RESOLVED that the Executive: Agree the draft budget proposals for 2015/16 as the basis for consultation with the Overview & Scrutiny Commission and other interested parties or individuals. Agree the Treasury Management Strategy and associated documents at Annexe E of the Borough Treasurer’s report and request that the Governance and Audit Committee review each of the key elements. Agree that the 2015/16 Schools Budget be set at the estimated level of grant income plus any accumulated balances , with the Executive Member for Children, Young People and Learning authorised to make amendments and agree budgets for schools and services centrally managed by the Council. Approve the virements relating to the 2014/15 budget as set out in Annexes F and G of the Borough Treasurer’s report and recommend those that are over £0.100m for approval by Council.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Under the Council’s constitution, the Executive is required to consult on its detailed budget proposals with the Council’s Overview & Scrutiny Commission and any other interested parties or individuals for a period of at least six weeks. This report summarises the current position on the Council’s budget preparations for 2015/16.
1.2At the time the Executive agenda was published the Provisional Local Government Financial Settlement had not been announced and is not expected until late December 2014. Therefore, in the absence of the Provisional Settlement, the report is based on the indicative 2015/16 funding figures received in February 2014.
1.3All comments received on these budget proposals will be submitted to the Executive on 10 February along with details of the final Financial Settlement. This will allow the Executive to determine its final budget package and recommend the appropriate Council Tax level to Council, who will formally approve the 2015/16 budget and Council Tax on 25 February 2015.
Recommendations
That the Executive:
2.1Agree the draft budget proposals for 2015/16 as the basis for consultation with the Overview & Scrutiny Commission and other interested parties or individuals.
2.2Agree the Treasury Management Strategy and associated documents at Annexe E and request that the Governance and Audit Committee review each of the key elements.
2.3Agree that the 2015/16 Schools Budget be set at the estimated level of grant income plus any accumulated balances, with the Executive Member for Children, Young People and Learning authorised to make amendments and agree budgets for schools and services centrally managed by the Council.
2.4Approve the virements relating to the 2014/15 budget as set out in Annexes F and G and recommend those that are over £0.100m for approval by Council.
Reasons for recommendations
3.1The recommendations are designed to allow the Executive to consult on its draft budget proposals for 2015/16 as required by the Local Government Act 2003.
Alternative options considered
4.1The range of options being considered is included in the report and its Annexes. Unrestricted
SUPPORTING INFORMATION
5 COMMITMENT BUDGET 2015/16 – 2017/18
5.1Initial preparations for the 2015/16 budget have focussed on the Council’s Commitment Budget for 2015/16 – 2017/18. This brings together the Council’s existing expenditure plans, taking account of approved commitments and the ongoing effects of service developments and efficiencies that were agreed when the 2014/15 budget was set.
5.2A number of changes are proposed to the Commitment Budget since it was last considered by the Executive in July and are reflected in the summary in Table 1. The most significant are set out below:
The latest waste projections have indicated an increase in waste tonnages and a reduction in the amount being recycled. In addition, increases in landfill tax are now directly linked to RPI and will be reflected in the inflation calculation (£0.380m).
The Local Development Framework has required updating due to changes in National Policy, including those brought in through the National Planning Policy Framework. This has resulted in additional costs for technical work and studies and has changed the spend profile over the next three years compared to the previous estimate (£0.163m). The new programme has been formalised in the updated Local Development Scheme approved by the Executive.
Inclusion of the forecast recruitment and retention payments in Children’s Social Care agreed by the Employment Committee on the 18 June (£0.130m). The budget increase will be reviewed once the actual number of employees entitled to the payment has been established.
The projection for the Minimum Revenue Provision now incorporates the latest forecast for capital spend and receipts and the on-going under spend from 2014/15 (-£0.390m).
Inclusion of the savings from the Aiming High programme agreed by the Executive on 23 September (-£0.108m).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.