RESOLVED that the sum of £585,000 be added to the capital budget, spread over three years, 2008-09 (£227,000), 2009-10 (£179,000) and 2010-2011 (£179,000). (ii) Joint Berkshire Minerals and Waste Local Development Framework – Submission Core Strategy Development Plan Document On the proposition of Councillor Mrs Ballin , Executive Member for Planning and Transportation, seconded by Councillor Worrall it was RESOLVED that ( i ) The emerging Joint Berkshire Minerals and Waste Local Development Framework Core Strategy Development Plan Document (DPD) be approved for Publication (2008 Regulation 27) and then submission (2008 Regulation 30 and Section 20 of the primary 2004 Act). (ii) The authority not to oppose minor changes to the Submission Joint Minerals and Waste Core Strategy DPD during the examination period for Development Plan Documents be delegated to the Head of Spatial Policy in consultation with the Executive Member for Planning and Transportation. (iii) The Publication and Submission versions of the Joint Minerals and Waste Core Strategy DPD be used as a material consideration for Development Management purposes.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Since the Executive report to the Council meeting on 18 June 2008, the Executive has met once on 24 June 2008. This report covers the decisions made at that meeting, summarised by reference to the relevant portfolio within which they fall.
2 COUNCIL STRATEGY AND COMMUNITY COHESION
2.1Corporate Performance Overview Report
2.1.1 The Executive received the Chief Executive’s latest Corporate Performance Overview Report.
2.1.2 The Departmental Service Plans for 2007/08 contained 344 detailed actions to be completed in support of the 12 interim Corporate Themes which were agreed by the Executive in March last year. Of these, 317 (92%) actions were achieved by year end, whilst 27 (8%) are still outstanding.
2.1.3 A significant part of the Council’s work relates to day-to-day service provision which is not specifically covered by priority actions in Service Plans. However, performance against targets for day-to-day services is also important. Of the 128 indicators where data is available, 79 (62%) achieved the target. The following highlight some areas of note.
• Work on the Town Centre regeneration progressed well this quarter, with the public inquiry into the compulsory purchase orders taking place. Stage D (Design Development) of the Civic Hub project is now almost complete.
• The entirety of the Council’s housing stock was successfully transferred to Bracknell Forest Homes in February.
• Fourth quarter figures show that overall BCS crime within the Borough fell by a remarkable 20.4% in 2007/08, contributing to a three-year reduction of 12.5%. The 2007/08 result for Bracknell Forest represents the biggest reduction of crime in the Thames Valley force area.
• The ‘Fear of Crime’ survey was completed during the quarter, with the results anticipated in June, and it has been agreed that the Crime and Disorder Reduction Partnership’s real-time data on anti-social behaviour within the Borough will be made available to the public via the Council website.
• The Community Cohesion Strategy (‘All of Us’), the new Voluntary Sector Compact and the Council’s Race and Gender Equality Schemes were finalised during the quarter, whilst work has progressed on the Equality Standard Action Plan with the aim of achieving Level 3 by March 2009. • The Council was notified of the successful outcome of its bid to secure £2.5m Lottery grant funding for renovation of the grounds at South Hill Park
• Whitegrove Primary School was judged by Ofsted to be ‘Outstanding’ – the third BFBC school to achieve this grade.
• Preparations for the transition from the Children and Young People’s Strategic Partnership to a Children’s Trust were completed
• The timetable for approving commissioning strategies was met, with the Executive approving Mental Health and Learning Disabilities strategies in February and a strategy for People with Long-Term Conditions in March.
• The Council slightly exceeded its year-end target of 26% of household waste recycled, and although low composting rates during the bad weather in Quarter 4 meant that the 14% target for composting was narrowly missed, a total of 40% of household waste in the Borough was either recylced or composted.
• 8,000 new smartcards for the National Concessionary Fares Scheme were issued with Bracknell Forest now having the most advanced multi-application smartcard in operation anywhere in the country.
2.1.4 Overall, therefore, performance against targets during the final quarter of 2007/08 was very good, with a number of key milestones being met. The progress achieved during the quarter has contributed to an extremely successful year for Bracknell Forest Borough Council, in which our solid performance was awarded national recognition in the CPA ‘Four Stars, Improving Strongly’ rating.
3 FINANCE, RESOURCES & ASSETS
3.1Revenue Expenditure Outturn 2007/08
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.