Recommendations from Cabinet 10 December 2024 - Minute No. 90 - Hawkwood Road Phase 2

Approved Committee 2 papers

Council approved this item on Tuesday 25 February 2025. Below is the council's own wording, with the papers it was decided on.

Item77

Resolved

RESOLVED that Council: - (a) approve option 1 for the Hawkwood Road development scheme for 68 units and a clinical facility at a total scheme cost of£28.7m (preferred option); (b) approve option 2 (fully residential) to be delivered at total scheme cost of £26.6m in the event we are unable to deliver Option 1(the mixed-use scheme which includes the clinical facility); (c) approve the financial strategy for the scheme for both options inclusive of borrowing level over 50 years from both Housing Revenue Account and the General Fund; (d) approve the procurement of construction works of Hawkwood Road Ph2 through an open and competitive tender for the preferred option, subject to securing Homes England Affordable Housing Grant and a viable HRA business plan; (e) approve of the delegation to the Chief Operations Officer in conjunction with the Director of Finance and the Director of Law & Governance authority to enter contracts for building works, the Memorandum of Understanding with the NHS Dorset and the lease for the Clinical Facility, providing all key parameters (including delivery within approved capital budget) are met; (f) Approval of the appropriation of part of the main Hawkwood Road south site for housing purposes under section 19 of the Housing Act 1985 following its appropriation for planning purposes, once the required car parking area has been formally closed; and (g) Approval of the transfer of land to be held for housing purposes from the general fund (GF) to the Housing revenue Account (HRA) for an appropriate certified financial consideration. Voting: Agreed with no dissent
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Council

CABINET

Report subject Hawkwood Road Phase 2

Meeting date 10 December 2024

Status Public Report

Executive summary This report sets out the redevelopment opportunity at Hawkwood Road, which is a priority project for the Boscombe Towns Fund. The report outlines two options for the delivery; either a mixed use site of residential home and a clinical facility in collaboration with the NHS (subject to contract, (Option 1) or a 100% residential scheme (Option 2) . The report confirms we will use best endeavours to pursue Option 1 mixed-use project, however, seeks authority to retain the flexibility to deliver the 100% residential (option 2), if necessary. The financial viability is dependent on Homes England grant for the delivery of 100% affordable homes and sufficient headroom in the Housing Revenue Account. Hawkwood Road delivers significant social and physical regeneration to the ward of Boscombe West and the associated local context. The project also contributes the delivery of much needed social homes.

Recommendations It is RECOMMENDED Cabinet recommends to Council the:

1. Approval of option 1 for the Hawkwood Road development scheme for 68 units and a clinical facility at a total scheme cost of £28.7m (preferred option).

2. Approval of option 2 (fully residential) to be delivered at total scheme cost of £26.6m in the event we are unable to deliver Option 1 (the mixed-use scheme which includes the clinical facility).

3. Approval of the financial strategy for the scheme for both options inclusive of borrowing level over 50 years from both the Housing Revenue Account and the General Fund. 4. Approval of the procurement of construction works of Hawkwood Road Ph2 through an open and competitive tender for the preferred option, subject to securing Homes England Affordable Housing Grant and a viable HRA business plan. 5. Approval of the delegation to the Chief Operations Officer in conjunction with the Director of Finance and the Director of Law & Governance authority to enter contracts for building works, the Memorandum of Understanding with the NHS Dorset and the lease for the Clinical Facility, providing all key parameters (including delivery within approved capital budget) are met.

6. Approval of the appropriation of part of the main Hawkwood Road south site for housing purposes under section 19 of the Housing Act 1985 following its appropriation for planning purposes, once the required car parking area has been formally closed. 7. Approval of the transfer of the land to be held for housing purposes from the General Fund (GF) to the Housing Revenue Account (HRA) for an appropriate certified financial consideration.

It is RECOMMENDED Audit and Governance Committee Recommend to Council:

8. Approval of an increase in the authorised borrowing limit of the Council to accommodate the £6.1m in the HRA for social rent/shared ownership and £3.2m in the general fund of prudential borrowing for Option 1 of this scheme and the proposal in the business cases for the financing of this debt. Or 9. Approval of an increase in the authorised borrowing limit of the Council to accommodate the £6.9m in the HRA for social rent/shared ownership of prudential borrowing for Option 2 of this scheme and the proposal in the business cases for the financing of this debt if Option 1 cannot be delivered.

Reason for To enable the delivery of social homes and a clinical facility to the recommendations benefit of Boscombe West, ensuring a revitalisation of an area in need of new homes and infrastructure. This will unlock long term social value in Boscombe West through the delivery of affordable homes and enabling long term residents to access much needed healthcare. Portfolio Holder(s): Cllr Kieron Wilson, Portfolio Holder for Housing and Regulatory Services

Corporate Director Glynn Barton, Chief Operating Officer

Report Authors Jonathan Thornton, Head of Housing Delivery Remi Oshibanjo, Housing Development Manager Peter Friend, Development Project Manager

Wards Boscombe West

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Hawkwood Road Phase 2- Boscombe Towns Fund, 10/12/2024 CabinetAppendix 5 166 KB Download
PDF
Recommendations from Cabinet 10 December 2024: Minute No. 90: Hawkwood Road Phase 2Report 196 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

65 of 80 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
LD
Councillor Lesley DedmanChair, present
SB
Councillor Simon BullVice-Chair, present
CA
Councillor Cameron AdamsCommittee Member, present
SA
Councillor Sue AitkenheadCommittee Member, present
HA
Councillor Hazel AllenCommittee Member, apologies
MA
Councillor Marcus AndrewsCommittee Member, present
SA
Councillor Sara ArmstrongCommittee Member, present
JB
Councillor Julie BagwellCommittee Member, apologies

All 80 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. Recommendations from Cabinet 10 December 2024 - Minute No. 90 - Hawkwood Road Phase 2This decision
  2. Recommendations from Portfolio Holders, Cabinet or CouncilDecided
  3. Recommendations from Portfolio Holders, Cabinet or CouncilDecided
  4. Recommendations from Portfolio Holders, Cabinet or CouncilDecided
  5. Cabinet 5 March 2025 - Minute No. 125 - Community Governance Review - Draft RecommendationsApproved
  6. Recommendations from Portfolio Holders, Cabinet or CouncilDecided

More from Bournemouth, Christchurch and Poole Council

All decisions
MeetingDecisionOutcome
11 Aug 2026 Confirmation of MinutesThat the minutes of the meeting held on 28 July 2026 be approved as a correct record. Approved Open
11 Aug 2026 Appointment of Corporate Director of Children's ServicesRESOLVED that: Council approved the appointment of Claire Shiels to the position of Corporate Director of Children’s ... Approved Open
11 Aug 2026 Notices of Motions in accordance with Procedure Rule 10That this Council resolves to: Instruct officers to review planning policies and advise on lawful options to limit th... Agreed Open
28 Jul 2026 Cabinet 22 July 2026 - Minute No. 26 - BCP Growth PlanRESOLVED that: - (a) the BCP Local Growth Plan be adopted; (b) the expected Dorset Local Enterprise Partnership capit... Approved Open
28 Jul 2026 Cabinet 22 July 2026 - Minute No. 28 - Youth Justice Plan 2026-2027RESOLVED that the Youth Justice Plan 2026/27 be approved by Full Council. Voting: Unanimous Councillor Sara Armstrong... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies