Reallocation of Housing Capital Funding to Procure Temporary to Permanent Housing

Approved Executive 1 paper

Executive approved this item on Tuesday 18 January 2011. Below is the council's own wording, with the papers it was decided on.

Item80c

Resolved

RESOLVED that 1 A supplementary capital estimate of £560,000 to fund a temporary to permanent scheme in 2010/11 be recommended for approval by Full Council 2 The scheme to enable a new build affordable rented scheme for £150,000 be deleted from the 2010/11 capital programme and that the scheme to make best use of the Council’s housing stock be reduced by £120,000 in 2010/11 capital programme. 3 Subject to the above decisions, the funding for temporary to permanent housing be used to finance the purchase of 2 x two bedroom properties and 1 x three bedroom property. 4 The rents for the properties are set at the relevant Local Housing Allowance (LHA) rates.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

2.1That a supplementary capital estimate of £560,000 is recommended for approval by the Full Council to fund a temporary to permanent scheme in 2010/11.

2.2That the scheme to enable a new build affordable rented scheme for £150,000 is deleted from the 2010/11 capital programme and that the scheme to make best use of the Council’s housing stock is reduced by £120,000 in 2010/11 capital programme.

2.3Subject to decisions at 2.1 and 2.2 the funding for temporary to permanent housing is used to finance the purchase of 2 x two bedroom properties and 1 x three bedroom property.

2.4That the rents for the properties are set at the relevant Local Housing Allowance (LHA) rates.

Reasons for recommendations

3.1At present there has been an increase in demand from homeless families. There are currently five households where the Council has agreed it has a homeless duty to provide temporary accommodation that are living in unsuitable accommodation. At the time of writing the Council has found it difficult to access private rented sector properties to provide temporary accommodation for those households. It has been possible to avoid the use of bed and breakfast accommodation for all but short emergency situations to date. The Council’s Temporary to Permanent Scheme was set up so that the Council would purchase properties to provide accommodation for homeless households and then give up the properties that it leases for that purpose. Executive agreed in June 2009 to set up the Temporary to Permanent Scheme and that, subject to homeless demand, to acquire further properties and relinquish leases where possible, hence the production of this report.

3.2The Housing Capital Programme included a provision to fund £150,000 towards a new build affordable rented scheme in the Borough. Since the Council approved this scheme the Homes and Communities agency (HCA) has decided not to partner with the Council. Moreover, the conditions of the funding offered from the HCA have also changed. The Council is now placed in a position where it may be required to provide additional funding for the scheme to proceed. Given this situation and the fact that the timing of the scheme is not critical this scheme can be deleted from the current years capital programme.

3.3The Housing Capital Programme also included a sum of £160,000 to fund adaptation of a Bracknell Forest Homes property to meet the specific needs of a disabled family. Bracknell Forest Homes have advised that they are only likely to require £40,000 of the allocated sum in this financial year. As such, a further £120,000 can be deleted from the current year’s capital programme. The balance of the funding required for the agreed scheme with Bracknell Forest homes can be met from the provision already made in 2011/12.

3.3It is estimated to cost £560,000 in total to purchase the three properties hence the recommendation to adopt a capital estimate for that amount. As capital spend on two schemes in the current financial year is recommended to be postponed the net cost of the capital estimate is £290,000 in this financial year.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reallocation of Housing Capital Funding to Procure Temporary to Permanent HousingReport 57 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
PB
Councillor Paul Bettison CONChair, apologies
AW
Councillor Alan Ward CONVice-Chair, present
MM
Councillor Mrs Mary Ballin CONCommittee Member, present
DG
Councillor Dr Gareth Barnard CONCommittee Member, present
DB
Councillor Dale Birch CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
AK
Councillor Alan Kendall CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
JD
Jemma DurkanClerk, expected

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies