RESOLVED that i n the event of the Section 106 obligations not being completed by 30 July 2010, the Head of Development Management be authorised to refuse the application for the following reason: 01 The proposed development would unacceptably increase the pressure on highways and transportation infrastructure, public open space facilities, and the Thames Basin Heaths Special Protection Area. In the absence of a planning obligation in terms that are satisfactory to the Local Planning Authority, and which secure contributions towards integrated transport and highway safety measures, open space facilities and mitigation measures for the SPA , the proposal is contrary to Policy CC7, NRM6 of the South East Plan, Policies EN3, R5 and M4of the Bracknell Forest Borough Local Plan and CS6, CS8, CS14 and CS24 of the Core Strategy Development Plan Document and to Supplementary Planning Document Limiting the Impact of Development (adopted July 2007).β
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
PLANNING APPLICATION 09/00664/FUL LAND WEST OF WOKINGHAM ROAD, WOKINGHAM ROAD, SANDHURST, BERKSHIRE.
Director of Environment, Culture and Communities
1 PURPOSE OF DECISION
1.1The Committee of 20 May 2010 resolved to approve Planning Application 09/00664/FUL for the Change of use of land to use as a residential site for 3 Caravans (2 of which could be static) including hard standings and erection of an amenity block at Land West of Wokingham Road, Wokingham Road, Sandhurst, Berkshire.
1.2The alternative recommendation to refuse the application for not completing the S106 planning obligations by the 30 June 2010 omitted reference to include the lack of avoidance mitigation in respect of the SPA within the grounds for refusal. It is also considered necessary to extend the period required for the satisfactory completion of the S106 planning obligations.
2 RECOMMENDATION(S)
2.1The committee are requested to agree the following amended reason for refusal that also extends the time to complete the s106 obligation.
βIn the event of the s106 obligation(s) not being completed by 30 July 2010, the Head of Development Management be authorised to refuse the application on the grounds of:
The proposed development would unacceptably increase the pressure on highways and transportation infrastructure, public open space facilities, and the Thames Basin Heaths Special Protection Area. In the absence of a planning obligation in terms that are satisfactory to the Local Planning Authority, and which secure contributions towards integrated transport and highway safety measures, open space facilities and mitigation measures for the SPA, the proposal is contrary to Policy CC7, NRM6 of the South East Plan, Policies EN3, R5 and M4 of the Bracknell Forest Borough Local Plan and CS6, CS8, CS14 and CS24 of the Core Strategy Development Plan Document and to Supplementary Planning Document Limiting the Impact of Development (adopted July 2007).β
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.