RESOLVED that the Borough Solicitor be authorised to enter into an agreement pursuant to section 106 of the Town and Country Planning Act 1990 containing planning obligations:- ( i ) Precluding the completion of more than 650 dwellings on the Jennett's Park development unless and until a new junction on the A329 (Berkshire Way) and a link road between the junction and Peacock Lane have been constructed under an agreement made pursuant to section 38 and/or section 278 of the Highways Act 1980; and (ii) Requiring the junction and link road to be constructed within 16 months from the date of service of a notice by the Council requiring such construction.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the Council enters into an agreement under section 106 of the Town and Country Planning Act 1990 to secure the construction of a new junction on the A329 (Berkshire Way), and the provision of a link road between this junction and Peacock Lane, under an agreement pursuant to sections 278 and 38 of the Highways Act 1980, in accordance with a scheme and plans to be submitted to and approved in writing by the Council, prior to the completion of the 650th dwelling on the Jennett’s Park development, or at the earliest practicable opportunity after the completion of the 430th dwelling on the Jennett’s Park development, whichever is sooner.
2.2That subject to such an agreement being completed the Council undertakes not to seek to take any action to enforce condition 36 of outline planning permission 98/00288/OUT.
3 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
3.1In order to seek a variation or removal of condition 36 the developer would have to submit an application pursuant to section 73 of the Town and Country Planning Act 1990. A section 73 application is one which seeks planning permission for the whole development but with different conditions. The Council's principal concern is to put in place an enforceable legal mechanism which will secure the provision of the link road. That mechanism could be a different condition attached to a section 73 consent. An alternative mechanism would be for the developer/owner to enter into a section 106 agreement containing a planning obligation to provide the link road by an appropriate trigger event. The mechanism of a section 106 agreement would technically leave in place condition 36 in its current form but the Council would not seek to take any action to enforce it.
Transportation Officer
3.2Works to improve Peacock Lane were completed at an early stage in the development of the site, but the construction of the link road, and the necessary junction on Berkshire Way, did not follow on straight away. The developer preferred to aim at their being completed later, but in time for the completion of the 430th dwelling.
3.3The slow-down in the housing market has led to a change in build rates on the site, so the expected date for completion of the 430th dwelling is now approximately December 2009.
3.4With a construction period of about 9 months for the link road, there would be an overlap with the roadworks on the B3408 London Road Improvement scheme, which started earlier this year, if the link road works were allowed to follow a programme tied to the developers continuing housing completions programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.