External Audit Completion Report 2024/2025 (ISA260)

Noted Finance 2 papers

AI summaryBoston Borough Council's Audit and Governance Committee noted KPMG's External Audit Completion Report for 2024/25, which expects an unmodified opinion. The audit is substantially complete, with £2.37m in adjusted misstatements, £499k unadjusted, and three matters still to close.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe Committee noted KPMG's audit completion report for 2024/25
Money£153,022PSAA scale fee for the 2024/25 audit, plus VAT
What happens nextSign the audit opinionAfter three outstanding matters are resolved
Who it affectsCouncil's 2024/25 accountsAudited financial statements of the Council and its group

What was decided

The Committee noted the External Audit Completion Report for 2024/25 from KPMG.

KPMG expects to issue an unmodified auditor's report once the three outstanding matters are resolved: related party testing, the management representation letter, and completion procedures. Report P3, P4, P9, P10

The audit identified £2.37m of adjusted misstatements which reduced the surplus, and £499k of unadjusted misstatements which would increase the surplus if posted. Report P62, P93

Why

KPMG found no significant weaknesses in the Council's value for money arrangements across financial sustainability, governance, and improving economy, efficiency and effectiveness. Report P80, P81

Significant audit risks on the valuation of land and buildings, management override of controls, and post-retirement benefit obligations were tested and found satisfactory or balanced. Report P8, P17, P24, P44

Management approved correction of the identified misstatements, which are reflected in the draft financial statements. Report P61

What happens next

KPMG will sign the audit opinion once related party testing, the management representation letter, and completion procedures are closed off and the statement of accounts is approved. Report P3, P9, P10

The Council is to introduce a formal log of efficiency savings decisions and actions, with a target completion date of 31 March 2026. Report P88

KPMG is awaiting instructions from the National Audit Office on the Whole of Government Accounts consolidation pack before issuing the audit certificate. Report P78, P93

The money

  • £153,022 PSAA scale fee for the 2024/25 external audit, plus VAT Report P76
  • 186.6 Total KPMG fees for 2024/25 in £'000, including non-audit work Report P120
  • £33.6 Housing benefit grant certification non-audit fees in £'000, expected Report P115
  • £2.37m Adjusted audit differences which decreased the reported surplus Report P93
  • £499k Uncorrected audit misstatements which would increase the surplus if posted Report P62, P129
  • £37.84m Value of the Council's Other Land and Buildings at 31 March 2025 Report P24
  • £10.2m Post-retirement benefit obligations balance Report P55
  • £1.49m Overstatement identified on the Land Value per Acre assumption, corrected by management Report P27

Implications

  • Risk: Control deficiencies identified over the valuation review process and segregation of duties in the General Ledger, with no counter-signatory on valuations. Report P28, P37
  • Legal: Audit certificate cannot be issued until the National Audit Office provides instructions on the Whole of Government Accounts consolidation pack. Report P78, P93
  • Other: Lack of formal recording of efficiency savings decisions identified as a performance improvement observation, with a recommendation to address it by 31 March 2026. Report P88
  • Staffing: Six councillors and two members of the Senior Leadership Team had not completed declarations of interest at the time of audit, raising a control deficiency. Report P37, P58

Who and where

  • Boston Borough Council as a corporate body, whose 2024/25 financial statements are the subject of the audit Report P2, P76
  • The Audit and Governance Committee, as the body receiving the report Report P2
  • Council members and senior officers, regarding completion of declarations of interest Report P37
  • Readers of the Council's accounts, including regulators, suppliers and residents Report P76

Timeline

  • 31 March 2025: Financial year end covered by the audit Report P2
  • 22 April 2025: Audit plan and strategy report presented to the Committee Report P3
  • 30 September 2025: Original due date for prior period efficiency programme recommendation, assessed as not implemented Report P91
  • 27 October 2025: Date of the draft year end report from KPMG Report P2, P5
  • 17 November 2025: Audit and Governance Committee meeting at which the report is noted Report P2
  • 31 March 2026: Target date for the Council to introduce a formal log of efficiency savings decisions Report P88

Plain English for the jargon

  • ISA 260: International Standard on Auditing (UK) on communicating with those charged with governance
  • DRC: Depreciated Replacement Cost, a method of valuing property assets
  • BCIS: Building Cost Information Service, which publishes construction cost indices used in the valuation
  • LGPS: Local Government Pension Scheme
  • PSAA: Public Sector Audit Appointments, which sets scale fees for local authority audits
  • WGA: Whole of Government Accounts, the national consolidation of public sector accounts
  • VFM: Value for Money, the auditor's assessment of arrangements to secure economy, efficiency and effectiveness
  • PRSA: Princess Royal Sports Arena, an asset whose valuation was examined
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33

Resolved

That the External Audit Completion Report for 2024/25 be noted.
Word for word from the decision Boston published for this meeting. Source: democracy.boston.gov.uk

Follow this further

Built from Boston's papers

What the report saysPro

Report to Audit & Governance Committee, 51 pages

Boston Borough Council DRAFT - Year End Report to the Audit & Governance Committee

Year end report for the year ended 31 March 2025 — 27 October 2025 Introduction To the Audit and Governance We are committed to providing you with a high quality service. If you have any concerns or are dissatisfied with any part of KPMG’s work, in the first instance you should contact James Boyle ([email removed]), the engagement lead to the Authority, who will try to resolve your complaint. If you are dissatisfied with the response, please contact the national Contents Page Committee of Boston Borough lead partner for all of KPMG’s work under our contract with Introduction 2

Council Public Sector Audit Appointments Limited, Tim Cutler. ([email removed]). After this, if you are still dissatisfied Important notice 3 with how your complaint has been handled you can access We are pleased to have the opportunity to meet with you on 17 KPMG’s complaints process here: Complaints. Our audit findings 4 November 2025 to discuss the results of our audit of the Key changes to our audit plan The engagement team 5 consolidated financial statements of Boston Borough Council (the ‘Council’) and its subsidiaries (the ‘Group’), as at and for the Significant risks and Other audit risks 6 year ended 31 March 2025. Subject to the approval of the statement of accounts, we Audit risks and our audit approach 7 We are providing this report in advance of our meeting to expect to be in a position to sign our audit opinion on the approval of those statement of accounts and auditor’s Key accounting estimates and management 13 enable you to consider our findings and hence enhance judgement the quality of our discussions. This report should be read in representation letter, provided that the outstanding matters noted on page 4 of this report are satisfactorily resolved. Other significant matters 15 conjunction with our audit plan and strategy report, presented on 22 April 2025. We will be pleased to elaborate There have been no significant changes to our audit plan and Audit misstatements 16 on the matters covered in this report when we meet. strategy other than those described on page 5. Group involvement – Significant component 17

How we deliver audit quality We expect to issue an unmodified Auditor’s Report. We draw your attention to the important notice on page 3 of audits Other matters 18 Audit quality is at the core of everything we do at KPMG and we this report, which explains: Value for money 19 believe that it is not just about reaching the right opinion, but how we reach that opinion. • The purpose of this report Appendix 23

We consider risks to the quality of our audit in our engagement • Limitations on work performed risk assessment and planning discussions. • Restrictions on distribution of this report We define ‘audit quality’ as being the outcome when: Yours sincerely, • Audits are executed consistently, in line with the James Boyle requirements and intent of applicable professional standards within a strong system of quality management; and, 27 October 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Year End ReportReport 51 pages DownloadRead as text
PDF
External Audit Completion Report 2024/2025 (ISA260)Report 2 pages Download

At this meeting

Whole meeting

Who was there

10 of 25 attended
BP
Councillor Barrie PierpointChairman, present
JC
Councillor James CantwellVice-Chairman, present
AD
Councillor Anton DaniCommittee Member, present
AD
Councillor Anne DorrianCommittee Member, absent
ND
Councillor Neil DraytonCommittee Member, present
AI
Councillor Andy IzardCommittee Member, present
JN
Councillor Jonathan NobleCommittee Member, present
RP
Councillor Ralph PrykeCommittee Member, present
LS
Councillor Lina SavickieneCommittee Member, apologies
DS
Councillor David ScootCommittee Member, present
SW
Councillor Stephen WoodliffeCommittee Member, present
AC
Adam CartwrightCo-Optee, present

All 25 on the meeting page

On this subject at Boston

Search all
  1. External Audit Completion Report 2024/2025 (ISA260)This decision
  2. External Audit plan and strategy for the year ending 31 March 2026Noted
  3. External Auditor’s Annual Report 2024/25Noted
  4. External Auditors Progress Report 2024/2025Noted
  5. Final External Audit Completion Report 23/24 (ISA 260)Noted
  6. Draft External Audit Annual ReportNoted

More from Boston Audit & Governance Committee

All decisions
MeetingDecisionOutcome
21 Apr 2026 Internal Audit Progress Report - April 2026It was agreed that this matter required further consideration to ensure future meetings were adequately supported. Th... Agreed Open
21 Apr 2026 External Audit plan and strategy for the year ending 31 March 2026That the External Audit Plan and Strategy for the year ending 31 March 2026 be noted. Noted Open
21 Apr 2026 Accounting Polices 2025/26That the Accounting Policies for 2025/26 ... view the full minutes text for item 61. Decided Open
21 Apr 2026 Regulation of Investigatory Powers Act (RIPA) 2000 - Annual UpdateThat the Regulation of Investigatory Powers Act 2000 – Annual Update be noted. Noted Open
21 Apr 2026 Work ProgrammeThat the Work Programme be noted. Noted Open