Civic Hub - Update

Decided Committee

Bracknell Town Centre Regeneration Committee decided this item on Monday 18 June 2007. Below is the council's own wording, with the papers it was decided on.

Item141a

Resolved

RESOLVED 1 That the concept design report be endorsed, noting the following outstanding issues : · The need for further information on the materials and design of the external elevations. · A firm commitment to support the Council’s Combined Heat and Power strategy for the civic campus. · Minor additional corrections requested by the Council’s project manager. · Satisfactory review of the supporting cost plan. 2 That the inclusion of a passenger hoist lift in the library (to be provided as part of the Council’s fit-out) be considered further by the Civic Centre Project Board having regard to the durability of the hoist. 3 That the approach outlined in the report to progress the designs of the New Jubilee Gardens be endorsed. 4 That formal sign-off of a revised Stage C report be delegated to the Chief Executive in consultation with the Civic Hub Project Board, scheduled for 29 June.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

4 of 8 attended
PB
Councillor Paul Bettison OBE CONChair, present
MM
Councillor Mrs Mary Ballin CONVice-Chair, present
GB
Councillor Gareth Barnard CONCommittee Member, present
IM
Iain McCracken CONCommittee Member, present
AS
Anne Shillcock LABNon-Voting Co-Optee, apologies
DB
Councillor Dale Birch CONSubstitute
DH
Councillor Dorothy Hayes CONSubstitute
AK
Councillor Alan Kendall CONSubstitute

On this subject at Bracknell Forest

Search all
  1. Civic Hub - UpdateThis decision
  2. Civic Hub - Combined Heat and Power - Budget ApprovalApproved
  3. Civic Hub Construction ProcurementAgreed
  4. Civic Hub - Design UpdateDecided
  5. Civic Hub - UpdateApproved

More from Bracknell Forest Bracknell Town Centre Regeneration Committee

All decisions
MeetingDecisionOutcome
6 Nov 2023 Exclusion of Public and PressRESOLVED that pursuant to Regulation 4 of the Local Authorities (Executive Arrangements) (Access to Information) Regu... Decided Open
11 Sep 2023 Town Centre off street day rate car park chargesRESOLVED that: i. The Committee notes the options on charging tariffs for The Avenue, High Street, Braccan Walk and W... Approved Open
11 Sep 2023 Exclusion of Public and PressRESOLVED that pursuant to Regulation 4 of the Local Authorities (Executive Arrangements) (Access to Information) Regu... Decided Open
10 Jul 2023 Election of ChairRESOLVED that Councillor Bidwell be elected Chair of the Bracknell Town Centre Regeneration Committee for the municip... Decided Open
10 Jul 2023 Appointment of Vice-ChairRESOLVED that Councillor Neil be nominated Vice Chair of the Bracknell Town Centre Regeneration Committee for the mun... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies