re3 Waste PFI Project - Progress Report

Noted Committee 1 paper

Joint Waste Disposal Board noted this item on Wednesday 14 December 2011. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

RESOLVED that 1 Progress made since the last meeting on 20 September 2011 be noted. 2 A single-axle trailer policy at the Household Waste Recycling Centres be agreed.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Joint Waste Disposal Board

Recommendations

2.1To note progress made since the last meeting on 20th September 2011.

2.2That Members consider whether they would like officers to review the current access controls as they relate to the use of trailers.

3. SUPPORTING INFORMATION

Operations and Facilities

3.1The Contractor is in the process of installing optical fire detection within the Smallmead MRF.

3.2The benefit of this system is that it identifies a fire itself rather than awaiting the product of the fire (smoke or heat) to be detected.

3.3This development is part of a process being undertaken by the Contractor, with support from the insurers (Zurich Municipal) and International Fire Consultants (IFC) Ltd, to improve the fire detection and protection system. The original system that was provided by the Engineering Procurement Construction (EPC) contract between the Contractor and their selected sub-contractor has not proved to be acceptable.

3.4Officers from the re3 Project Team and Bracknell Forest Borough Council have been in discussion with the Contractor about the requirement, with the planning permission for Longshot Lane, for appropriate traffic management systems.

3.5While a system was proposed in the planning application, it has not yet been utilised according to the permission given. The Contractor has sought approval from the WRG Board for changes to be made at Longshot Lane such that a permanent, two- lane access is created for users of the Household Waste Recycling Centre (HWRC).

3.6Furthermore, Officers are requiring the reinstatement of a webcam for use by patrons planning a visit to Longshot Lane.

3.7Following the aborted procurement process earlier in 2011, The Contractor has now appointed a haulier for the next five years of the Contract.

3.8The exact impact on the total cost of ‘internal’ contractual haulage is hard to estimate but it should result in a small saving to the councils against the current cost. At a time of rising costs that is a positive outcome.

3.9The successful bidder is a company called Fred Sherwood and Sons (Transport) Ltd. 3.10 The previous haulage contract, covering the first five years of the PFI contact and which was held by BP McKeefry Ltd, came to an end at midnight on December 3rd 2011.

Access Arrangements at Household Waste Recycling Centre’s (HWRC’s)

3.11Members have previously received reports on the subject of access controls at both Smallmead and Longshot Lane HWRC’s. Access controls have been a feature at both sites for some time and are quite normal at sites around the country.

3.12The controls take a number of forms. There is a height-barrier at both sites and there are restrictions on the amount a householder can bring in for some types of waste. A further control relates to the use of trailers.

3.13Initially, the control related to the length of trailer and was set at 6 feet. The length being set at a scale which was manageable in the facility (for safe parking and manoeuvring) and also that corresponded with a ‘household’ sized amount of waste.

3.14This proved impractical, however, because of the wide range of sizes of trailer available. A householder with a slightly larger trailer than the limit would feel harshly treated and if any lee-way was applied it could soon have made the whole affair very tricky to manage consistently.

3.15As a result, the control was amended to accept single-axle trailers only. This was decided-upon because it was easier to identify compliance or non-compliance with the standard and still took account of the original reasoning (as described at 3.12 above).

3.16During 2010/11 the partnership received 4 complaints about the policy of trailer control. The facilities cater for up to 6,000 visits per week.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
re3 Waste PFI Project: Progress ReportReport 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
MD
Councillor Mrs Dorothy Hayes MBE CONBracknell Forest Councillor, present
IM
Councillor Iain McCracken CONBracknell Forest Councillor, apologies
PG
Councillor Paul Gittings LABReading Borough Council, present
RE
Councillor Rachel EdenReading Borough Council, present
GC
Councillor Gary CowanWokingham Borough Council, present
RS
Councillor Rob StantonWokingham Borough Council, present
PB
Pete BaveystockOfficer, present
PT
Pete ThompsonOfficer, present
OB
Oliver BurtOfficer, present
JD
Janet DowlmanOfficer, present
DF
Dave FisherOfficer, present
KH
Kevin HolyerOfficer, present

All 15 on the meeting page

On this subject at Bracknell Forest

Search all
  1. re3 Waste PFI Project - Progress ReportThis decision
  2. Audit Report - Waste PFI Review 2015Noted
  3. Report on the Project Initiation Document for Review of Years Five to Ten of re3 Joint Waste PFIApproved
  4. Audit of re3 Joint Waste PFIApproved
  5. Audits of the re3 Joint Waste PFIDecided
  6. RE3 Waste PFI Project - Confidential ReportAgreed

More from Bracknell Forest Joint Waste Disposal Board

All decisions
MeetingDecisionOutcome
11 Jun 2026 Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. Decided Open
11 Jun 2026 re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... Noted Open
11 Jun 2026 re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... Approved Open
11 Jun 2026 re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. Noted Open