Boston Borough Council
Full Council, Monday 12 January 2026

Quarter 2 2025/26 Capital Forecast Outturn

Approved Committee 1 paper

AI summaryBoston Borough Council approved 2025/26 capital programme amendments, including a £100k net increase for Levelling Up Fund projects brought forward from 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull Council approved the forecast outturn and changes to the 2025/26 capital programme
Money£100k net LUF increaseTotal revised budget 38,563 in £'000, forecast outturn 37,328
What happens nextAmendments implementedChanges take effect to align with current project delivery
Who it affectsCouncil capital projectsIncludes Towns Fund, LUF, UKSPF, BPF and other schemes

What was decided

Approved the Quarter 2 2025/26 Capital Forecast Outturn, including the proposed amendments to the capital programme as set out in Tables 1 and 2. Report P2

Approved reallocations within the Levelling Up Fund, including a net £100k increase brought forward from 2026/27 to accelerate the Crown House scheme. Report 1.5

Why

To ensure the capital programme is considered and that Full Council is aware of the financial position to make informed, affordable and sustainable decisions. Report P3

The amendments are required to align the capital programme with current project delivery across connected LUF sites. Report 1.5, P11

What happens next

The amended budgets will be used to track delivery against the revised 2025/26 capital programme to 31 March 2026. Report 1.3, P11

The money

  • £100k Net LUF increase brought forward from 2026/27 to Crown House Report 1.5
  • 1,148 Increase to LUF Crown House budget (in £'000) Report 1.5, P8
  • (576) Reallocation from LUF Civic Hub to Crown House (in £'000) Report 1.5, P8
  • (472) Reallocation from LUF Public Realm to Crown House (in £'000) Report 1.5, P8
  • 100 Net change to LUF budget in Table 2 (in £'000) Report 1.5, P8
  • 38,563 Grand total revised capital budget 2025/26 (in £'000) Report P8
  • 37,328 Grand total forecast outturn 2025/26 (in £'000) Report P8
  • (1,235) Grand total variance, underspend (in £'000) Report P8

Options considered

  • Chosen: Approve the amendments to the 2025/26 capital programme as set out in Tables 1 and 2. To align the capital programme with current project delivery and ensure financial sustainability Report P2, P3, P11
  • Rejected: Do not approve the amendments to the 2025/26 capital programme Report P4

Implications

  • Financial: Financial implications are as contained in the report and appendix. Report P26

Who and where

  • Boston Borough Council as the recipient and manager of the capital programme Report 1.2, P1
  • Projects funded by Towns Fund, Levelling Up Fund, UK Shared Prosperity Fund, and the Boston Project Fund Report 1.2, P8
  • Disabled Facilities Grant recipients Report 1.2, P8

Timeline

  • 10 December 2025: Cabinet noted the Q2 forecast outturn and resolved to forward the capital programme amendments to Full Council Report 1.1, P47
  • 12 January 2026: Full Council approved the Q2 2025/26 Capital Forecast Outturn and amendments
  • 31 March 2026: Projected end of 2025/26 financial year against which the forecast outturn is measured Report 1.3

Plain English for the jargon

  • LUF: Levelling Up Fund, a government grant programme funding local growth schemes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

That the Quarter 2 2025/26 Capital Forecast Outturn, including the proposed amendments to the capital programme for 2025/26 as set out in the report, be approved.
Word for word from the decision Boston published for this meeting. Source: democracy.boston.gov.uk

Follow this further

Built from Boston's papers

What the report saysPro

Report to Full Council, 6 pages

Summary

This report sets out the Capital Programme for the Council and the amendments required for 2025/26.

Recommendations

It is recommended: That Full Council approve the amends to the Capital Programme for 2025/26 as outlined in Table 1 and Table 2.

Reasons for recommendations

To ensure the Council’s Capital Programme for 2025/26 is considered and related decisions approved. It is important that Full Council are aware of the financial position to ensure they can make informed decisions that are affordable and financially sustainable for the Council. Other Options Considered

To not approve the amendments to the 2025/26 Capital Programme.

Background

1.1Cabinet noted the 2025/26 Quarter 2 Forecast Outturn on Wednesday 10 December 2025 and resolved to forward the amendments to the 2025/26 Capital Programme recommendation to Full Council for further consideration.

1.2The Capital Programme includes provision for Investment and Growth mainly funded through grant funding from Levelling Up Funds, Waste Services investment, IT investment and Disabled Facilities Grants.

1.3Table 1 details the revisions to the capital programme and progress against the 2025/26 approved programme including the projected forecast to 31 March 2026. The proposed amendments to the 2025/26 Capital Programme are highlighted below in blue and are also included separately in table 2.

Table 1 – Capital Programme 2025/26 Forecas Approve Changes Revised Actuals to Variance t d Budget to Budget Septembe (underspend Outturn Scheme 2025/26 Approve 2025/26 r 2025 )/ overspend 2025/26 d Budget at Q2 £’000 £’000 £’000 £’000 £’000 £’000 Disabled Facilities Grant 885 - 885 276 1,100 215 Vehicle Replacements 536 - 536 98 536 - Information Technology Infrastructure Refresh 412 - 412 105 402 (10) Swimming Pool Support Fund 122 76 198 198 198 - Uniform 291 - 291 - 231 (60) Unit 4 Implementation 47 - 47 - 47 - Affordable Housing Commuted Sum 1,074 - 1,074 - - (1,074) Capital Enhancements 604 - 604 127 312 (292) Depot Purchase 150 - 150 3 150 - Food Waste 154 (154) - - - - Homelessness Prevention Van 7 - 7 5 5 (2) Market Regeneration - 23 23 23 23 - Boston Council Chamber Mics - 33 33 - 33 - Total Projects (Excl Towns Funds, UKSPF, LUF & BPF) 4,282 (22) 4,260 835 3,037 (1,223) Towns Fund - Leisure 7,895 - 7,895 685 7,895 - Towns Fund - Mayflower 3,600 - 3,600 3,600 3,600 - Towns Fund - St Botolph’s Library 57 - 57 - 57 - Towns Fund - Healing the High St (incl. Shodfriars) 2,433 - 2,433 318 2,433 - Towns Fund - Boston Station 864 - 864 - 864 - Total Towns Fund Projects 14,849 - 14,849 4,603 14,849 - UKSPF (Capacity building projects for local groups) 275 - 275 42 264 (11) UKSPF Rural (Community projects aimed at reducing the cost of living) 129 - 129 18 128 (1) Total UKSPF Projects 404 - 404 60 392 (12) LUF - Civic Hub 581 (576) 5 5 5 - LUF - Crown House 4,877 1,148 6,025 441 6,025 - LUF - Public Realm 5,412 (472) 4,940 1,566 4,940 - Total LUF Projects 10,870 100 10,970 2,012 10,970 - BPF - Boston United Football Sports Complex 1,450 - 1,450 3 1,450 - BPF - Affordable Homes (Quadrant Housing Development) 1,752 - 1,752 442 1,752 - BPF - Haven Wharf 2,800 - 2,800 - 2,800 - BPF - PE21 Rosegarth Square 398 - 398 124 398 - BPF - Community Organisations Package 690 - 690 44 690 - BPF - Boston Connected 570 - 570 - 570 - BPF - Boston Community Research Project 370 - 370 32 370 - BPF – St Botolph’s Church Visitor Offer 50 - 50 - 50 - Total BPF Projects (excl Boston Leisure) 8,080 - 8,080 645 8,080 - Grand Total 38,485 78 38,563 8,155 37,328 (1,235)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 2025/26 Capital Forecast OutturnReport 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

26 of 40 attended
BP
Councillor Barrie PierpointMayor, present
PM
Councillor Patricia MarsonDeputy Mayor, present
AA
Councillor Alison AustinCommittee Member, present
RA
Councillor Richard Austin BEMCommittee Member, present
JB
Councillor John BaxterCommittee Member, present
PB
Councillor Peter BedfordCommittee Member, present
DB
Councillor David BrownCommittee Member, present
DB
Councillor Dale BroughtonCommittee Member, present
CB
Councillor Callum ButlerCommittee Member, present
JC
Councillor James CantwellCommittee Member, present
EC
Councillor Emma CresswellCommittee Member, apologies
AD
Councillor Anton DaniCommittee Member, present

All 40 on the meeting page

More from Boston Full Council

All decisions
MeetingDecisionOutcome
19 Oct 2026 Constitutional AmendmentsThat the proposed amendments to the Council’s ... view the full minutes text for item 30. Decided Open
19 Oct 2026 Audit & Governance MinutesThat the minutes of the Audit & Governance Committee meeting held on 29 June 2026 be noted. Noted Open
19 Oct 2026 Audit & Governance Committee Annual Report 2025/2026That the Audit & Governance Committee Annual Report 2025/2026 be noted. Noted Open
19 Oct 2026 Overview & Scrutiny Annual Report 2025/2026That the Annual Overview & Scrutiny Report 2025/2026 be noted. Noted Open
19 Oct 2026 Local Code of Corporate GovernanceThat the revised Local Code of Corporate Governance be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies