RESOLVED that 1 A supplementary capital estimate of £560,000 to fund a temporary to permanent scheme in 2010/11 be recommended for approval by Full Council 2 The scheme to enable a new build affordable rented scheme for £150,000 be deleted from the 2010/11 capital programme and that the scheme to make best use of the Council’s housing stock be reduced by £120,000 in 2010/11 capital programme. 3 Subject to the above decisions, the funding for temporary to permanent housing be used to finance the purchase of 2 x two bedroom properties and 1 x three bedroom property. 4 The rents for the properties are set at the relevant Local Housing Allowance (LHA) rates.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That a supplementary capital estimate of £560,000 is recommended for approval by the Full Council to fund a temporary to permanent scheme in 2010/11.
2.2That the scheme to enable a new build affordable rented scheme for £150,000 is deleted from the 2010/11 capital programme and that the scheme to make best use of the Council’s housing stock is reduced by £120,000 in 2010/11 capital programme.
2.3Subject to decisions at 2.1 and 2.2 the funding for temporary to permanent housing is used to finance the purchase of 2 x two bedroom properties and 1 x three bedroom property.
2.4That the rents for the properties are set at the relevant Local Housing Allowance (LHA) rates.
Reasons for recommendations
3.1At present there has been an increase in demand from homeless families. There are currently five households where the Council has agreed it has a homeless duty to provide temporary accommodation that are living in unsuitable accommodation. At the time of writing the Council has found it difficult to access private rented sector properties to provide temporary accommodation for those households. It has been possible to avoid the use of bed and breakfast accommodation for all but short emergency situations to date. The Council’s Temporary to Permanent Scheme was set up so that the Council would purchase properties to provide accommodation for homeless households and then give up the properties that it leases for that purpose. Executive agreed in June 2009 to set up the Temporary to Permanent Scheme and that, subject to homeless demand, to acquire further properties and relinquish leases where possible, hence the production of this report.
3.2The Housing Capital Programme included a provision to fund £150,000 towards a new build affordable rented scheme in the Borough. Since the Council approved this scheme the Homes and Communities agency (HCA) has decided not to partner with the Council. Moreover, the conditions of the funding offered from the HCA have also changed. The Council is now placed in a position where it may be required to provide additional funding for the scheme to proceed. Given this situation and the fact that the timing of the scheme is not critical this scheme can be deleted from the current years capital programme.
3.3The Housing Capital Programme also included a sum of £160,000 to fund adaptation of a Bracknell Forest Homes property to meet the specific needs of a disabled family. Bracknell Forest Homes have advised that they are only likely to require £40,000 of the allocated sum in this financial year. As such, a further £120,000 can be deleted from the current year’s capital programme. The balance of the funding required for the agreed scheme with Bracknell Forest homes can be met from the provision already made in 2011/12.
3.3It is estimated to cost £560,000 in total to purchase the three properties hence the recommendation to adopt a capital estimate for that amount. As capital spend on two schemes in the current financial year is recommended to be postponed the net cost of the capital estimate is £290,000 in this financial year.
Alternative options considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.