RESOLVED that the Schools Forum requested the following comment be presented in respect of the 2014/15 budget proposals of the Executive for the Children, Young People and Learning Department on: The revenue budget (Annexes B and C), and The capital programme (Annex D). The Schools Forum were concerned regarding all of the proposed budget cuts in services in relation to Children, Young People and Learning and the potential impact on education and children and young people in Bracknell Forest, but were particularly concerned with budget cuts affecting the most vulnerable children, including the Early Years Service, and looked after children. The Forum noted that economies needed to be made but were concerned about the impact on frontline services at the Borough Council.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Under the Council’s constitution, the Executive is required to consult on its detailed budget proposals with the Council’s Overview & Scrutiny Commission and any other interested parties or individuals for a period of at least six weeks. This report summarises the current position on the Council’s budget preparations for 2014/15.
1.2At the time the Executive agenda was published the Provisional Local Government Financial Settlement had not been announced and is not expected until early January 2014. Therefore, in the absence of the Provisional Settlement, the report is based on a number of assumptions regarding government funding.
1.3All comments received on these budget proposals will be submitted to the Executive on 11 February along with details of the final Financial Settlement. This will allow the Executive to determine its final budget package and recommend the appropriate Council Tax level to Council, who will formally approve the 2014/15 budget and Council Tax on 26 February 2014.
1.4Whilst setting out the key budget issues facing the Council next year, his report to the Schools Forum focuses on the impact expected on the Children, Young People and Learning Department.
Recommendations
2.1That the Schools Forum comments on the 2014/15 budget proposals of the Executive for the Children, Young People and Learning Department in respect of:
i. The revenue budget (Annexes B and C), and ii. The capital programme (Annex D).
Reasons for recommendations
3.1The Executive seeks the views of the Schools Forum as an interested party on the 2014/15 budget proposals.
Alternative options considered
4.1The range of options being considered is included in the report and its Annexes. Unrestricted
5 SUPPORTING INFORMATION
Revenue Budget
Commitment budget 2014/15 – 2016/17
5.1Initial preparations for the 2014/15 budget have focussed on the Council’s Commitment Budget for 2014/15 – 2016/17. This brings together the Council’s existing expenditure plans, taking account of approved commitments and the ongoing effects of service developments and efficiencies that were agreed when the 2013/14 budget was set.
5.2The Commitment Budget was approved by the Executive in October and is summarised in Table 1. Table 1 shows that base expenditure (excluding schools) is planned to decrease by £1.288m to £83.951m next year, before consideration is given to allowances for inflation and the budget proposals identified by individual Departments in 2014/15.
Movements in Year: Chief Executive / Corporate Services 112 56 -70 Children, Young People and Learning (excluding -160 -5 -30 schools) Adult Social Care, Health and Housing -327 -10 0 Environment, Culture & Communities 97 151 72 Non Departmental / Common -1,010 0 775 Total Movements -1,288 192 747
Adjusted Base 83,951 84,143 84,890
5.3The most significant changes to the Commitment Budget include:
• The removal of one off items included in the 2013/14 budget, in particular the revenue contribution to the works at Time Square (-£1.100m), the Members’ Initiative Fund (-£0.420m) and the additional investment in dementia and long term conditions resulting from increased demand for rehabilitation and social care support (-£0.183m). • The revenue impact of the 2013/14 capital programme, including IT maintenance and support costs (£0.071m) and the minimum revenue provision (£0.262m), representing the annual amount of the capital investment repaid from revenue. • An increase in the employer’s contribution to the pension fund arising from the inclusion of non contractual overtime and additional hours for part time staff within pensionable pay (£0.180m) in accordance with the national scheme. Unrestricted
Provisional Local Government Finance Settlement 2014/15
National Perspective
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.