RESOLVED that the Schools Forum: NOTED the budget variances being forecast on the 2013-14 Schools Budget that in total aggregate to a net under spending of £0.251m, which increased to £0.646m when unallocated year end balances were also taken into account (paragraph 5.6); RECOMMENDED to the Executive Member that the required budget transfers between Pupil behaviour, SEN provisions and support services and Education out of school were AGREED (paragraph 5.3); ... view the full minutes text for item 7.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of this report is for the Schools Forum to:
i. Endorse budget transfers proposed for 2013-14; ii. Receive an update the 2013-14 forecast budget monitoring position for the Schools Budget; iii. Agree loan requests received from schools, and; iv. Agree changes to the criteria for in-year budget allocations to schools experiencing significant growth in pupil numbers.
Recommendations
That the Schools Forum:
2.1NOTES the budget variances being forecast on the 2013-14 Schools Budget that in total aggregate to a net under spending of £0.251m, which increases to £0.646m when unallocated year end balances are also taken into account (paragraph 5.6);
2.2RECOMMENDS to the Executive Member that the required budget transfers between Pupil behaviour, SEN provisions and support services and Education out of school are AGREED (paragraph 5.3);
2.3AGREES that due to on-going uncertainties, the use of any under spend forecast for 2013-14 is considered in January 2014 when the 2014-15 budget is agreed (paragraph 5.9);
2.4AGREES the loan requests for Wildmoor Heath Primary and Sandhurst Secondary Schools (paragraph 5.11);
2.5AGREES the updated criteria for in-year budget allocations to schools experiencing significant growth in pupil numbers, as set out in Annex B (paragraph 5.16).
Reasons for recommendations
3.1It is appropriate for the Schools Forum to be aware of, and where relevant, comment on these financial matters. Unrestricted
Alternative options considered
4.1Where relevant, these are set out in the supporting information.
5 SUPPORTING INFORMATION
2013-14 Monitoring of the Schools Budget
Approved budget
5.1Based on recommendations of the Schools Forum, in March 2013, the Executive Member for Children, Young People and Learning agreed a Schools Budget for 2013-14. Subsequent to this initial approval, at the last Forum meeting in June it was reported that the level of Dedicated Schools Grant (DSG) to be received from the Department for Education (DfE) had been adjusted so that a deduction of £3.503m would be made to pay Ranelagh Academy the budget share due from the BF Funding Formula, with a further net deduction of £0.371m for transferred Special Educational Needs (SEN) funding responsibilities, making a net reduction in funding of £3.874m and a revised DSG income of £74.991m.
5.2To ensure budgets correctly reflect anticipated spending requirements, adjustments would be made to the areas of the accounts that these changes relate to. As the reduction in DSG is in response to reduced funding responsibilities, these changes should not have a significant financial impact on the Schools Budget.
5.3In reviewing the budget, it has become apparent that £0.050m of costs currently charged to Pupil Behaviour relates to management and staff time directed at other targeted services and should be recorded as £0.030m in SEN provisions and support services and £0.020m in Education out of school. Provisions within the Council’s Financial Regulations require the Executive Member to agree a relevant budget transfer, and the Forum is recommended to propose that the change is agreed.
Forecast budget variances
5.4As part of the Council’s Financial Regulations, the Schools Budget is subject to monthly budget monitoring. This involves forecasting likely expenditure and income through to the end of the year, identification of reasons for variations against original budgets, and where relevant, setting out options for management action. This process allows for a forecast year end level of balances to be calculated.
5.5It is appropriate for the Forum to be aware of the current forecast year end balance as this may need to be taken into account when the 2014-15 budget is agreed. It is also possible that a number of variances identified this year will be on-going, and will therefore need to be addressed in next year’s budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.