What was decided
Cabinet accepted the UK Government funding award and delegated signing of the Memorandum of Understanding to the Executive Director, Finance and Section 151 Officer. Report P3
Cabinet delegated authority to the Section 151 Officer to vary the Council's capital and revenue base budgets within the limits set out in Section 2 of the report for Pride in Place projects. Report P4
Cabinet delegated authority to the Executive Director, Economic Development to enter into all associated delivery contracts and grant funding agreements, in consultation with the Section 151 Officer and Deputy Leader. Report P7
Why
To enable the Council to receive annual funding allocations under the Pride in Place Programme and support the Boston Neighbourhood Board to progress delivery. Report P8
To ensure that all public funds are used lawfully, effectively and in line with Government rules and the Council's procedures. Report P8
To ensure transparent, consistent and robust decision making, with appropriate due diligence on recommended funding awards before contracting and expenditure. Report P8
What happens next
The Section 151 Officer will sign the Memorandum of Understanding received from the UK Government on 31st March 2026. Report P3, 2.1
The Boston Neighbourhood Board will consider and recommend how funding is allocated to individual projects, with Cabinet kept informed of priorities, allocations, spend profile, risks and benefits. Report P5, 1.2
A dedicated programme manager and programme coordinator (shared with the Spalding Neighbourhood Board) will be recruited to support delivery, with additional support from the Economic Development directorate and PSPS Ltd. Report P36
The money
up to £20million new grant funding for Boston over a ten-year period under Phase One of the Pride in Place Programme Report 1.1
19,535 Total funding across the ten years (revenue plus capital) as set out in the financial table Report P21
14,936 Total capital funding (grants) across the ten years Report P21
4,599 Total revenue funding (capacity and grants) across the ten years Report P21
600 Total revenue funding (capacity) across the ten years Report P21
3,999 Total revenue funding (grants) across the ten years Report P21
742 Total funding released in 26/27 (first year of delivery) Report P21
up to £80m Cumulative new investment for the South and East Lincolnshire Councils Partnership over the next ten financial years under the Pride in Place Programme Report P32
Options considered
Chosen: Accept the Pride in Place funding for Boston and delegate authorities to officers as set out in the report. Enables receipt of annual funding, supports the Neighbourhood Board and ensures lawful, transparent use of public funds. Report P8, P9
Rejected: Do not accept the Pride in Place funding for Boston Report P10
Rejected: Work with the Boston Neighbourhood Board to identify an alternative accountable body structure for the governance and management of the approved funding Report P10
Implications
Legal: The Council as accountable body must comply with the Subsidy Control Act 2022, public contract regulations, and the Nolan Principles and Managing Public Money principles. Report P39, P40, P50
Financial: The Section 151 Officer is authorised to vary the Council's capital and revenue base budgets within the limits set out in Section 2 of the report. Report P4, P43, P44
Staffing: Initial project management resources have been approved to recruit a dedicated programme manager and programme coordinator (shared with Spalding), with additional support from the Economic Development directorate and PSPS Ltd. Report P36
Risk: Five key risks have been identified for the programme: capacity, inclusive engagement, partnership, deliverability and accountability. Report P45
Other: The role of the local authority may change as the Neighbourhood Board is expected to move to a community-led delivery model by Year Three of the programme (March 2029). Report 3.2
Other: Boston, Skegness and Spalding are included in Phase One of the Programme; Mablethorpe is allocated under Phase Two, due to commence from April 2027. Report P32
Who and where
Residents, businesses and visitors of Boston town (within the agreed intervention boundary) Report 1.5, P32
Boston Neighbourhood Board, which will recommend project funding allocations Report 1.2, P5
Local community groups, businesses and other appropriately constituted organisations who may receive grant funding via passporting arrangements Report 2.8, 2.9
South and East Lincolnshire Councils Partnership area, which is due to receive up to £80m cumulatively Report P32
Boston Borough Council staff, including the Economic Development directorate and PSPS Ltd supporting delivery Report P36
Timeline
31st July 2025: Cabinet previously approved delivery arrangements for capacity funding under the programme Report 1.3, P66
25th September 2025: UK Government published the wider Pride in Place Strategy Report 1.1
13th November 2025: Cabinet approved the submission of the Neighbourhood Board's Regeneration Plan for Boston (also noted as 16th November 2025 in P66) Report 1.3, P66
31st March 2026: The Council received the Memorandum of Understanding from the UK Government Report 2.1
2026/27: First year of programme delivery Report 1.3, 3.2
2026-27 to 2029-30: Investment Period 1 (4 years) Report 2.5
2030-31 to 2032-33: Investment Period 2 (3 years) Report 2.5
2033-34 to 2035-36: Investment Period 3 (3 years) Report 2.5
by March 2029: Latest policy guidance expects the Neighbourhood Board to move to a community-led delivery model by Year Three Report 3.2
Plain English for the jargon
MoU: Memorandum of Understanding (the agreement between the UK Government and Boston Borough Council for the Pride in Place Programme)
Pride in Place Programme: UK Government funding programme formerly known as Plan for Neighbourhoods and Long Term Plan for Towns
Accountable body: The local authority responsible for ensuring that all expenditure is managed in line with public sector financial principles and compliant with procurement law and subsidy control requirements
Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of the Council's financial affairs
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76
Resolved
That the funding award for Boston be accepted and that authority be delegated to the Council’s Executive Director – Finance and Section 151 Officer to sign the Memorandum of Understanding for the Pride in Place Programme in Boston, as set out within Appendix A to the report; 2. That authority be delegated to the Executive Director – Finance and Section 151 Officer to vary the Council’s Capital and Revenue base budgets, within the limits set out in Section 2 within the report, for projects delivered under the Pride in Place programme for Boston; 3. That the Boston Neighbourhood Board be responsible for considering and recommending the allocation of funding to individual projects, with Cabinet be kept informed of the Board’s priorities, approved projects, funding allocations, expenditure profile, and the monitoring of risks and benefits on a regular basis; 4. That authority be delegated to the Council’s Executive Director ... view the full minutes text for item 76.
Word for word from the decision Boston published for this meeting.Source: democracy.boston.gov.uk
This paper seeks Cabinet approval to accept the UK Government’s Memorandum of Understanding to enable the local authority to undertake the lead contracting and accountable body requirements to progress delivery of the Pride in Place programme for Boston. It will ensure that the spend decisions recommended by the Boston Neighbourhood Board are subject to appropriate compliance and assurance work by the Council prior to contracting and meet the requirement to ensure effective and lawful use of the allocated public funds. Recommendations
That Cabinet
1. Accepts the funding award for Boston and delegates authority to the Council’s Executive Director – Finance and Section 151 Officer to sign the Memorandum of Understanding for the Pride in Place Programme in Boston, as attached at Appendix A;
2. Delegates authority to the Executive Director – Finance and Section 151 Officer to vary the Council’s Capital and Revenue base budgets up to the limits of the provisions set out in Section 2 of the report for projects under the parameters of the Pride in Place programme for Boston;
3. Notes that it is the responsibility of the Boston Neighbourhood Board to consider and recommend how the funding is allocated to individual projects. The Cabinet will be kept notified and updated with the Board’s priorities, approved projects, allocations and spend profile and monitoring of risks and benefits on regular basis;
4. Delegates authority to the Council’s Executive Director – Finance and Section 151 Officer to approve the Neighbourhood Board’s recommended expenditure, following due diligence and in consultation with the Executive Director – Economic Development and Deputy Leader of the Council; and
5. Delegates authority to the Council’s Executive Director – Economic Development to enter into all associated delivery contracts and grant funding agreements on behalf of the Council in consultation with the Council’s Executive Director – Finance and Section 151 Officer and the Deputy Leader of the Council.
Reasons for recommendations
• To enable the Council to receive the annual funding allocations under the Pride in Place Programme and support the Boston Neighbourhood Board to progress with the delivery of the subsequent investment periods. • To ensure that all public funds associated with the programme delivery are used lawfully, effectively and in line with Government rules and relevant Council procedures. • To ensure transparent, consistent and robust decision making and appropriate due diligence is undertaken on the recommended funding awards prior to formal contracting and expenditure.
Other Options Considered
• To not accept the Pride in Place funding for Boston • To work with the Boston Neighbourhood Board to identify an alternative accountable body structure for the governance and management of the approved funding 1. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Strategy / Policy Review and DevelopmentThat the policies and strategies listed in Appendix A be extended to 31 March 2028 where their current expiry date is...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.