Boston Borough Council
Cabinet, Tuesday 5 May 2026

Pride in Place Programme Delivery

Approved Executive 2 papers

AI summaryCabinet accepted a UK Government funding award of up to £20million over ten years for Boston's Pride in Place Programme and delegated authority to senior officers to sign the Memorandum of Understanding, vary budgets and enter into delivery contracts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Moneyup to £20millionover ten years from 2026/27 to 2035/36
What happens nextSign MoU, recruit programme staffSection 151 Officer to sign; programme manager and coordinator to be recruited
Who it affectsBoston town residents and businesseswithin the Pride in Place intervention boundary

What was decided

Cabinet accepted the UK Government funding award and delegated signing of the Memorandum of Understanding to the Executive Director, Finance and Section 151 Officer. Report P3

Cabinet delegated authority to the Section 151 Officer to vary the Council's capital and revenue base budgets within the limits set out in Section 2 of the report for Pride in Place projects. Report P4

Cabinet delegated authority to the Executive Director, Economic Development to enter into all associated delivery contracts and grant funding agreements, in consultation with the Section 151 Officer and Deputy Leader. Report P7

Why

To enable the Council to receive annual funding allocations under the Pride in Place Programme and support the Boston Neighbourhood Board to progress delivery. Report P8

To ensure that all public funds are used lawfully, effectively and in line with Government rules and the Council's procedures. Report P8

To ensure transparent, consistent and robust decision making, with appropriate due diligence on recommended funding awards before contracting and expenditure. Report P8

What happens next

The Section 151 Officer will sign the Memorandum of Understanding received from the UK Government on 31st March 2026. Report P3, 2.1

The Boston Neighbourhood Board will consider and recommend how funding is allocated to individual projects, with Cabinet kept informed of priorities, allocations, spend profile, risks and benefits. Report P5, 1.2

A dedicated programme manager and programme coordinator (shared with the Spalding Neighbourhood Board) will be recruited to support delivery, with additional support from the Economic Development directorate and PSPS Ltd. Report P36

The money

  • up to £20million new grant funding for Boston over a ten-year period under Phase One of the Pride in Place Programme Report 1.1
  • 19,535 Total funding across the ten years (revenue plus capital) as set out in the financial table Report P21
  • 14,936 Total capital funding (grants) across the ten years Report P21
  • 4,599 Total revenue funding (capacity and grants) across the ten years Report P21
  • 600 Total revenue funding (capacity) across the ten years Report P21
  • 3,999 Total revenue funding (grants) across the ten years Report P21
  • 742 Total funding released in 26/27 (first year of delivery) Report P21
  • up to £80m Cumulative new investment for the South and East Lincolnshire Councils Partnership over the next ten financial years under the Pride in Place Programme Report P32

Options considered

  • Chosen: Accept the Pride in Place funding for Boston and delegate authorities to officers as set out in the report. Enables receipt of annual funding, supports the Neighbourhood Board and ensures lawful, transparent use of public funds. Report P8, P9
  • Rejected: Do not accept the Pride in Place funding for Boston Report P10
  • Rejected: Work with the Boston Neighbourhood Board to identify an alternative accountable body structure for the governance and management of the approved funding Report P10

Implications

  • Legal: The Council as accountable body must comply with the Subsidy Control Act 2022, public contract regulations, and the Nolan Principles and Managing Public Money principles. Report P39, P40, P50
  • Financial: The Section 151 Officer is authorised to vary the Council's capital and revenue base budgets within the limits set out in Section 2 of the report. Report P4, P43, P44
  • Staffing: Initial project management resources have been approved to recruit a dedicated programme manager and programme coordinator (shared with Spalding), with additional support from the Economic Development directorate and PSPS Ltd. Report P36
  • Risk: Five key risks have been identified for the programme: capacity, inclusive engagement, partnership, deliverability and accountability. Report P45
  • Other: The role of the local authority may change as the Neighbourhood Board is expected to move to a community-led delivery model by Year Three of the programme (March 2029). Report 3.2
  • Other: Boston, Skegness and Spalding are included in Phase One of the Programme; Mablethorpe is allocated under Phase Two, due to commence from April 2027. Report P32

Who and where

  • Residents, businesses and visitors of Boston town (within the agreed intervention boundary) Report 1.5, P32
  • Boston Neighbourhood Board, which will recommend project funding allocations Report 1.2, P5
  • Local community groups, businesses and other appropriately constituted organisations who may receive grant funding via passporting arrangements Report 2.8, 2.9
  • South and East Lincolnshire Councils Partnership area, which is due to receive up to £80m cumulatively Report P32
  • Boston Borough Council staff, including the Economic Development directorate and PSPS Ltd supporting delivery Report P36

Timeline

  • 31st July 2025: Cabinet previously approved delivery arrangements for capacity funding under the programme Report 1.3, P66
  • 25th September 2025: UK Government published the wider Pride in Place Strategy Report 1.1
  • 13th November 2025: Cabinet approved the submission of the Neighbourhood Board's Regeneration Plan for Boston (also noted as 16th November 2025 in P66) Report 1.3, P66
  • 31st March 2026: The Council received the Memorandum of Understanding from the UK Government Report 2.1
  • 2026/27: First year of programme delivery Report 1.3, 3.2
  • 2026-27 to 2029-30: Investment Period 1 (4 years) Report 2.5
  • 2030-31 to 2032-33: Investment Period 2 (3 years) Report 2.5
  • 2033-34 to 2035-36: Investment Period 3 (3 years) Report 2.5
  • by March 2029: Latest policy guidance expects the Neighbourhood Board to move to a community-led delivery model by Year Three Report 3.2

Plain English for the jargon

  • MoU: Memorandum of Understanding (the agreement between the UK Government and Boston Borough Council for the Pride in Place Programme)
  • Pride in Place Programme: UK Government funding programme formerly known as Plan for Neighbourhoods and Long Term Plan for Towns
  • Accountable body: The local authority responsible for ensuring that all expenditure is managed in line with public sector financial principles and compliant with procurement law and subsidy control requirements
  • Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of the Council's financial affairs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76

Resolved

That the funding award for Boston be accepted and that authority be delegated to the Council’s Executive Director – Finance and Section 151 Officer to sign the Memorandum of Understanding for the Pride in Place Programme in Boston, as set out within Appendix A to the report; 2. That authority be delegated to the Executive Director – Finance and Section 151 Officer to vary the Council’s Capital and Revenue base budgets, within the limits set out in Section 2 within the report, for projects delivered under the Pride in Place programme for Boston; 3. That the Boston Neighbourhood Board be responsible for considering and recommending the allocation of funding to individual projects, with Cabinet be kept informed of the Board’s priorities, approved projects, funding allocations, expenditure profile, and the monitoring of risks and benefits on a regular basis; 4. That authority be delegated to the Council’s Executive Director ... view the full minutes text for item 76.
Word for word from the decision Boston published for this meeting. Source: democracy.boston.gov.uk

Follow this further

Built from Boston's papers

What the report saysPro

Report to Cabinet, 8 pages

Summary

This paper seeks Cabinet approval to accept the UK Government’s Memorandum of Understanding to enable the local authority to undertake the lead contracting and accountable body requirements to progress delivery of the Pride in Place programme for Boston. It will ensure that the spend decisions recommended by the Boston Neighbourhood Board are subject to appropriate compliance and assurance work by the Council prior to contracting and meet the requirement to ensure effective and lawful use of the allocated public funds. Recommendations

That Cabinet

1. Accepts the funding award for Boston and delegates authority to the Council’s Executive Director – Finance and Section 151 Officer to sign the Memorandum of Understanding for the Pride in Place Programme in Boston, as attached at Appendix A;

2. Delegates authority to the Executive Director – Finance and Section 151 Officer to vary the Council’s Capital and Revenue base budgets up to the limits of the provisions set out in Section 2 of the report for projects under the parameters of the Pride in Place programme for Boston;

3. Notes that it is the responsibility of the Boston Neighbourhood Board to consider and recommend how the funding is allocated to individual projects. The Cabinet will be kept notified and updated with the Board’s priorities, approved projects, allocations and spend profile and monitoring of risks and benefits on regular basis;

4. Delegates authority to the Council’s Executive Director – Finance and Section 151 Officer to approve the Neighbourhood Board’s recommended expenditure, following due diligence and in consultation with the Executive Director – Economic Development and Deputy Leader of the Council; and

5. Delegates authority to the Council’s Executive Director – Economic Development to enter into all associated delivery contracts and grant funding agreements on behalf of the Council in consultation with the Council’s Executive Director – Finance and Section 151 Officer and the Deputy Leader of the Council.

Reasons for recommendations

• To enable the Council to receive the annual funding allocations under the Pride in Place Programme and support the Boston Neighbourhood Board to progress with the delivery of the subsequent investment periods. • To ensure that all public funds associated with the programme delivery are used lawfully, effectively and in line with Government rules and relevant Council procedures. • To ensure transparent, consistent and robust decision making and appropriate due diligence is undertaken on the recommended funding awards prior to formal contracting and expenditure.

Other Options Considered

• To not accept the Pride in Place funding for Boston • To work with the Boston Neighbourhood Board to identify an alternative accountable body structure for the governance and management of the approved funding 1. Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pride in Place for Boston: Memorandum of UnderstandingAppendix A 7 pages Download
PDF
Pride in Place Programme DeliveryReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
DB
Councillor Dale BroughtonLeader, present
MG
Councillor Mike GilbertDeputy Leader, present
JB
Councillor John BaxterCommittee Member, present
CB
Councillor Callum ButlerCommittee Member, present
SG
Councillor Sandeep GhoshCommittee Member, present
CM
Councillor Chris MountainCommittee Member, present
CR
Councillor Claire RylottCommittee Member, present
SS
Councillor Sarah SharpeCommittee Member, present
HS
Councillor Helen StaplesCommittee Member, apologies
RB
Rob BarlowOfficer, in attendance
PP
Pranali ParikhOfficer, in attendance, virtual
MC
Maria CottonOfficer, in attendance

All 13 on the meeting page

On this subject at Boston

Search all
  1. Pride in Place Programme DeliveryThis decision
  2. Pride in Place Impact FundAgreed

More from Boston Cabinet

All decisions
MeetingDecisionOutcome
24 Jun 2026 Draft Outturn 2025/26That the draft outturn revenue position of a £0.064m underspend for 2025/26, as detailed in Appendix A – Table 1 with... Noted Open
24 Jun 2026 Local Council Tax Support Scheme 2027/28 - ConsultationThat the consultation to retain the current scheme, updated in line with the Department for Work and Pension (DWP) an... Approved Open
24 Jun 2026 South & East Lincolnshire Destination Management PlanThat the South & East Lincolnshire Destination Management Plan 2026 – 2030, attached in Appendix A to the report, be ... Approved Open
24 Jun 2026 Public Spaces Protection Order for Dog ControlsThat, after taking into account the consultation feedback, the proposal to extend the Public Spaces Protection Order ... Approved Open
24 Jun 2026 Strategy / Policy Review and DevelopmentThat the policies and strategies listed in Appendix A be extended to 31 March 2028 where their current expiry date is... Decided Open