Resolved
RESOLVED that progress made since the last meeting on 17 December 2008 be noted.
Joint Waste Disposal Board noted this item on Wednesday 18 March 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that progress made since the last meeting on 17 December 2008 be noted.
2.1To note progress made since the last meeting on 17th December 2008.
3. SUPPORTING INFORMATION
Operations
3.1Since the last JWDB meeting in December, the Smallmead MRF has been certified as complete and has opened. The three councils have been delivering material, directly and indirectly to the MRF.
3.2The sharp fall in demand for recycled materials, which we discussed at the last meeting, was most pronounced immediately after Christmas. In the last month it appears to have abated somewhat and WRG have been able to continue to market material delivered by the councils throughout the period.
Finance and Performance
3.3The PFI is currently projecting an under spend of £490,000 against budget. (See Finance Appendix 1). The projected under spend is primarily due to contract tonnage being significantly lower than forecast.
3.4Annual contract waste for 2008/09 is now expected to reach approximately 205,000 tonnes, compared with the annual forecast of 215,000 tonnes.
3.5Landfill tonnage from Council collections and the Household Waste Recycling Centres (HWRCs) is down by over 6,000 tonnes compared to forecast in the period April 2008 to January 2009.
3.6Recyclate tonnage from Council deliveries and the HWRCs is also down by 3,700 tonnes compared to forecast in the same period.
3.7Green waste tonnage from Council deliveries and the HWRCs is actually up by 500 tonnes compared to forecast in the period.
3.8WRG continued to incur significant performance deductions throughout Quarter 3 due to ongoing issues with one of their bring bank contractors. However, WRG have recently replaced the problematic contractor, which has resolved the issue. 3.9 The PFI Management Budget is currently projecting an under spend of £10,600. See Finance Appendix 1.
3.10The £30,000 provision for additional legal fees that had previously been set aside has not been required due to the resolution of the Lakeside EfW issue (see paragraph 3.18).
3.11Current recycling rates are; Bracknell 41.1%, Reading 35.3% and Wokingham 37.3%.
Risk Register
3.12The councils Management Team have developed a Risk Register to identify and plan the management of areas of risk associated with the PFI contract.
3.13The Risk Register is appended to this report for information.
3.14Fire detection – The O&M (Operating and Maintenance) manuals relating to the fire detection system have been found to be inconsistent between Phase 1 (HWRC and Transfer Station) and Phase 2 (MRF and offices). These inconsistencies have meant that WRG can not be confident that the system would be attended immediately (by the installers or a retained maintenance contractor) in the event of a default being identified. As a result, WRG have commissioned an independent report with the intention of clarifying matters and ensuring that we are confident going forward. We are currently awaiting the results of the report. The re3 Project Director has written to WRG to raise our concerns and seek resolution.
3.15Landfill Gas - WRG and the EPC Contractor have taken steps to address the implications of the detection of a build-up of gas in the HWRC prior to Christmas. The temporary ducting (used during construction) has now been sealed, to reduce pathways into the facility. Monitoring by WRG continues and as no further incidents have been reported. WRG continue to report progress to both the councils and the Environment Agency.
Lakeside
3.16Members will be aware that, following consultation with officers from the re3 councils, WRG had negotiated an extension to the Longstop Date for the commissioning of Lakeside.
3.17Consequently they drafted a letter, confirming the terms of the extension, and were awaiting its signature and return.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
JWDB Project Update Appendix 1Appendix | 31 KB | Download |
PDF |
JWDB Project UpdateReport | 57 KB | DownloadRead as text |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.