RESOLVED that Bracknell Forest Council introduces a Permit Scheme as set out in the report, subject to a successful consultation outcome and a successful application to the Department for Transport (DfT) be agreed. Specific details of the Draft consultation Permit Scheme be delegated to the Chief Officer: Planning and Transport in consultation with the Executive Member for Planning and Transport be agreed.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
IMPLEMENTATING A PERMIT SCHEME FOR BRACKNELL FOREST
Background Report
Introduction
1. It is estimated that currently over 10,000 excavations take place annually in the Borough to enable various types of road and street works to be carried out. These excavations can cause considerable inconvenience to residents and businesses and substantial delays to traffic. Effective co-ordination is therefore essential to minimize disruption whilst allowing works promoters the necessary time and space to complete their work.
2. Highway Authorities have a duty to co-ordinate all works on the highway under the New Roads & Street Works Act 1991 (NRSWA). Under the current regulations, Statutory Undertakers (SU) are only required to notify the Highway Authority when they need to undertake repairs or improvements to their apparatus. Other than co-ordinate their works with other SUs and the Council’s own schemes, the NRSWA provides limited powers to the Council as highway authority to control the way in which the works are completed. For example under a notification process the Council has limited control of when works start and finish, which can also hinder our capability to inspect works in progress, and also limits opportunities to promote integration or joint working.
3. The Traffic Management Act 2004 (TMA) placed a new Network Management Duty on all Highway Authorities in England. This Duty is defined in Section 16(1) of the TMA:
‘It is the duty of a local traffic authority to manage their road network with a view to achieving, so far as may be reasonably practicable having regard to their other obligations, policies and objective, the following objectives:
i) Securing the expeditious movement of traffic on the authority’s road network; and,
ii) Facilitating the expeditious movement of traffic on road networks for which another authority is the traffic authority.’
4. Benefits have already been seen from Permit Schemes which are already in operation across London and in Kent County Council. The report on the first year of operation of the London Permit Scheme (LoPS), which as ‘Tranche 1’ was operated by 17 London Boroughs and Transport for London (TfL) highlighted ;
a. An increase of 147% in the number of recorded days of disruption
1 saved through collaborative working, from 726 days to 1793 days
b. An increased discipline amongst Highway Authorities in recording their own works, leading to a 237% increase in formally recorded works, providing more opportunity for collaboration and better public information through the ‘Londonworks’ website.
c. A 17% reduction in the volume of works undertaken (compared against a 7% reduction in non-permitting London Authorities at that time)
d. Better quality of works information available to make considered coordination decisions
e. Delivery of a large percentage of the expected benefits for average journey time and journey reliability times
5 The success of LoPS has seen other Boroughs join the scheme and the final ‘Tranche 4’ of LoPS will mean that all London Boroughs operate LoPS .
6 The Kent CC Permit Scheme was the first scheme introduced outside of London, commencing shortly after LoPS. Benefits outlined in the first year of operation included;
a. A 26% reduction in complaints about ‘congestion and Coordination
b. A significant reduction in the volume of ‘street works enquiries’ from the public
c. In excess of 1500 total number of days saved as a result of collaborative working (monetised benefit to travelling public of c£1m)
d. 5% increase in the number of ‘first time’ reinstatements (75% to 80%)
e. Significant cultural change in respect of pre-planning and coordination of works – especially of Kent CC’s own highways works, limiting disruption and providing safer road works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.