RESOLVED that the application be granted planning permission in line with the recommendation as set out in the report with an amendment to Condition 2 to read as follows: Condition 2: Unless otherwise agreed in writing by the mineral planning authority, no development shall be carried out other than in strict accordance with the approved plans, schemes and details submitted as part of the original planning application number: 8/2001/0192; plans and details approved under planning permission 8/16/2011, as listed below; and other plans and details approved under the requirements of these conditions. DRG No: 347D 01-01 Location Plan Drawing No. ST1 4939 -002 Plant Site Area Approved Hydrology Details The development shall be carried out in full accordance with the approved plans, schemes and details for the duration of this permission. Reason: To manage the development in the interests of ensuring that the permission is implemented correctly thereby avoiding, reducing or mitigating the environmental effects of the development having regard to: Policies SS1; SS2; AS1; CC1; RS1; RS2; DM1; DM2; DM3; DM4; DM5; DM7; DM8; DM9and Policy DM10 of the Bournemouth, Dorset and Poole Minerals Strategy; and Policies 1; 16; 12 and 8 of the Bournemouth, Christchurch, Poole and Dorset Waste Plan 2019 Voting: For - Unanimous
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Application Address Hurn Quarry Hurn Court Lane Christchurch BH23 6AX
Proposal Extension to sand and gravel extraction at Hurn Quarry followed by filling with imported inert materials and restoration - Variation of Condition 1 (Time limit - Commencement of Development) and Condition 6 (Pre- Commencement - Archaeology) of App 8/16/2010/DCC to - Extend the end date of Hurn Quarry to support the restoration of the Western Extension.
Application Number 8/20/0016/CONDR
Applicant [name removed] [name removed] Application Valid 6 January 2020
Decision Due Date 2 March 2020
Extension of Time Date (if applicable)
Ward Commons
Report status Public
Meeting date 13th August 2020
Recommendation Grant, subject to conditions
Reason for Referral to The application is referred to Committee by Cllr Phipps on Planning Committee the following grounds;
Saved Policies Christchurch Local Plan ENV2 and ENV3 apply to potential noise issues from 24 hour running of generator to pump ground water away from development
Policy HE3 Christchurch Core Strategy, potential landscape and mature tree issues relating to routing of water run off from pumping ground water away from development
Policies ME6 and ME7 Christchurch Core Strategy, route of pumped water run off from the development could cause localised flooding which is not addressed in the application
Case Officer Kim Bowditch Title:
Description of Development 1. Extension to sand and gravel extraction at Hurn Quarry followed by filling with imported inert materials and restoration - Variation of Condition 1 (Time limit - Commencement of Development) and Condition 6 (Pre-Commencement - Archaeology) of App 8/16/2010/DCC to - Extend the end date of Hurn Quarry to support the restoration of the Western Extension.
Proposal Extension to sand and gravel extraction at Hurn Quarry, Dorset, followed by filling with imported materials and restoration - the deletion of condition 3 (Limit and Depth of Extraction) of App. No. 8/16/2011/DCC to avoid the sterilization of 305,168 tonnes of sub-groundwater mineral and the variations of condition 2 (Development to be in accordance with approved plans) and condition 18 (Throughput and type of waste) to adopt a revised scheme of working and the volume of imported restoration materials.
Application Number 8/20/0017/CONDR
Applicant [name removed] [name removed] Application Valid 6 January 2020
Decision Due Date 2 March 2020
Extension of Time Date (if applicable)
Ward Commons
Report status Public
Meeting date 13th August 2020
Recommendation Grant, subject to conditions
Reason for Referral to The application is referred to Committee by Councillor Planning Committee Phipps on the grounds of;
Saved Policies Christchurch Local Plan ENV2 and ENV3 apply to potential noise issues from 24 hour running of generator to pump ground water away from development
Policy HE3 Christchurch Core Strategy, potential landscape and mature tree issues relating to routing of water run off from pumping ground water away from development
Policies ME6 and ME7 Christchurch Core Strategy, route of pumped water run off from the development could cause localised flooding which is not addressed in the application
Case Officer Kim Bowditch Title:
Description of Development 2. Extension to sand and gravel extraction at Hurn Quarry, Dorset, followed by filling with imported materials and restoration - the deletion of condition 3 (Limit and Depth of Extraction) of App. No. 8/16/2011/DCC to avoid the sterilization of 305,168 tonnes of sub-groundwater mineral and the variations of condition 2 (Development to be in accordance with approved plans) and condition 18 (Throughput and type of waste) to adopt a revised scheme of working and the volume of imported restoration materials.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning Committee at Bournemouth, Christchurch and Poole and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.