CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Boston Borough Council
Annual Meeting, Full Council, Monday 18 May 2026

South & East Lincolnshire Councils Partnership Performance Report and Memorandum of Agreement (MOA)

Noted Committee 2 papers

AI summaryBoston Borough Council approved an updated Memorandum of Agreement for the South & East Lincolnshire Councils Partnership, subject to other partner councils' agreement, and noted partnership progress including £277,894,888 in external funding secured since 2020.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSubject to other partnership councils' agreement
Money£277,894,888 total external fundingSecured across all three councils since August 2020
What happens nextExecutive Director to sign revised AgreementDelegated authority to replace previous agreement
Who it affectsNot stated

What was decided

The Full Council noted the South & East Lincolnshire Councils Partnership performance report. Report P2

Council approved the updated Memorandum of Agreement, subject to agreement by the other Partnership Councils. Report P3

Authority was delegated to the Executive Director for Programme Delivery to sign the revised Agreement on behalf of the Council. Report P3

Why

To monitor and report on the progress of the Partnership, which launched on 1st October 2021 and is now embedded. Report P4, 1.1, P5

To update the Memorandum of Agreement in response to feedback from the 2024 Partnership Scrutiny, including changes to the Joint Strategy Board approval process and scrutiny arrangements. Report P5, P63

The option of not updating the Memorandum of Agreement was discounted because a review was considered necessary following the 2024 annual Partnership scrutiny. Report P7

What happens next

Pending agreement from East Lindsey and South Holland councils, the Executive Director for Programme Delivery will sign the revised Agreement, replacing the previous one. Report P3, P96

Partnership performance reports to Council will move from six monthly to annually, and the termination and withdrawal period is extended from 12 to 18 months. Report P63

Bids will be submitted to Sport England for each Council area over the next 6 months, and a new Agency Agreement with Parkwood started on 1st April. Report P38, P40

The money

  • £277,894,888 Total external funding secured across all three Partnership councils since August 2020 Report P14
  • £22,200,000 Funding secured for Boston Borough Council in 2020/21 Report P14
  • £2,811,466 Funding secured for Boston Borough Council in 2025/26 Report P14
  • £42m Financial efficiencies identified in the Partnership Business Case as achievable Report 2.4
  • £47,333,486 Cashable and non-cashable efficiencies achieved to end of March 2026 Report 2.5, P24
  • £14million Cost of the new TEC College in Skegness, completed September 2025 Report P29

Options considered

  • Chosen: Approve the updated Memorandum of Agreement. A review and updating of the Agreement were considered necessary following the 2024 annual Partnership scrutiny. Report P3, P7
  • Rejected: Do not update the Memorandum of Agreement. A review and updating of the Agreement were considered necessary following the 2024 annual Partnership scrutiny. Report P7

Implications

  • Legal: The constitutional and legal arrangements for the Partnership have been approved by all three partner Councils; a new clause at 10.8 states the Partnership will cease to exist if the Councils cease to exist as legal Local Government entities. Report P75, P63
  • Other: No specific staffing, financial, data protection, risk, contracts, equality or safeguarding implications were identified in this report. Report P71, P73, P77, P79, P80, P85, P89
  • Other: The Partnership is preparing for Local Government Reorganisation in Greater Lincolnshire, which indications suggest will still take place in early 2028, with the Government's chosen model likely known before the summer Parliamentary recess. Report 4.7, 4.8

Who and where

  • Boston Borough Council, East Lindsey District Council and South Holland District Council (the three Partnership Councils) Report 1.1
  • Residents across the South & East Lincolnshire sub-region, including those targeted by skills and health programmes Report P29, 3.3
  • Community Safety Partnership partners including Lincolnshire Police, Probation Service and Community Safety Officers Report 3.4, P44
  • Boston Community Safety Officers who delivered over 750 hours of patrols Report P44

Timeline

  • 1st October 2021: South & East Lincolnshire Councils Partnership launched Report 1.1
  • 2024: Partnership Scrutiny undertaken, recommending review of the Memorandum of Agreement Report P5, 5.6
  • September 2025: Completion of new £14million TEC College in Skegness Report P29
  • January 2026: TEC College officially opened Report P29
  • February 2026: South & East Lincolnshire Community Safety Partnership meeting held Report P42
  • March 2026: The Mayflower learning centre in Boston officially opened by Boston College Report P29
  • End of March 2026: Efficiencies of £47,333,486 achieved against £42m Business Case target Report 2.5, P24
  • 1st April (year not specified, context suggests 2026): New Agency Agreement with Parkwood commenced Report P40
  • Before summer Parliamentary recess (year not specified): Government's chosen model for Reorganisation in Greater Lincolnshire likely to be known Report 4.7
  • Early 2028: Local Government Reorganisation indications suggest it will still take place Report 4.8

Plain English for the jargon

  • MOA: Memorandum of Agreement, the document underpinning how the three partner councils work together.
  • SELCP: South and East Lincolnshire Councils Partnership.
  • ADP: Alignment and Delivery Plan, which sets out the Partnership's activities.
  • UKSPF: UK Shared Prosperity Fund, a central government funding stream.
  • LGR: Local Government Reorganisation, the planned restructuring of councils.
  • SELCAN: South and East Lincolnshire Climate Action Network.
  • HLB: Healthy Living Board, providing strategic oversight on health inequalities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the report be noted; 2. That, subject to agreement by the other Partnership Councils, the updated Memorandum of Agreement for the South & East Lincolnshire Councils Partnership (Appendix A within the report) be approved; and 3. That authority be delegated to the Executive Director – Programme Delivery to sign the revised Agreement on behalf of the Council, to replace the previous agreement.
Word for word from the decision Boston published for this meeting. Source: democracy.boston.gov.uk

Follow this further

Built from Boston's papers

What the report saysPro

Report to Annual Meeting, Full Council, 11 pages

Summary

This report sets out the progress of the South & East Lincolnshire Councils Partnership since the last update in Autumn 2025.

Recommendations

1. That the content of this report in respect of the progress of the South & East Lincolnshire Councils Partnership be noted; and

2. That subject to agreement by the other Partnership Councils, Council approves the updated Memorandum of Agreement for the South & East Lincolnshire Councils Partnership (Appendix A) and delegates authority to Executive Director (Programme Delivery) for Boston to sign the revised Agreement on behalf of this Council. The new Agreement, upon signing, will replace the previous Agreement. Reasons for Recommendations

• To monitor and report on the progress of the Partnership.

• To update the Memorandum of Agreement to reflect the Partnership is now embedded and in response to feedback from the Partnership Scrutiny undertaken in 2024.

Other Options Considered

• To not update the Memorandum of Agreement – discounted. A review and updating of the Agreement were considered necessary following the 2024 annual Partnership scrutiny.

Background

1.1The South & East Lincolnshire Councils Partnership (Boston Borough Council, East Lindsey District Council and South Holland District Council) launched on 1st October 2021.

1.2This report sets out the progress of the Partnership since the last update in Autumn 2025.

2. Alignment and Delivery Plan (ADP)

2.1Progress of Alignment and Delivery Plan activity is being monitored by Joint Strategy Board to support the Partnership in delivering on its priorities, as well as sovereign Council ambitions.

2.2For the year 2025/26, of the 102 activities in the ADP for the year, 81% were completed, or on track if a multi-year action. Delivery is being managed by Service Directors and corporate monitoring.

Funding secured BBC ELDC SHDC COMBINED since August 2020

2020/21 £22,200,000 £48,718,578 £8,300,000 £79,218,578 2021/22 £3,395,318 £5,068,169 £2,397,892 £10,861,379 2022/23 £17,704,882 £13,766,960 £22,234,304 £53,706,146 2023/24 £7,386,953 £24,368,636 £13,455,393 £45,210,982 2024/25 £20,680,797 £28,505,595 £3,581,838 £52,432,508 2025/26 £2,811,466 £25,833,400 £7,402,429 £36,465,294 TOTAL £74,179,415 £146,261,338 £57,371,856 £277,894,888 2.3 A key element of the plan is securing external funding. The table below sets out external funding secured since August 2020 by sovereign Council and in total for the Partnership. Recent grant awards cover a range of initiatives, including funding for Pride in Place, Extended Producer Responsibility and Household Support Fund.

2.4The Partnership Business Case identified that £42m in financial efficiencies could be derived from the 3 Councils working together. The graph shows the financial efficiencies - both cashable and non-cashable - that have been identified so far (to the end of March 2026).

SELCP £42m Savings Tracker - cashable and non- £50,000,000 cashable £40,000,000

£30,000,000

£20,000,000

£10,000,000

£0 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 30/31 31/32

2.5The blue line on the graph shows the target in the Partnership’s Business Case. The orange bars show where the Partnership is against that target. This shows that the Partnership is already on track to achieve the efficiency savings up to £47,333,486 Additional efficiencies for future years will be added as they are identified through matters such as contract reviews and service reviews.

SAVINGS PROFILE – CASHABLE AND NON-CASHABLE TARGET TOTAL ALLIANCE 20/21 £600,000 £872,415 21/22 £1,200,000 £2,440,787 SOUTH & EAST LINCOLNSHIRE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Memorandum of AgreementAppendix A 24 pages Download
PDF
South & East Lincolnshire Councils Partnership Performance Report and Memorandum of Agreement (MOA)Report 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

26 of 36 attended
JN
Councillor Jonathan NobleMayor, present
JC
Councillor James CantwellDeputy Mayor, present
AA
Councillor Alison AustinCommittee Member, present
RA
Councillor Richard Austin BEMCommittee Member, present
JB
Councillor John BaxterCommittee Member, present
PB
Councillor Peter BedfordCommittee Member, present
DB
Councillor David BrownCommittee Member, present
DB
Councillor Dale BroughtonCommittee Member, present
CB
Councillor Callum ButlerCommittee Member, present
EC
Councillor Emma CresswellCommittee Member, present
AD
Councillor Anton DaniCommittee Member, present
AD
Councillor Anne DorrianCommittee Member, apologies

All 36 on the meeting page

On this subject at Boston

Search all
  1. South & East Lincolnshire Councils Partnership Performance Report and Memorandum of Agreement (MOA)This decision
  2. Reserve Sites Policy in the South East Lincolnshire Local PlanApproved
  3. South & East Lincolnshire Destination Management PlanApproved
  4. South and East Lincolnshire Traditional Building Design GuideApproved
  5. Terms and Conditions alignment across the South & East Lincolnshire Councils PartnershipApproved
  6. South & East Lincolnshire Community Safety StrategyNoted

More from Boston Annual Meeting, Full Council

All decisions
MeetingDecisionOutcome
18 May 2026 To Elect the MayorThat Councillor Jonathan Noble be elected Mayor of the Borough of Boston to hold office until the next Annual Meeting... Decided Open
18 May 2026 To Elect the Deputy MayorThat Councillor James Cantwell be elected Deputy Mayor of the Borough of Boston to hold office until the next Annual ... Decided Open
18 May 2026 Vote of Thanks to the Retiring MayorThat the best of thanks of the Council be extended to Councillor Barrie Pierpoint for his term of office as Mayor, an... Decided Open
18 May 2026 Vote of Thanks to the Retiring Deputy MayorThat the best of thanks of the Council be extended to Councillor Patsie Marson for her term of office as Deputy Mayor... Decided Open
18 May 2026 Democratic Arrangements 2026/27That the establishment of Committees, Sub-Committees, Panels and Working Groups for the municipal year 2026/27, inclu... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies