RESOLVED that, subject to no responses being received raising material matters that had not been covered in this report, the Head of Planning and Building Control be authorised to approve the application, subject to the following conditions:- 01. The development hereby permitted shall be carried out only in accordance with the following plans: Drawing number 05/027/PB1 Rev 00 received 26th July 2006 (or any plans or details subsequently agreed in writing by the Local Planning Authority as an amendment to the approved plans).
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
ITEM NO: 13 Application No. Ward: Date Registered: Target Decision Date: 06/00694/FUL Winkfield And 26 July 2006 20 September 2006 Cranbourne Site Address: Orsett House Pigeonhouse Lane Winkfield Windsor Berkshire SL4 4SD Proposal: Retention of Basement. Applicant: Rigsby Group Ltd Agent: (There is no agent for this application) Case Officer: John Devonshire, 01344 352000 [email protected]
Site Location Plan (for identification purposes only, not to scale)
Planning & Highways Committee 24th August 2006 1 RELEVANT PLANNING HISTORY (If Any)
01/00571/FUL Validation Date: 07.06.2001 Erection of 1no. 5 bedroomed detached dwelling following demolition of existing dwelling. Erection of detached buildings forming garages, swimming pool/gymnasium/plant and stables. Refused
03/00920/FUL Validation Date: 24.09.2003 Erection of 1no. 5 bedroomed house following demolition of existing dwelling. Refused
04/00233/FUL Validation Date: 09.03.2004 Erection of 1no. 5 bedroomed detached dwelling following demolition of existing. Approved
99/00880/FUL Validation Date: 20.09.1999 Erection of a 5 bedroom dwelling following demolition of existing house. Approved
05/00497/FUL Validation Date: 31.05.2005 Erection of detached dwelling following demolition of existing house and outbuilding. Refused
05/00841/FUL Validation Date: 07.09.2005 Erection of detached house following demolition of existing dwelling and outbuilding. Approved
2 RELEVANT PLANNING POLICIES
Key to abbreviations BSP Berkshire Structure Plan 2001-2016 BFBLP Bracknell Forest Borough Local Plan SPG Supplementary Planning Guidance PPG (No.) Planning Policy Guidance (published by Department for Transport, Local Government and the Regions) RPG Regional Planning Guidance MPG Minerals Planning Guidance WLP Waste Local Plan for Berkshire
Note: The BSP and the BFBLP contain some policies with the same title, e.g. EN1. In such cases, the policy will be suffixed with an “_S” for the BSP and an “L” for the BFBLP, e.g. EN1_S, EN1L..
Plan Policy Description (May be abbreviated) BFBLP EN20 Design Considerations In New Development BFBLP GB1 Building In The Green Belt 3 CONSULTATIONS (Comments may be abbreviated)
Winkfield Parish Council
No objection
4 REPRESENTATIONS
No letters of representation have been received with respect to this application.
Planning & Highways Committee 24th August 2006 5 OFFICER REPORT
This application is reported to the Committee as it proposes an increase in floor area in a Green Belt location above the guideline as set out in the Bracknell Forest Borough Local Plan. Further, this application is recommended to be delegated to the Head of Planning and Building Control, as the period for receiving comments has not yet expired
1) PROPOSAL AND BACKGROUND
This application seeks full permission for the retention of a basement to a replacement dwelling.
The basement would create a floor area of some 163sqm and would form a storage area, utility room, hall, plant rooms and a wine cellar. The whole of the basement area is to be sited underground, with no part protruding above ground level.
Previous applications for a replacement dwelling at the site have been granted in 2004 and 2005 under references 04/00233/FUL and 05/00841/FUL respectively. The 2004 approval has not been implemented, and the plans for this current application for the retention of the basement relate to the approval granted under 05/00841/FUL.
The approved replacement dwelling granted in 2005 proposed a floor area of some 417sqm. The original floor area of the existing dwelling as it stood prior to May 1980 was 300sqm. Therefore the replacement dwelling proposed an increase of 39%, over and above the floor area of the original dwelling, which is consistent with Green Belt Policy as contained within the Bracknell Forest Borough Local Plan.
2) SITE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.