RESOLVED that the minutes of the meeting of the Board held on 7 July 2011 be approved as a correct record and signed by the Chairman subject to the addition of the following to minute 39: 4 An analysis be undertaken in order to gain a better understanding of the potential benefits and disadvantages within the partnership.” It was agreed that Councillor McCracken and the Project Director would meet to agree what was required and how best to progress the work. Arising on the minutes, the officers also answered a number of questions from the Board on progress since the last meeting on issues which would not otherwise be considered during the meeting. The main points made were that: · The contractor was proposing to make changes to the MRF themselves to increase performance. · Officers would approach the Contractor with a request for a proposal in relation to tetrapaks. · There had been no progress since the last meeting on savings proposals. · A date for a further session to follow-up the actions proposed at the waste management workshops held late in 2010 would be arranged shortly.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Present: Bracknell Forest Borough Council Councillor Iain McCracken Councillor Mrs Dorothy Hayes MBE
Reading Borough Council Councillor Paul Gittings
Wokingham District Council Councillor Gary Cowan Councillor Rob Stanton
Officers Pete Baveystock, Wokingham Borough Council Pete Thompson, Reading Borough Council Oliver Burt, re3 Project Manager Janet Dowlman, Bracknell Forest Council Dave Fisher, Reading Borough Council Kevin Holyer, Reading Borough Council Steve Loudoun, Bracknell Forest Council Mark Moon, re3 Project Director Claire Armstrong, Reading Borough Council Kevin Parker, Reading Borough Council
Apologies for absence were received from: Councillor Eden
34. Declarations of Interest There were no declarations of interest.
35. Appointment of Vice-Chairman RESOLVED that Councillor Gittings be elected Vice-Chairman of the Board.
36. Minutes of the Meeting of the Joint Waste Disposal Board RESOLVED that the minutes of the meeting of the Joint Waste Disposal Board held on 16 March 2011, be approved as a correct record and signed by the Chairman.
37. Urgent Items of Business There were no urgent items of business.
38. Progress Report The Board considered a report informing of progress since the last meeting on 16 March 2011. The report covered:
• Operations and Facilities – A proposal by the contractor was being developed on amendments to the MRF to increase performance. This would lead to more recycling which in turn create an increase in income for the Contractor and potentially the councils.
• Retail Outlet Replacement – Since the arrangement began in March 2011 items retrieved from the re3 HWRC’s have raised £6,000 for Sue Ryder Care.
It was noted that a press release with correct information would be sent out on this matter
• Community repaint – A proposal had been received from Green Machine on managing unwanted paint through the HWRC’s. The proposal was to divert for community re-use across the re3 area 40% of paint currently received for a payment of 30% of the total annual cost. The savings for the councils would be the equivalent to 10% of the total cost. Since this proposal the Contractor has also submitted a scheme to process all the paint at one of their own facilities.
WRG were encouraged to propose their business case at the earliest opportunity. If no proposal was made before the next JWDB meeting then the existing Green Machine proposal would be given preference. (Action: Oliver Burt)
• Haulage Contract Re-let – The re3 project Team had been working with the contractor to follow the process for the Haulage Market Testing to seek to minimise any increase in costs. Progress was being made and the new haulage arrangements were due to commence in December 2011.
• Savings Proposals – Discussions had taken place with the Contractor in relation to savings and income generation and as a result of this two options had been considered.
The Board considered the first proposal for savings regarding two members of staff who delivered the education and waste minimisations functions of the contract. As a result of staff turnover these roles were currently vacant which enabled the re3 councils an opportunity to consider the value of this service within the re3 partnership. The Board agreed that the savings could be made by utilising the approach to the service and facilitating provisions within councils departments. A budget of £50,000 would be retained for education and waste minimisation activities across the re3 area and the remainder would be taken as a saving via the appropriate contractual mechanism.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.