RESOLVED that 1 An equity share scheme to enable first time buyers to buy a home is established in Bracknell Forest. 2 Subject to the decision above, £1 million is allocated from the existing housing capital programme to support the equity share scheme in 2010/11 to fund a maximum of 20 equity shares in this financial year. 3 The delivery of the equity share scheme is managed externally from the Council. 4 The revised housing strategy programme of spend as set out in Appendix A to the report be agreed.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That an equity share scheme to enable first time buyers to buy a home is established in Bracknell Forest.
2.2That, subject to the decision at 2.1, £1 million is allocated from the existing housing capital programme to support the equity share scheme in 2010/11 to fund a maximum of 20 equity shares in this financial year.
2.3That the delivery of the equity share scheme is managed externally from the Council.
2.4That the revised housing strategy programme of spend as set out in Appendix A.
Reasons for recommendations
3.1Executive agreed the housing strategy spending programme in conjunction with the housing strategy in July 2009. There were a number of schemes within the programme that have not taken place either because of the condition of the residential property market or the improved performance of the Council in terms of homeless prevention.
3.2The Council had agreed to allocate £100,000 in 20019/10 to a home loan scheme. The basis of the scheme was to provide a loan with a five year repayment holiday to act as a deposit for those households who wished to purchase a home due to the increased demands from lending institutions. It was found the lending institutions would still require a substantial deposit even after the provision of the home loan and as such the product has not been taken up.
3.3Secondly, the Council allocated over £1million in 2009/10 to finance the purchase of land for residential development. Property services have been unable to identify any opportunities that represent good value for money for the Council in the current market. Very little property currently on the market with developers holding on waiting for improvement in market conditions before they intend to sell. What does come to the market can command a premium due scarcity value. It is recommended that this approach is not continued and alternatively an equity share scheme is established.
3.4The Council agreed to establish a project to purchase properties to rent to homeless households, the temporary to permanent scheme and allocated £250,000 in 2009/10. The intention of the scheme was that properties would be purchased to replace the properties that the Council leased. One property was purchased in 2009/10 but due to the improved performance of the Council in terms of homeless prevention it has not been necessary to replace the leased properties that have been given up.
Alternative options considered
4.1The Council’s housing strategy programmes are funded by the proceeds of the stock transfer. The Council committed to invest £17.250 million and deliver at least 250 affordable housing units. Therefore, the programmes have been recommended to address that target.
4.2The Council could continue with the current programmes. However, the current state of the residential property market means that funding for the supply of new housing is likely to remain unused. The market conditions lend themselves to promoting a product that provides support so that households can purchase a home taking advantage of the competitive pricing of property at the moment. Hence, the recommendation to establish equity share scheme which will provide households the financial support to buy a home of their choice.
4.3To continue with the temporary to permanent scheme runs the risk of the Council owning property with no homeless households to take up occupation and thus losing rent. Therefore, it is recommended to discontinue the scheme at this time and look to finance permanent affordable housing instead.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.