RESOLVED that 1. the new internal audit services contract commencing on 1 April 2009 be awarded to Tenderer A for a period of three years with the option to extend for one further year. 2. an additional £65,000 be added to the 2009/10 budget.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the new internal audit services contract commencing on 1 April 2009 be awarded to Tenderer A for a period of three years with the option to extend for one further year.
2.2That an additional £65,000 be added to the 2009/10 budget.
Reasons for recommendations
3.1To ensure that the Council meets its requirements under the Accounts and Audit Regulations 2003 (amended 2006) to maintain an adequate and effective system of internal audit of its accounting records and of its system of internal control.
Alternative options considered
4.1The Council has already extended the contract with the existing provider. The extension to the contract expires on 31 March 2009 and no further extensions are permissible. The only other alternative to re-tendering the contract would be to establish an in-house internal audit team. However, outsourcing provision of the service is financially advantageous, enables the Council to avoid the recruitment and retention issues that other authorities with in-house teams are experiencing and furthermore enables the Council to draw on the contractor’s specialist staff, for example, computer auditors, which it would not be viable to employ in an in-house team.
5 SUPPORTING INFORMATION
5.1The Council’s internal audit services have been carried out by the same provider since becoming a unitary authority in 1998. The contract was re-let for a period of 3 years with a start date of 1 April 2004 with the option to extend for 2 years. No further extensions after 31March 2009 are permissible. Given that current Council spending on internal audit services is in excess of £160k per annum and hence in excess of EU procurement regulation limits, the options available were to use an Office of Government Commerce (OGC) framework agreement or advertise the contract in OJEU. The option to utilise an OGC framework was discounted given that the existing contractor was not an OGC supplier and because the Tender Evaluation Team took the view that medium ranking firms that would offer a more favourable rate were also not on the OGC framework list.
5.2The decision was taken that the contract would be advertised in OJEU. It was also agreed that this would be tendered as a framework agreement allowing other local authorities to utilise the framework in order to take advantage of any volume based discounts that might be made available with a greater number of audit days. Other authorities wishing to utilise the framework would agree their own contract with the supplier based on the terms and conditions in the framework.
5.3Following OJEU advertisement, all firms who expressed an interest were forwarded a Pre-Qualification Questionnaire (PQQ) for return by 29 August 2008. A total of 8 PQQ forms were returned. Following PQQ evaluation, 6 firms were short-listed to tender.
5.4Letters were sent on 16 September 2009 to all firms who had submitted a PQQ advising them if they had been short-listed to tender or had failed to be short-listed on this occasion. Tender documentation for completion was despatched on 16 October with a due date of 26 November 2008. Four West Berkshire local authorities provided information on indicative days they might purchase under the framework and this was included in the tender documentation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.