Town Area Committee (BTAC) approved this item on Wednesday 16 September 2015. Below is the council's own wording, with the papers it was decided on.
That the full cost model for the purchase, installation and movement of a data gathering speed indicating device (SID), totalling £3,198 excluding VAT with a management fee of £847 exclusive of VAT plus 3% per annum, be approved, with Members to identify six sites throughout the BTAC area for the device to be located.
Word for word from the decision Boston published for this meeting.Source: democracy.boston.gov.uk
Report to Boston Town Area Committee (BTAC), 13 pages
Summary
At its meeting on 1 July 2015, BTAC asked that a full cost model for the purchase, installation and movement of a Speed Indicating Device (SID) at six locations (to be agreed) throughout the BTAC area. The purchase price of one SID to be used across six BTAC locations is £3,198 exclusive of VAT, with an annual management fee of £847 exclusive plus 3% per annum.
Recommendations
That BTAC considers the information presented and determines its way forward.
Reasons for recommendations
The recommendation is that of the Committee itself.
ALTERNATIVES CONSIDERED
None. REPORT
Background
1.1On 1st October 2014, BTAC considered information on the Speed Watch Initiative, launched by Lincolnshire Road Safety Partnership and resolved:
“That the Community Speed Watch Initiative is noted, its availability is welcome and BTAC is prepared to consider applications from Placecheck or other community groups for funding to purchase signs and speed indication devices if they come forward with evidence of problems.”
1.2Following a request from a member of the public that BTAC facilitate the purchase, installation and monitoring of a Speed Indicating Device on London Road, Boston at its meeting on 1 July 2015, the Committee requested a further report, this report, that set out the full cost of purchasing a single SID, a number of mounting plates and an annual cost for ‘managing’ a SID throughout the BTAC area. Section 2 presents this information.
Financial implications
2.11 X Bluetooth SID (inc 1 mounting plate) £2,038 5 x additional mounting plates @ £49 ea £245 6 x Mounting Plate installations £675 (max cost) 6 x Site Application @ £40 ea £240
Total (Exclusive of VAT) £3,198
BBC management fee @ 26 moves per annum £847 (plus 3% per annum)
2.2The BBC management fee includes a maximum of 26 SID moves per annum, SID charging and data collection. The data will be shared with Lincolnshire Police and the Road Safety Partnership to inform where mobile speed units may be well targeted.
2.3Maintenance and/or repair outside of the manufacturer warranty for the SID would be at full cost to BTAC.
3 SID Locations
3.1Archer Survey data available for Boston is set out at Appendix 1. Data is available for Horncastle Road, Freiston Road, Sleaford Road, High Street, London Road, Marsh Lane and Linley Drive. BTAC members will of course be able to determine any final locations subject to survey. 4 CONCLUSION
4.1With the financial implications set out, BTAC will be able to consider whether it supports the purchase and use of a SID in the BTAC area.
1 X Bluetooth SID (inc 1 mounting plate) £2,038 5 x additional mounting plates @ £49 ea £245 6 x Mounting Plate installations £675 (max cost) 6 x Site Application @ £40 ea £240
Total (Exclusive of VAT) £3,198
BBC management fee @ 26 moves per annum £847 (plus 3% per annum)
Any cost agreed will be met from the BTAC budget.
Legal implications
None identified
ANY OTHER IMPLICATIONS
None identified
Consultation
CMT
Appendices
Appendices are listed below and attached to the back of the report: -
Appendix 1 – Archer Survey Data for Boston.
Background papers
No background papers as defined in Section 100D of the Local Government Act 1972 were used in the production of this report. CHRONOLOGICAL HISTORY OF THIS REPORT
A report on the Community Speed Watch Initiative was previously considered by BTAC on 1st October 2014 and 1 July 2015. BOSTON BOROUGH COUNCIL PROFORMA FOR EXECUTIVE APPROVAL OF THE RELEASE OF RESOURCES (CAPITAL AND REVENUE BUDGETS)
FROM: Caroline Thacker
THIS PROFORMA PROVIDES THE FINANCIAL IMPLICATIONS IN RESPECT OF THE ATTACHED
REPORT: Boston Town Speed Indicating Device (SID)
REPORT DATE: 16 September 2015
£ Year 1 £ Year 2 £ Year 3 £ Year 4 £ Year 5 2015/16 2016/17 2017/18 2018/19 2019/20 Revenue Speed Indicating device, 3198 0 0 0 0 mounting plates, installation and Site applications
BBC management fee 847 872 899 926 953
Total Cost to BTAC 4,045 872 899 926 953
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.