Resolved
RESOLVED that the minor amendment be approved .
Planning & Highways Committee approved this item on Thursday 16 October 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minor amendment be approved .
ADDITIONAL INFORMATION ITEM:
Application No. Ward: Date Registered: Target Decision Date: AMD1/07/0057 Ascot 19 August 2008 18 September 2008 0/ Site Address: Land Between South Of Drift Road Winkfield and The Surrey Hill and Crowthorne Reservoirs Swinley Road Ascot Berkshire Proposal: Application for engineering works for the construction of an underground water supply main pipeline from land south of Drift Road, Foliejon Park to the Surrey Hill and Crowthorne Reservoirs with associated shafts, washout chambers, sluice valve chambers, air valves, kiosks and temporary working areas, proposed amendment: change in the method of installation of a 21m section of pipeline at Bog Lane to use a no-dig method. Applicant: South East Water Agent: Adams Hendry Consulting Ltd. Case Officer: Natalie Brown, 01344 352000 [email protected]
Site Location Plan (for identification purposes only, not to scale)
Planning & Highways Committee 16th October 2008 Planning & Highways Committee 16th October 2008 1 RELEVANT PLANNING HISTORY (If Any)
07/00570/FUL Validation Date: 08.06.2007 Application for engineering works for the construction of an underground water supply main pipeline from land south of Drift Road, Foliejon Park to the Surrey Hill and Crowthorne Reservoirs with associated shafts, washout chambers, sluice valve chambers, air valves, kiosks and temporary working areas. Approved
2 CONSULTATIONS (Comments may be abbreviated)
Winkfield Parish Council
Observations: That the Parish Council expresses concern that work is proceeding without the amendments being approved and is being carried out, out of permitted hours. The Council also supports the concerns of the local residents and requests that this application is considered by the Planning Committee.
Environmental Health and Safety
No objection.
3 REPRESENTATIONS
5 letters of objection (including one from local MP) on grounds of:
- Compound been erected on site (in breach of condition 24 of original application) - Works are taking place without approval - Concerns regarding noise impact - Works taking place and machinery in operation outside of the hours permitted by condition 3 of the original application (9am-5pm Monday-Friday and 9am-2pm on Saturday) - No re-assessment of vibration impact upon nearby properties - No reference of the distance of the works to nearby properties - No re-assessment of dust/air quality impacts - No information regarding location of gas mains
[ Officer comment: The issues of noise and the compound are addressed in the main section of the report, below. The applicant has confirmed that any vibration, dust/air quality issues would be within the parameters of the original environmental statement. The distance of the works to nearby properties is within the already approved working width.]
4 OFFICER REPORT
Summary Of Key Aspects Of The Proposal (If Any)
Planning & Highways Committee 16th October 2008 The amendment is before the Committee as more than 3 objections have been received.
i) PROPOSAL
Amendment to application 07/00570/FUL to change in the method of installation of a 21m section of pipeline at Bog Lane to use a no-dig method.
The original application approved a 17km water pipeline from Bray Reservoir to the Crowthorne and Surrey Hills Reservoirs.
The proposed works would be within the consented pipeline working width approved by the original application
It should be noted that since the amendment was submitted, works have taken place, and the ‘no-dig’ constructed tunnel is now in place, with only the pipe needing to be placed within it. Therefore, the amendment is now retrospective.
ii) SITE
21m section of pipeline adjacent to Bog Lane entrance, lying to east of properties at Wareham Road. The nearest property lies some 40m from the pipeline.
iii) PLANNING CONSIDERATIONS
(1) Principle of Development
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AMD1/07/00570/: Land between South of Drift Road, Winkfield and The Surrey Hill and Crowthorne Resevoirs, Swinley Road, AscotReport | 110 KB | DownloadRead as text |
Follow Planning & Highways Committee at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 May 2011 | 11/00123/FUL - 29 Essex Rise, Warfield, BracknellRESOLVED that the application be refused for the following reason:- 01. The proposed extension by reason of its desig... | Refused | Open |
| 26 May 2011 | 11/00177/FUL - 25 Branksome Hill Road College Town SandhurstThe following development plan policies have been taken into account in determining this planning application: Brackn... | Decided | Open |
| 26 May 2011 | PS 11/00239/RTD - Land Opposite Byways Crowthorne Road SandhurstRESOLVED that the siting and appearance of the development proposed be refused for the following reason: 1. The propo... | Refused | Open |
| 26 May 2011 | 11/00308/RTD - Land Adjacent To Electricity Substation, Victoria Road, OwlsmoorRESOLVED that the siting and appearance of the development proposed be approved in accordance with the plans as state... | Approved | Open |
| 25 May 2011 | Election of chairmanRESOLVED that Councillor Dudley be elected Chairman of the Planning and Highways Committee for the Municipal Year 201... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.