RESOLVED that Cabinet: - (a) approves the further allocation of £750,000 to complete the conversion of the Bournemouth Learning Centre; and (b) requests the Chief Executive to use the urgency powers delegated to him under Part 3.15 of the BCP Council Constitution to approve the combined spend on this project of £1,250,000 in advance of the next available Council meeting, scheduled for 2 June 2021 and that he report this decision to Council at that meeting, in order for the additional school places to be available for eligible children by September 2021. Voting: Unanimous Portfolio Holder: Covid Resilience, Public Health and Education To enable the completion of the project at the BLC site to create a high quality special school satellite provision for Longspee Special School, meeting local need and reducing pressure on the high needs budget.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Report subject Special Educational Needs and Disability Capital Investment – Expansion of Longspee Special School at the Bournemouth Learning Centre
Meeting date 14 April 2021
Status Public Report
Executive As part of the Council’s commitment to pupils with special summary educational needs and disabilities (SEND), Cabinet in June 2020 approved £500,000 to re-purpose the former Bournemouth Learning Centre (BLC) building as a satellite site for Longspee Special School. The Council has a duty to ensure a sufficiency of school places in its area under s14 of the Education Act 1996. After that original cost estimate, and as a result of the procurement process carried out by the Council’s partner, the Ambitions Academies Trust, the total cost of the capital works amounts to £1,250,000, leaving a shortfall of £750,000 which the Council intends to meet in order to ensure the extra places are available for September 2021. Funding is available to meet the shortfall. The reasons for the shortfall, set out in the report, include unforeseen works due to the poor condition of the building and the need to increase the specification in order to be able to take on roll children and young people with the broadest range of needs. The project still represents exceptional value for money as the cost of each place will be more than 40% below the national average and as a result of not needing so many independent placements, the council will make a revenue saving in the region of £1.2 million annually.
Recommendations It is RECOMMENDED: 1. That Cabinet approves the further allocation of £750,000 to complete the conversion of the Bournemouth Learning Centre; 2. That Cabinet requests the Chief Executive to use the urgency powers delegated to him under Part 3.15 of the BCP Council Constitution to approve the combined spend on this project of £1,250,000 in advance of the next available Council meeting, scheduled for 2 June 2021 and that he report this decision to Council at that meeting, in order for the additional school places to be available for eligible children by September 2021;.
Reason for To enable the completion of the project at the BLC site to create recommendations a high quality special school satellite provision for Longspee Special School, meeting local need and reducing pressure on the high needs budget.
Portfolio Holder(s): Councillor Nicola Greene, Portfolio Holder for Covid Resilience, Public Health and Education
Corporate Director Elaine Redding - Interim Corporate Director, Children’s Services
Report Author Simon McKenzie, Head of Service, Special Educational Needs and Disability
Wards All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.