AI summaryCabinet gives the Leader and Cabinet Chair delegated authority to commence a new BCP Local Plan under the 30-month system, with a cross-party working group to guide it.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet agreed governance and delegated authority to start the Plan
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet gave the Leader of the Council and Chair of Cabinet delegated authority to issue the Notice to Commence, publish the timetable and Project Initiation Document, run a 6-week scoping consultation, and progress the Plan through the Gateway stages.
Cabinet agreed the Terms of Reference of the Local Plan Working Group, with a provision allowing substitute members if group leaders notify at least 72 hours before a meeting and the substitute attends an officer briefing.
Officers must clarify which non-statutory stakeholders will be engaged, and Ward members are asked to suggest organisations; a devolution and local government reorganisation risk is to be added to the Project Initiation Document risk register.
Why
In June 2025 Cabinet agreed to prepare a new Local Plan under the reformed 30-month plan-making system, and the Government has since published the Regulations and guidance. This decision puts the governance in place to formally start that work. Report P1, P2, P3
What happens next
Issue the Notice to Commence plan making and publish the timetable and Project Initiation Document, updating as required.
Run a scoping consultation exercise for a period of 6 weeks.
Progress the Local Plan through the prescribed Gateway stages, with Cabinet retaining a decision at each formal consultation stage.
Implications
Governance: A cross-party Local Plan Working Group is being set up to guide the Plan, with substitution rules set by Cabinet.
Risk: A risk on the wider implications of devolution and local government reorganisation, including changing consultees, is to be added to the risk register within the Project Initiation Document.
Other: Statutory consultation duties remain; beyond them, further clarification is sought on which stakeholders will be engaged and Ward members are asked to suggest organisations.
Who and where
Residents and communities across Bournemouth, Christchurch and Poole Report P2, P3
Statutory consultees and other stakeholders to be engaged in plan-making
Ward members, who are asked to suggest organisations to engage
The cross-party Local Plan Working Group and its substitutes
Timeline
June 2025: Cabinet agreed to prepare a new Local Plan under the reformed plan-making system. Report P1
2026-05-27: Cabinet approved the governance and delegated authority to commence the new BCP Local Plan.
6 weeks: Length of the scoping consultation exercise to be run once the Notice to Commence is issued.
30 months from Gateway 1: Government's target timeframe for preparing and adopting the new Local Plan. Report P2
Plain English for the jargon
Local Plan: The statutory planning document setting out local planning policies and site allocations for the area.
Gateway stages: Formal checkpoints in the reformed 30-month plan-making system that a plan must pass through.
Notice to Commence: The formal notification issued by the council to start preparing a local plan.
Scoping consultation: An early consultation to define the issues, vision and scope the plan will address.
Project Initiation Document (PID): The document setting out the timetable, governance, risks and resources for the project.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
RESOLVED that: - (a) Cabinet give delegated authority to the Leader of the Council and Chair of the Cabinet to undertake the necessary activities to: (i) Issue the Notice to Commence plan making; (ii) Publish the timetable and Project Initiation Document, and update as required. (iii) Publish a scoping consultation exercise for a period of 6 weeks. (iv) Progress the Local Plan through the Gateway stages. (b) Cabinet agreed the Terms of Reference of the Local Plan Working Group subject to the inclusion to allow the possibility for substitute members provided that group leaders or their nominated representative notify of the change at least 72 hours in advance of a meeting and provided that the substitute attend a briefing with relevant officers prior to the meeting: (c) further clarification be provided on the stakeholders who will be engaged with, beyond the statutory consultees and that Ward members be encouraged to provide the details to officers of any organisations that they feel should be engaged with as stakeholders; and (d) a risk concerning the wider potential implications of devolution and local government reorganisation, e.g. changing consultees, be added to the risk register included within the Project Initiation Document Voting: Unanimous Portfolio Holder: Leader of the Council To agree the governance arrangements and enable work to formally commence on preparing a new Local Plan within the reformed 30-month plan making system.
Word for word from the decision Bournemouth, Christchurch and Poole published for this meeting.Source: democracy.bcpcouncil.gov.uk
Follow this further
Built from Bournemouth, Christchurch and Poole's papers
Executive summary In June 2025, Cabinet agreed to prepare a new Local Plan under the Government’s reformed plan-making system. The Government has now published the Regulations and guidance setting out the new process, which is intended to enable plans to be prepared and adopted within 30 months from Gateway 1. This report summarises the process and proposed timetable for preparing the new BCP Local Plan and seeks authorisation to undertake the Stage 1 (“Getting ready”) activities, together with delegated authority to progress the Plan through the prescribed Gateway stages. Cabinet decisions will remain for each formal consultation stage. A cross party Working Group is being set up to guide the Local Plan.
Recommendations It is RECOMMENDED that Cabinet:
1. Give delegated authority to Leader of the Council and Chair of Cabinet to undertake the necessary activities to: a. Issue the Notice to Commence plan making; b. Publish the timetable and Project Initiation Document, and update as required. c. Publish a scoping consultation exercise for a period of 6 weeks. d. Progress the Local Plan through the Gateway stages. 2. Agree the Terms of Reference of the Local Plan Working Group.
Reason for To agree the governance arrangements and enable work to recommendations formally commence on preparing a new Local Plan within the reformed 30-month plan making system. Portfolio Holder(s): Millie Earle
Corporate Director Glynn Barton
Report Authors Laura Bright
Wards Council-wide
Classification For Decision Ti t l e:
Background 1. There is a statutory duty under both the Planning and Compulsory Purchase Act 2004, amendments made by the Levelling Up and Regeneration Act 2023 and the Town and Country Planning (Local Planning) (England) Regulations 2026 (the 2026 Regulations) to prepare and adopt a Local Plan. 2. Following advice from the Planning Inspectorate, Cabinet (June 2025) agreed to withdraw the BCP Local Plan which had been prepared and submitted for examination in 2024, and prepare a new BCP Local Plan (the Plan). The new Plan will establish how land within our area will be used and developed, setting out priorities for housing, employment, infrastructure, and environmental issues. It will provide a clear, deliverable and legally compliant spatial strategy, site allocations and policy framework to guide development and infrastructure investment over a 15 year period from 2028/29 – 2043/44.
New Plan-making system 3. Government published guidance on the new plan making process in November 2025 and associated 2026 Regulations. Consultation on a proposed draft new National Planning Policy Framework was released in December 2025 and includes updates regarding the new system. The new system is a structured process with clear stages and ‘gateways’, there is a mandatory 30-month time limit from Gateway 1 to Adoption. The sequence of tasks are set out below. Stage 1 Getting ready Publish timetable (this must be updated at each key stage) May 2026
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Learning Disability Big Plan 2026–2031RESOLVED that Cabinet approved the Learning Disability Big Plan for future publication and delivery against the prior...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.