CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council

Severe Weather Working Group Report

Agreed Scrutiny 2 papers

Environment, Culture and Communities Overview & Scrutiny Panel agreed this item on Tuesday 22 June 2010. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

It was agreed that this would be reflected in the conclusion of the working group report. Some schools had used a text messaging service to keep parents informed of decisions to open and close the school for the day which had proved successful. It was agreed that recommendation 6.7 of the report would be expanded to include the use of text messaging. RESOLVED that the report of the Severe Weather report with amendments, be agreed and commended to the Overview and Scrutiny Commission for adoption and for sending formally to the Executive.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Environment, Culture and Communities Overview & Scrutiny Panel

Background

1.1On 21 December 2009 and then during the period 5 -14 January 2010 freezing temperatures and snowfall were experienced across the borough and nationally. Snow and ice caused widespread disruption across the borough on both occasions.

1.2The Working Group was established at the request of the Leader to review the Council’s response to the severe weather conditions during December 2009 and January 2010 with a view to making recommendations on any action to be taken based on lessons learned from these events.

1.3The Working Group review took into account the Officer Review of the Council’s response and hoped to provide any further comments or amendments on actions to improve the Council’s future response.

2. MEMBERSHIP AND SCOPE OF THE REVIEW

2.1The Working Group was established with the following membership: Councillors Harrison (Co-Chairman), Turrell (Co-Chairman) and Finnie.

2.2The scope of the review was to consider:

• The Council’s ability to maintain traffic movement on the highway; • How the Council maintained its normal services; • Use of resources; • Information available.

3. MEETINGS

3.1The Working Group met on 6 occasions:

• 15 February 2010 • 3 March 2010 • 14 April 2010 • 4 May 2010 • 14 May 2010; and • 7 June 2010

3.2In addition Bracknell Forest Borough Councillors were contacted for their views on the Council’s response to the severe weather and any issues that may have arisen in their wards during the periods of severe weather. The Group received a number of responses which were taken into account and considered during the review where appropriate.

3.3The Working Group also contacted the Borough’s Parish and Town Councils to ask for their views on the whether the Borough Council’s response was appropriate and timely and if anything could be done to improve the response during future severe weather events.

1 3.4. The Group held discussions with Bracknell Forest Council staff from the Adult Social Care & Health, the Children, Young People & Learning and the Environment, Culture & Communities departments.

3.5Discussions were also held with representatives of SITA and Ringway, two of the Council’s partners.

3.6Councillor Edger joined the working group for their meeting held on 4 May 2010.

4. FINDINGS

Context

4.1The Group noted that occurrences of severe weather were rare and recognised that the Council was not able to keep all services running as they would in normal circumstances. The two severe weather events that occurred in 2009 and 2010 were different in their nature and so impacted on the Council in different ways with each event requiring a different response.

Borough Councillor responses

4.2Input was received from several councillors, which taken together cover most of the Borough. The Working Group would like to thank Councillors Thompson, Brossard, [name removed], Beadsley, Kendall, Kensall, [name removed], Brunel-Walker and [name removed].

4.3A number of key points were raised by members:

4.4Communication - Members appreciated the regular severe weather email updates although they generally felt that the updates to the public-facing website could have been better co-ordinated. Members felt the Council’s team had done a good job but that the full extent of the effort to keep the Borough moving could be improved upon.

4.5Travel - Members noted that the severe weather was an exceptional event out of keeping with the relatively mild weather experienced by the UK over recent years. It was noted that the combination of rain on the 21st December 2009, followed by freezing temperatures and snow during the rush hour had prevented salting of roads from being effective. This led to traffic delays in many areas, not just Bracknell Forest. Once the snowfall had stopped, major routes were cleared relatively quickly allowing access for residents and the major stores to re-stock.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10 SWW Report 20.05.10 FINALReport 139 KB DownloadRead as text
PDF
Severe Weather Working Group ReportReport 18 KB Download

At this meeting

Whole meeting

Who was there

16 of 24 attended
ME
Councillor Mrs Emma Barnard CONCommittee Member, apologies
MB
Councillor Mike Beadsley LABCommittee Member, present
NB
Councillor Norman Bowers CONCommittee Member, present
AF
Councillor Alvin Finch CONCommittee Member, present
JF
Councillor Jim Finnie CONCommittee Member, present
MA
Councillor Mrs Anne Fleming CONCommittee Member, present
IL
Councillor Ian Leake CONCommittee Member, apologies
MJ
Councillor Mrs Jennifer McCracken CONCommittee Member, apologies
RM
Councillor Robert McLean CONCommittee Member, apologies
MM
Councillor Mrs Maureen Beadsley LABSubstitute
MB
Councillor Michael Brossard CONSubstitute, present as substitute
MA
Councillor Mrs Anne Shillcock LABSubstitute

All 24 on the meeting page

On this subject at Bracknell Forest

Search all
  1. Severe Weather Working Group ReportThis decision
  2. Overview & Scrutiny Commission Working Group Report - Response to Severe WeatherDecided

More from Bracknell Forest Environment, Culture and Communities Overview & Scrutiny Panel

All decisions
MeetingDecisionOutcome
10 Sep 2019 Minutes and Matters Arisingthat the Minutes of the Environment, Culture and Communities Overview and Scrutiny Panel held on 18 June 2019 be appr... Approved Open
18 Jun 2019 Election of ChairmanRESOLVED that Councillor Porter be elected Chairman of the Panel for the Municipal year 2019/20. Decided Open
18 Jun 2019 Appointment of Vice ChairmanRESOLVED that Councillor McKenzie-Boyle be appointed Vice-Chairman of the Panel for the Municipal year 2019/20. Decided Open
18 Jun 2019 Minutes and Matters ArisingRESOLVED : that the Minutes of the Environment, Culture and Communities Overview & Scrutiny Panel held on 3 July 2019... Approved Open
18 Jun 2019 Quarterly Service Report (QSR)It was agreed that due to questions being submitted on the day officers would respond to the questions following the ... Agreed Open