RESOLVED that:- (a) a review of the management arrangements for public leisure centres within BCP be supported; (b) the allocation of £20k from existing service revenue budgets to procure a specialist leisure consultant to support the review be approved; and (c) it was noted that current agreements may need to be extended until future management arrangements are approved. Voting: Unanimous Portfolio Holder: Tourism, Leisure and Communities Following LGR there is an opportunity to review the current arrangements for the management of leisure centres with the aims of: · Improving the offer to local people by providing consistencies in facility provision & service standards · Making the services more accessible and transparent · Standardising building and maintenance responsibilities · Reducing BCP subsidies and liabilities · Streamlining management arrangements · Enabling continued investment
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Report subject Review of Leisure Centre Management
Meeting date 15 January 2020
Status Public Report
Executive summary The purpose of this report is to seek approval to undertake a review of the management arrangements for public leisure centres within BCP.
BCP Council owns 8 leisure centres which are currently operated under four different models of management and a variety of lease and contractual arrangements. The review would focus primarily on future arrangements at Ashdown, Poole (Dolphin), Rossmore and 2Riversmeet Leisure Centres, due to the length of existing arrangements at other sites.
The review would explore the options to generate capital investment to improve facilities and revenue savings for leisure, whilst providing a service that integrates with health and wellbeing through prevention at scale generating longer term savings elsewhere for the Council.
Recommendations It is RECOMMENDED that Cabinet:
(a) Support a review of the management arrangements for public leisure centres within BCP. (b) Approves the allocation of £20k from existing service revenue budgets to procure a specialist leisure consultant to support the review. (c) Note that current agreements may need to be extended until future management arrangements are approved.
Reason for Following LGR there is an opportunity to review the current recommendations arrangements for the management of leisure centres with the aims of: Improving the offer to local people by providing consistencies in facility provision & service standards Making the services more accessible and transparent Standardising building and maintenance responsibilities Reducing BCP subsidies and liabilities Streamlining management arrangements Enabling continued investment Portfolio Holder(s): Councillor Lewis Allison (Portfolio Holder Tourism, Leisure & Communities)
Corporate Director Bill Cotton (Corporate Director Regeneration and Economy)
Contributors Anthony Rogers (Head of Leisure)
Wards All
Classification For Decision
Background 1. BCP Council owns eight leisure centres, details of which are summarised in Table 1 below. The centres are a vital component of the sports and leisure infrastructure in the area enabling residents and visitors to lead active healthy lifestyles and participate in a wide range of sports and recreation activities. Appendix 1 provides further details of the facilities and services available at each site. 2. The centres provide a wide range of services using a mix of indoor, outdoor or water- based facilities. They are extensively used by local people and welcome more than 3.5 million residents and visitors each year. 3. They are operated under four different models of management and a variety of lease and contractual arrangements. In-house, local and national operators provide the services on behalf of BCP Council and there are differences in financial arrangements and building liabilities with each model.
Table 1 : BCP Leisure Centres
Area Bournemouth Christchurch Poole Leisure centres Littledown 2 Riversmeet Ashdown The Junction, Broadstone Pelhams Rossmore Stokewood Poole (Dolphin)
Operator BH Live In house Everyone YMCA Active (SLM Ltd) Tenancy Lease + n/a Lease + Lease agreement Contract Contract End date 2035 n/a 2021 2068
Approx. annual 1.8m 0.3m 1.1m 0.3m visits Focus of the Review
4. The tenancy agreements with BH Live and YMCA both have a minimum of 16 years left until they expire. The primary focus of the review therefore will be to determine the future management arrangements for the three leisure centres in Poole managed by Everyone Active (SLM Ltd) and 2Rivermeet Leisure Centre (2RM) in Christchurch, which is currently managed in-house by BCP Council (Leisure). 5. Should Cabinet decide to support the review, the options for future management arrangements for leisure centres in Christchurch and Poole could include:
Option Description Christchurch Poole (2RM) (Ashdown, Dolphin, Rossmore)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.