RESOLVED that Cabinet:- (a) Authorises the Chief Executive, in consultation with the Leader and Deputy Leader, to procure and review advice from external consultants and to recommend to Cabinet as appropriate the creation of suitable structures to accelerate the delivery of regeneration projects, including the creation of structures or mechanisms to deliver the development of sites; and (b) Notes that reports will be brought to future Cabinet and Council meetings as appropriate setting out proposals for the use of the Futures Fund and the process for bringing forward individual sites for development. Voting: Unanimous Portfolio Holder: Regeneration, Economy and Strategic Planning To enable greater focus and corporate grip on realising opportunities for delivering homes and jobs on sites owned or controlled by the council and increasing the scale and pace of delivery. The internal management of site delivery is too small in scale to deliver the ambitions set out in the Big Plan which was considered by Cabinet and Council in February.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Report subject The Future of Regeneration in Bournemouth, Christchurch and Poole
Meeting date 10 March 2021
Status Public Report
Executive summary This report summarises the opportunities and the Council’s ambitions for regeneration in the BCP area. It seeks to strengthen the Council’s capacity to deliver, setting out an approach for reviewing and progressing the available options to realise those opportunities and ambitions. The report sets out the options for increasing our regeneration delivery capacity, working with an urban regeneration company and other forms of partnerships as well as sourcing external consultancy input.
Recommendations It is RECOMMENDED that Cabinet:
1. Authorises the Chief Executive, in consultation with the Leader and Deputy Leader, to procure and review advice from external consultants and to recommend to Cabinet as appropriate the creation of suitable structures to accelerate the delivery of regeneration projects, including the creation of structures or mechanisms to deliver the development of sites. 2. Notes that reports will be brought to future Cabinet and Council meetings as appropriate setting out proposals for the use of the Futures Fund and the process for bringing forward individual sites for development.
Reason for To enable greater focus and corporate grip on realising recommendations opportunities for delivering homes and jobs on sites owned or controlled by the council and increasing the scale and pace of delivery. The internal management of site delivery is too small in scale to deliver the ambitions set out in the Big Plan which was considered by Cabinet and Council in February. Portfolio Holder(s): Councillor Drew Mellor, Councillor Philip Broadhead
Corporate Director Bill Cotton
Report Authors Graham Farrant
Wards Council-wide
Classification For Decision Title:
Background 1. BCP Council has a significant regeneration agenda and the level of investment expected into sites across the BCP area exceeds £3 billion, with the gross development of value of Council-owned sites alone nearing £1bn. This includes a range of sites owned by the Council, both small sites, largely on land managed under the Housing Revenue Account (HRA) for the development of less than 10 homes and significant sites of regional interest including the former power station site at Holes Bay which could deliver 800+ new homes in a new community. There are also significant redevelopment opportunities in the town centres, most notably in Poole town centre and on other significant sites such as Wessex Fields. 2. Historically the capacity of the Council, and the preceding councils, has not been sufficient to deliver these sites at pace and the skills have not been available in- house to project manage the delivery of regeneration at this scale. The preceding councils, whilst introducing some innovative partnership structures such as the Bournemouth Development Company (BDC), and the Council’s wholly owned Seascape Homes and Property Limited, were not able to bring sufficient capacity to bear to deliver all of the regeneration opportunities at scale and with the pace that is sought.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.