Resolved
RESOLVED that the Re3 Municipal Waste Management Strategy 2008-13 as set out in the Annex 1 to the report of the Director of Environment, Culture & Communities be adopted.
Executive approved this item on Tuesday 21 October 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Re3 Municipal Waste Management Strategy 2008-13 as set out in the Annex 1 to the report of the Director of Environment, Culture & Communities be adopted.
2.1That the Re3 Municipal Waste Management Strategy 2008-2013 as set out in Annex 1 to the report be adopted.
3.1To enable this Council in partnership with Reading and Wokingham BC to have a common strategy under the re3 management arrangements for dealing with the waste being generated by the community.
4.1None. The production and adoption of a strategy is now expected by Government. To adopt one jointly with the re3 partners is good management practice.
5 SUPPORTING INFORMATION
5.1As a key part of their strategic planning processes, the Government expects all local authorities to produce or contribute to a Municipal Waste Management Strategy (MWMS). The Joint Municipal Waste Management Strategy (JMWMS) as attached in Annex 1 has been fully considered by the JWDB taking due account of the public consultation undertaken via the Council websites of the re3 Councils during August and September. Members at each of the Councils were also invited to comment and those comments have been taken into account during the drafting process prior to consideration by the JWDB.
5.2The JMWMS has been produced with the input of consultants (Enviros) following the successful bid for funding from DEFRA. Content of Municipal Waste Management Strategy (MWMS)
5.3The production of the JMWMS has been relatively straightforward. This is because through the work of our Joint Waste PFI, we have already undertaken much of the strategic planning and subsequent procurement that is envisaged will follow on from the development of a MWMS.
5.4The intention of the document goes beyond merely satisfying the basic requirements of a MWMS. The document goes on to plot a course for the re3 councils to achieve statutory targets and the financial and environmental objectives of the PFI contract.
5.5The JMWMS has to be both a working document for the Councils and a public document for residents and stakeholders. With this dual role in mind the JMWMS starts by explaining both what it is and what the re3 partnership is. The JMWMS also describes the environmental, legislative and financial influences on waste, some demographic information, current levels of performance in the three Councils and the role of the PFI contract. Collectively these sections provide the context for the Action Plan (Appendix 2).
5.6The Action Plan has been written to reflect the direction given to local authorities in the Government's Waste Strategy 2007 (which replaces the previous guidance - Waste Strategy 2000). New areas of specific focus are on subjects such as Climate Change, supporting businesses and the voluntary sector and partnerships.
5.7The action plan is the section of the Strategy in which the Councils' objectives are identified and the steps we intend to take to achieve them are explained. The Action Plan will be reviewed on an annual basis via the Joint Waste Disposal Board.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The Borough Solicitor has no comments to add to the report.
Borough Treasurer
6.2The Strategy was funded by a specific grant from DEFRA. Any new initiatives arising from the Strategy not already included in the commitment budget for the waste PFI project will be funded from the Waste and Performance Efficiency Grant from DEFRA.
Equalities Impact Assessment
6.3Not applicable.
Strategic Risk Management Issues
6.4There are none arising from this report assuming the Strategy is adopted.
7.1The draft was subject to consultation as outlined in the report. Background Papers Reports to Joint Waste Disposal Board 19 March 2008
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Joint Municipal Waste Strategy Annex 1Appendix | 1.2 MB | Download |
PDF |
Joint Municipal Waste Strategy Annex 1 AppendicesAppendix | 3 MB | Download |
PDF |
Joint Waste Disposal Board: Joint Municipal Waste Management StrategyReport | 60 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.