It was RESOLVED that: i) approval be given to the deletion of the posts identified in Exempt Appendix B, subject to any redeployment opportunities or “buy back” arrangements from schools which were offered by the termination date of 31 March 2011 (or otherwise where indicated in the Appendix) ii) the postholders be declared redundant in accordance with the terms set out in Appendix B with the costs being met from the Structural Changes Fund.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That approval is given to the deletion of the posts identified in Exempt Appendix B, subject to any redeployment opportunities or “buy back” arrangements from schools which are offered by the termination date of 31 March 2011 (or otherwise where indicated in the Appendix).
2.2That the postholders are declared redundant in accordance with the terms set out in Appendix B with the costs being met from the Structural Changes Fund.
3 SUPPORTING INFORMATION
3.1At its meeting on 14 December 2010, the Executive considered the overall position facing the Council in setting a budget for 2011/12. At the time the Executive agenda was published, the Provisional Local Government Financial Settlement had not been announced and therefore the report was based on a number of assumptions regarding government funding. However, the report explained that the proposals contained in the report represented a ‘core budget package’ that would be needed under almost all funding scenarios. As the provisional settlement was published 24 hours before the meeting, Members were also informed that further savings were likely to be required. In this broad context, the Executive published its draft budget proposals and these have been consulted on with the public, the Council’s Overview & Scrutiny Commission and Scrutiny Panels, with town and parish councils, business ratepayers, the Schools Forum, the Over 50 Forum and voluntary organisations.
The 2011/12 settlement was unprecedented both in terms of its complexity and in the scale of funding changes and reductions. The complexity arises because the funding previously provided through almost all specific grants and the Area Based Grant has either been:
• transferred into a new funding stream; • reduced; • transferred and reduced, or • cut completely.
Other key features of the settlement include a reduction in the number of specific grants, from over 80 to less than 10 alongside the “unringfencing” of most of these grants. In practice this means that although the government may allocate funding for a particular purpose, the Council is at liberty to use it in a way which it considers most appropriate for its local need.
Overall, the actual settlement proved to be more challenging than the worst case assumed in the “core budget package” proposals published on 14 December 2010. The impact of the provisional settlement relative to the draft budget proposals has meant a net reduction in funding of £3.189 million.
Inevitably in the two months since the Executive published the draft budget proposals more information became available, in particular the release of the Local Government Finance Settlement and the need to find further savings to meet an additional funding gap of £1.869m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Policy review and 7 HR policy updatesRESOLVED that the six HR policies presented, excluding the Organisational Change Policy which had been withdrawn for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.