Resolved
RESOLVED that Supplier E be appointed as the Council’s capital managing partner for the delivery of the Council’s capital programmes for children & young people.
Executive decided this item on Tuesday 17 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Supplier E be appointed as the Council’s capital managing partner for the delivery of the Council’s capital programmes for children & young people.
2.1That Supplier E be appointed as the Council’s capital Managing Partner for the delivery of the Council’s capital programmes for children & young people.
3.1The value of this contract constitutes a Key Decision under the Council’s Contract Regulations, for which Executive approval is required.
4.1The Managing Partner has been procured following a mini competition under a national Buying Solutions framework, details of which are set out in the body of the report.
5 SUPPORTING INFORMATION
5.1The amount of external funding on the Capital Programme in respect of education related schemes has increased significantly in recent years and in the current year totals over £51m. The bulk of this funding has been made available from the Department for Children, Young People and Families (DCSF) to support the delivery of the Children & Young People’s Plan and the “Every Child Matters” agenda. Whilst future spending decisions have yet to be made, indicative project life spans and grant allocations indicate that there will continue to be significant sums of external funding in the medium to long term.
5.2In July 2008 a Capital Framework was produced that set out the key programmes and projects that would be delivered with this funding, including:
a) Building Schools for the Future and the One School Pathfinder project at Garth Hill b) The Primary Capital Strategy for Change c) Children’s Centres d) Creation of Sufficient Pupil Places
5.3Delivery of the Primary Capital Strategy for Change has put pressure on in house resources, and in July 2009 CMT agreed to the procurement of an external managing
3 partner. The managing partner will to provide the role of programme manager and any additional technical support necessary for delivery of the programme over the three year life of the contract. The Council will have the option to extend the contract for a further year after this, and the ongoing relationship will minimise the transaction costs of multiple procurements undertaken previously, and maximise our economies of scale.
5.4The funding for the first phase of the programme is confirmed.
Managing Partner
5.5There are two elements to the contract, a fixed annual fee; and a percentage on-cost to each project, varying upon project value which will only apply to those projects implemented through the contract.
5.6On-cost fees are a replacement for the fees normally paid on projects and included in approved project costs on the Council’s capital programme. If no projects are implemented through the contract, then there will be no fees. The selection of projects to be implemented through the contract will take into account the availability of in house resources.
5.7The Managing Partner will be responsible and accountable for the performance of projects to a set of contractual KPIs, to include communication, programme, cost and delivery. They will report to a Project Board chaired by the Chief Officer: Performance & Resources. A baseline will be established against which improved performance can be measured and demonstrated.
Procurement
5.8A number of pan-government frameworks have been established which has reduced the cost of tendering exercises undertaken by public bodies. In July 2009 the government national consultancy framework administered by Buying Solutions on behalf of the Office of Government Commerce, was selected for the procurement of the managing partner. Expressions of interest were invited from the framework suppliers, and a mini competition was held during August 2009, in response to which the Council received five bids.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appointment of Managing PartnerReport | 61 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.