RESOLVED that taking into account the full equality impact assessment appended to the Borough Treasurer’s report, the Executive: Approve the revised Commitment Budget for 2013/14 to 2015/16 at Annexe A of the Borough Treasurer’s report Agree the draft budget proposals for 2013/14 as the basis for consultation with the Overview & Scrutiny Commission and other interested parties or individuals. Agree the Treasury Management Strategy and associated documents at Annexe E of the Borough Treasurer’s report and request that the Governance and Audit Committee review each of the key elements. Agree that the 2013-14 Schools Budget be set at the estimated level of Dedicated Schools Grant income, with the Executive Member for Children, Young People and Learning authorised to agree budgets for schools and services centrally managed by the Council. Approve the virements relating to the 2012/13 budget as set out in Annexes F and G of the Borough Treasurer’s report and recommend those over £0.100m for approval by Council.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Under the Council’s constitution, the Executive is required to consult on its detailed budget proposals with the Council’s Overview & Scrutiny Commission and any other interested parties or individuals for a period of at least six weeks. This report summarises the current position on the Council’s budget preparations for 2013/14.
1.2The 2013/14 budget process has been characterised by unprecedented levels of uncertainty around the level of central government support and proposed changes to the funding regime (e.g. localisation of business rates). At the time the Executive agenda was published the Provisional Local Government Financial Settlement had not been announced and is not expected until late December. Therefore, in the absence of the provisional settlement, the report is based on a number of assumptions regarding government funding.
1.3All comments received on these budget proposals will be submitted to the Executive on 13 February along with details of the final finance settlement. This will allow the Executive to determine its final budget package and recommend the appropriate Council Tax level to Council, who will formally approve the 2013/14 budget and Council Tax on 27 February 2013.
Recommendations
That the Executive:
2.1Approve the revised Commitment Budget for 2013/14 to 2015/16 at Annexe A;
2.2Agree the draft budget proposals for 2013/14 as the basis for consultation with the Overview & Scrutiny Commission and other interested parties or individuals.
2.3Agree the Treasury Management Strategy and associated documents at Annexe E and request that the Governance and Audit Committee review each of the key elements.
2.4Agree that the 2013-14 Schools Budget be set at the estimated level of Dedicated Schools Grant income, with the Executive Member for Children, Young People and Learning authorised to agree budgets for schools and services centrally managed by the Council.
2.5Approve the virements relating to the 2012/13 budget as set out in Annexes F and G and recommend those over £0.100m for approval by Council. Unrestricted
Reasons for recommendations
3.1The recommendations are designed to allow the Executive to consult on its draft budget proposals for 2013/14 as required by the Local Government Act 2003.
Alternative options considered
4.1The range of options being considered is included in the report and its Annexes.
SUPPORTING INFORMATION
5 COMMITMENT BUDGET 2013/14 – 2015/16
5.1Initial preparations for the 2013/14 budget have focussed on the Council’s Commitment Budget for 2013/14 – 2015/16. This brings together the Council’s existing expenditure plans, taking account of approved commitments and the ongoing effects of service developments and efficiencies that were agreed when the 2012/13 budget was set.
5.2A number of changes are proposed to the Commitment Budget since it was last considered by the Executive in July and are reflected in the summary in Table 1. The most significant are set out below:
• Decreases in projected landfill tax and waste disposal costs (-£0.417m).
• The Council will now be able to make a full pre-payment on its pension fund contributions for a further year and thus earn a higher discount than could be earned through its own investment opportunities (-£0.200m).
• Increases in the projected Minimum Revenue Provision (£0.405m). This is based on new council financed capital spend divided by the resulting assets life. The latest projection incorporates the latest forecast for capital spend and receipts.
5.3Taking account of these changes, Table 1 summarises the position and shows that base expenditure (excluding schools) is planned to decrease by £0.749m to £71.581m next year, before consideration is given to allowances for inflation and the budget proposals identified by individual Departments in 2013/14. The commitment budget is shown in more detail in Annexe A. Unrestricted
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies