Bournemouth Development Company LLP Business Plan

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 5 March 2025. Below is the council's own wording, with the papers it was decided on.

Item134

Resolved

RESOLVED that Cabinet: - (a) Agrees the principle of an extension of the Winter Gardens site "Option Execution Date", with details to be agreed to be delegated to the Chief Operations Officer acting in consultation with the Leader of the Council, or until Cabinet have had the opportunity to review a revised partnership business plan including the site development plan for the revised Winter Gardens scheme. (b) Instructs officers to explore the available funding options such that a funding strategy can be developed for the Winter Gardens project and be put forward at a future Cabinet meeting ; (c) Notes the timetable for producing a new Partnership Business Plan for BDC and a Cabinet report later this year; (d) Notes the interdependency with the current work to review Shareholder Governance and that the composition of the BDC Board is under review . Voting: Unanimous Portfolio Holders: Leader of the Council Housing and Regulatory Services To contribute to the Council’s Corporate Strategy, specifically helping to revitalise high streets and regenerate key sites to create new opportunities and to provide good quality homes that are accessible, sustainable and affordable for all. The emerging Local Plan includes an allocation of 400 new homes in the Bournemouth Arc area. This project offers the potential to make a significant contribution to exceed this target. The Council has reserved the right for Cabinet to approve Site Development Plans (SDP) and further approvals are necessary to vary terms.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting. Source: democracy.bcpcouncil.gov.uk

Follow this further

Built from Bournemouth, Christchurch and Poole's papers

What the report saysPro

Report to Cabinet

CABINET

Report subject Bournemouth Development Company LLP Business Plan

Meeting date 05 March 2025

Status Public Report

Executive summary Bournemouth Development Company LLP (“BDC”) is a joint venture between the Council and Community Solutions for regeneration Bournemouth, a subsidiary of MUSE Developments Limited (itself a subsidiary of Morgan Sindall Group plc). It was established in 2011 and is currently due to expire in 2031.

In March 2023, Cabinet approved a request to extend the Site Option Execution Date for Winter Gardens to September 2024. This date has passed and a further extension is required in order for BDC to continue working on a new scheme.

A Strategy Day was held on 6 December to review and consider options for moving forward with the Winter Gardens site. Following that meeting, Muse have committed funds to take forward new high-level design and capacity work for the site. Early indications show potential for a housing-led scheme with circa 500 homes, including a good proportion of affordable homes, along with some street level retail and commercial space.

The purpose of this report is to update Cabinet on progress since the recent BDC Strategy Day, agree the proposed timetable for the new Partnership Business Plan and to update on the priority project, Winter Gardens, including the proposed strategy for bringing forward residential development on the site, which requires approval to extend the Site Option Execution date.

Recommendations It is RECOMMENDED that Cabinet:

1. Agrees to amend the Winter Gardens site “Option Execution Date” to expire on 30 September 2028. There is no financial exposure to extend this date;

2. Instructs officers to explore the available funding options such that a funding strategy can be developed for the Winter Gardens project and be put forward at a future Cabinet meeting; 3. Notes the timetable for producing a new Partnership Business Plan for BDC and a Cabinet report later this year; 4. Notes the interdependency with the current work to review Shareholder Governance and that the composition of the BDC Board is under review.

Reason for To contribute to the Council’s Corporate Strategy, specifically recommendations helping to revitalise high streets and regenerate key sites to create new opportunities and to provide good quality homes that are accessible, sustainable and affordable for all.

The emerging Local Plan includes an allocation of 400 new homes in the Bournemouth Arc area. This project offers the potential to make a significant contribution to exceed this target.

The Council has reserved the right for Cabinet to approve Site Development Plans (SDP) and further approvals are necessary to vary terms.

Portfolio Holder(s): Councillor Millie Earl, Leader and Portfolio Holder for Planning & Local Plan, and Regeneration & Infrastructure. Councillor Kieron Wilson, Portfolio Holder for Housing & Regulatory Services.

Corporate Director Glynn Barton Chief Operating Officer

Report Authors Rob Dunford, Corporate, Business Case & Commercial Manager

Wards Bournemouth Central

Classification For Update and Decision Ti t l e: Background

1. The Bournemouth Development Company LLP (BDC) was set up in 2011 by Bournemouth Borough Council as a joint venture (JV) between the Council and Morgan Sindall Investments (MSIL).

2. In 2020, following an internal reorganisation, part of the business of Morgan Sindall Investments Limited (“MSIL”) was transferred to Muse Developments Limited (“Muse”). As a result, MSIL sought confirmation of the Council’s agreement to transfer to Muse the contractual obligations in two development management agreements (DMAs) between MSIL and the Bournemouth Development Company LLP (“BDC”). Cabinet dated 29 September 2021 acknowledged and approved this novation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Bournemouth Development Company LLPAppendix 1 1.9 MB Download
PDF
Bournemouth Development Company LLP Business PlanReport 557 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 23 attended
P
Presentthe member of the committee was present as expected at the meeting
A
Apologiesthe member of the committee was unable to attend and reported their apologies in advance (substitute
A
Absentthe member of the committee was not present and did not apologise for their absence
IA
In attendancea councillor, who was not a member of the committee, was also in attendance
ME
Councillor Millie EarlChair, present
MC
Councillor Mike CoxVice-Chair, present, as expected, virtual
DB
Councillor David BrownCommittee Member, present
RB
Councillor Richard BurtonCommittee Member, present
AH
Councillor Andy HadleyCommittee Member, present
JH
Councillor Jeff HannaCommittee Member, present
RH
Councillor Richard HerrettCommittee Member, present
AM
Councillor Andy MartinCommittee Member, present

All 23 on the meeting page

On this subject at Bournemouth, Christchurch and Poole

Search all
  1. Bournemouth Development Company LLP Business PlanThis decision
  2. Bournemouth Development Company LLP – Extension of Option Execution DatesAgreed
  3. Bournemouth Development Company LLP Business PlanApproved
  4. Bournemouth Town Centre Vision (TCV): Durley Road Development – Approval of Additional Council Finance and Site Lease ValueApproved
  5. Bournemouth Development Company (BDC) - Changes to Members AgreementAgreed
  6. Bournemouth Development Company LLP Business PlanApproved

More from Bournemouth, Christchurch and Poole Cabinet

All decisions
MeetingDecisionOutcome
2 Sep 2026 2026/27 Council Budget monitoring at Quarter 1RESOLVED that Cabinet: - (a) noted the Quarter 1 position for 2026/27, actions taken by the Section 151 Officer to da... Noted Open
2 Sep 2026 Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior... Approved Open
2 Sep 2026 IT & Programmes Infrastructure Capital Investment Plan 2026–2032RESOLVED that Cabinet: - (a) approved delegated procurement authority to Director of IT & Programmes; (b) recommend t... Approved Open
2 Sep 2026 BCP Homes Performance and Regulatory Compliance UpdateRESOLVED that Cabinet noted the content of the report and raised any issues for consideration by officers. Voting: Un... Noted Open
22 Jul 2026 Recommendations from the Overview and Scrutiny CommitteesDecision) The Leader thanked Councillor Canavan and the Committee for bringing their recommendation to Cabinet and ex... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies