Provision of Highway Depot

Decided Executive 1 paper

Executive decided this item on Tuesday 14 September 2010. Below is the council's own wording, with the papers it was decided on.

Item67a

Resolved

RESOLVED that the Council make provision for £425k from capital funds in the current fiscal year to enable works to the Lorry Park and the Depot to be completed by the end of March 2011.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendation

2.1That the Council make provision for £425k from capital funds in the current fiscal year to enable works to the Lorry Park and the Depot to be completed by the end of March 2011.

Reasons for recommendation

3.1Highway maintenance is a mandatory function of the Council. Without depot facilities including a salt barn, the Council would fail in its legal duty. The contractor has tried to find alternative local sites but has been unable to do so. Surrey County Council requires the full use of the Bagshot site from April 2011. The salt barn needs to be provided as soon as possible to enable the stocks of salt in time for the winter season starting in October 2011.

3.2Although the possibility that Ringway may not have been asked to tender for the new Surrey contract was known, it was not felt prudent to allocate resources in the 2010-11 capital programme due to the uncertainty of the tender outcome.

Alternative options considered

4.1The possibility of providing all such facilities on the existing depot site was considered but dismissed on grounds of cost. To do so requires a substantial amount of demolition work and loss of rental income from third party users. The Lorry Park is not big enough. Wokingham DC has leased its depot site to its waste collection contractors and its highways contractor and there is no available space there.

5 BACKGROUND INFORMATION

5.1Ringway provide a range of services under contract to this Council in respect of both the highway and street cleansing needs. The highway works include winter maintenance and the service is operated mainly from the Surrey County Council site in Bagshot. A small element of the contract relies on the use of a temporary site in Market Street. The street cleansing function operates from the Council's depot in Downshire Way. The contract with Ringway runs until 30 September 2014. At this time the contract will have to be retendered.

5.2Highway maintenance and street cleansing are mandatory functions for the Council and over the past year Ringway has been looking for suitable local sites in case their contract with Surrey was terminated, but without success. If they had found a site the costs would have been passed on to the Council, these being estimated at £250,000 per annum arising from lease costs, business rates and the need to write down any investment in terms of buildings and set up costs over a very short term. Therefore it is in the Council's best interests to effect a solution if it can. Doing so also gives greater certainty to future tendering processes as the availability or otherwise of a local depot can be a make or break factor for a would-be bidder.

5.3Having considered all the options the most cost effective solution is to split the function between the current lorry park and the depot. The lorry park is of a size that would provide for a salt barn and the heavy works elements of the highway contract. The depot would provide for the core management and minor works teams. Street Cleansing would not be affected, nor would the operations of our refuse collection contractor or landscape team. The Market Street site would no longer be needed which is an advantage to the Council. Splitting the operation in this way avoids expensive demolition works to the depot and there is minimal consequence to existing tenants.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Provision of Highway DepotReport 34 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
PB
Councillor Paul Bettison CONChair, apologies
AW
Councillor Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, apologies
AK
Councillor Alan Kendall CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
JD
Jemma DurkanClerk, expected

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies