RESOLVED that: - Cabinet approved the Traffic Regulation Orders as advertised to enable the order to be made, sealed and to implement the restrictions which are outlined in this report and appendices. Voting: Unanimous Portfolio Holders: Climate Response, Environment and Energy Leader of the Council and Portfolio Holder for Dynamic Places Deputy Leader of the Council and Portfolio Holder for Connected Communities To approve the making and sealing of the Orders. This will enable the implementation of new and amended traffic restrictions on the following roads in Highcliffe: · Field Way · Forest Way · Parkside · Smugglers Lane North · Smugglers Lane South · Woodfield Gardens The above are required to facilitate the delivery of safer routes to school access improvements and reduce conflict in the area around the school and improve walking and cycling for pupils at key locations and the wider community. In taking this decision regard has been had to the council’s duty under section 122 of the Road Traffic Regulation Act 1984. Support and Objections have been received, which are outlined in Appendix 2.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Report subject Traffic Regulation Orders for Highcliffe School Area - P35 2023
Meeting date 26 July 2023
Status Public Report
Executive summary The proposals aim is to improve safety for pupils, parents/carers, staff and residents by introducing various parking changes at key points in the Highcliffe School area. It is hoped that this will in turn encourage walking and cycling to the school meeting corporate and Local Transport Plan objectives to encourage sustainable travel choices and improve safety.
Recommendations It is RECOMMENDED that:
Cabinet approve the Traffic Regulation Orders as advertised to enable the order to be made, sealed and to implement the restrictions which are outlined in this report and appendices.
Reason for To approve the making and sealing of the Orders. This will enable recommendations the implementation of new and amended traffic restrictions on the following roads in Highcliffe: Field Way Forest Way Parkside Smugglers Lane North Smugglers Lane South Woodfield Gardens The above are required to facilitate the delivery of safer routes to school access improvements and reduce conflict in the area around the school and improve walking and cycling for pupils at key locations and the wider community. In taking this decision regard has been had to the council’s duty under section 122 of the Road Traffic Regulation Act 1984. Support and Objections have been received, which are outlined in Appendix 2. Portfolio Holder(s): Councillor Vikki Slade - Leader of the Council and Portfolio Holder for Dynamic Places Councillor Millie Earl - Deputy Leader of the Council and the Portfolio Holder for Connected Communities Councillor Andy Hadley - Portfolio Holder for Climate Response, Environment and Energy
Corporate Director Jess Gibbons – Chief Operations Officer
Report Authors Andy Brown – Traffic Team Leader Matthew Carruthers – Traffic Technician
Wards Highcliffe & Walkford;
Classification For Decision Ti t l e:
Background 1. The BCP Traffic Team were approached by the previous ward member for Highcliffe & Walkford following issues raised by residents in the Parkside and Field Way area regarding traffic concerns primarily at school times. In addition, concerns had been raised by Highcliffe School regarding pupil safety travelling to and from school. 2. Subsequent site meetings were carried out between BCP Traffic Engineers, Ward Members, Highcliffe School representatives, Highcliffe & Walkford Parish Council representatives and local residents to address the concerns, understand the issues and take forward proposals. 3. Consultation was carried out on the proposals by way of legal 21 day notice from 17 February 2023 to 11 March 2023. Notices were placed in the local Daily Echo as required along with notices placed locally on site. The matter was also discussed locally at Highcliffe and Walkford Parish Council. 4. A summary of the support, objections and comments is outlined in Appendix 2.
Options Appraisal 5. There are 2 Options: Make the Orders and implement the provisions as advertised (this is the preferred option and proposed decision, as set out in Appendix 2). Not to make the Orders.
Summary of financial implications 6. The costs associated with the consultation of the Orders are estimated to be £2,500, with a scheme implementation cost of approx. £8000 funded from the Local Transport Plan allocation for 2023/24.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.