Resolved
RESOLVED that the Board notes and endorses the measures underway to improve and transform the planning service. Voting: Agreed with no dissent
AI summaryBournemouth, Christchurch and Poole scrutiny board endorses planning service improvements after review shows statutory targets on speed and quality are being met.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Board notes and endorses the measures underway to improve and transform the planning service. Voting: Agreed with no dissent
OVERVIEW AND SCRUTINY BOARD
Report subject Planning Performance Update
Meeting date 24 August 2026
Status Public Report
Executive summary This update on the ongoing work to improve the performance of BCP Council planning service with significant success in the last year to reduce backlog and increase performance.
Recommendations It is RECOMMENDED that:
Note and endorse the measures underway to improve and transform the planning service.
Reason for To update on the performance of the BCP Council planning service. recommendations tfolio Holder(s): Cllr Millie Earl, Leader of the Council and Chair of the Cabinet
Corporate Director Glynn Barton, Chief Operations Officer
Report Authors Jon Bishop, Head of Planning Operations
Wards Council-wide
Classification For Information Ti t l e:
Background 1. The purpose of this report is to update Members on the performance of the planning service including its performance against national and local measures
Planning Improvement Journey 2. A Planning Improvement Board was established in April 2021, chaired by the Chief Executive and attended by relevant Portfolio Holder Members and key officers. This Board met on a monthly basis to oversee the Planning Improvement programme until the middle of 2025 when the meeting frequency was reduced due to the scale of progress. The objectives of the programme were:
Achieve high and consistent standards of performance delivering to the expectations of customers Deliver the local plan to set out the framework for growth meeting the areas sustainable development need Deliver strong and responsive development management including proactively managing the backlog of older cases Utilise modern ways of working and new technology to optimise the efficiency of working practices Create an environment for staff to have job satisfaction and develop their careers within the service that is known for delivering positive outcomes and has a strong reputation.
4. The programme has consisted of five workstreams working to meet these objectives:
Structure, People and Culture Performance and Development Management System and Process Harmonisation Customer Service and Support Services Local Plan 5. The following sections provides an update on the progress against the key objectives within each workstream.
Structure, People and Culture
6. The key objectives for this workstream were:
Recruitment to vacant posts and reduction of agency staff. Implement a new fit for purpose structure. Address workforce issues including low morale, high workloads, staff wellbeing and resilience pressures. Develop a new culture which supports to optimum performance. Address challenges of home working. 7. Progress within this workstream has been significant since the last report to the Board in 2025.
Recruitment, revised structure and home working
8. Early in 2023, a new structure for Planning was agreed with senior officers partly to formalise a range of temporary working arrangements whereby a number of staff where in interim roles, whilst also enabling promotion opportunities for staff who have proven themselves to be worthy of more challenging roles. This process was completed in late December 2023.
9. Since the last report, a number of recruitment exercises have been undertaken to result in a situation where there are currently only two vacancies in Development Management. The current vacancies are considered to be the level normally expected for a team of this size. Recruitment is currently underway and it is anticipated that the posts will be filled in due course. The new structure was implemented in March 2025 to coincide with the implementation of the new Mastergov IT system
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Performance UpdateReport | 380 KB | DownloadRead as text |
Follow Overview and Scrutiny Board at Bournemouth, Christchurch and Poole and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Work PlanThat a review of Seafront Commercial Operations be added to the Board’s Work Programme. Voting: Unanimous | Decided | Open |
| 15 Jun 2026 | Work PlanIt was agreed that the request would be considered at a future meeting of the Board. Board Members were asked to cont... | Agreed | Open |
| 18 May 2026 | Election of ChairRESOLVED that Cllr K Salmon be elected Chair of the Overview and Scrutiny Board for the 2026/27 Municipal Year. | Decided | Open |
| 18 May 2026 | Election of Vice-ChairRESOLVED that Cllr S Aitkenhead be elected Chair of the Overview and Scrutiny Board for the 2026/27 Municipal Year. | Decided | Open |
| 18 May 2026 | Work PlanThat the Charminster Library item be added to the Board’s work plan. 2. That a small group of members develop key lin... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.